Submitted by / Soumis par:
Nancy Schepers, Deputy City Manager/Directrice municipale adjointe
Infrastructure Services and Community
Sustainability/
Services d’infrastructure et
Viabilité des collectivités
Ward/Quartier 5 – West Carleton Ward/Quartier 19 – Cumberland Ward/Quartier 20 – Osgoode Ward/Quartier 21 – Rideau-Goulbourn |
|
Ref N°: ACS2010-ICS-INF-0010 |
SUBJECT:
|
|
|
|
OBJET :
|
That Agriculture and Rural Affairs Committee receive this report for information
Que le Comité de l’agriculture et des affaires
rurales prenne connaissance du présent rapport.
At the 31 March 2008 meeting, the Agriculture and Rural Affairs Committee (ARAC) endorsed the following motion related to boundary roads:
WHEREAS, the conditions of our
boundary roads have been identified from residents of the east, west and south
on numerous occasions through public delegations at ARAC and RIAC as well as
through written correspondence, and;
WHEREAS, the ongoing operations and maintenance of these boundary roads is shared with our neighbouring municipalities;
THEREFORE BE IT RESOLVED THAT staff in
Public Works and Services be directed to review the condition of our boundary
roads and ditches, and report back to ARAC;
THEREFORE BE IT FURTHER RESOLVED THAT staff work with
the Public Works Departments of our neighbouring municipalities to develop a
strategy to ensure that these roads and ditches are maintained within the
parameters of City standards.
Since the approval of this motion, staff has been working with the
City’s neighbouring municipalities. The
purpose of this report is to provide the outcome of those discussions.
Boundary Roads Identification
The City of Ottawa has over 5,550 km
of roads and shares 114km of boundary roads with 12 bordering
municipalities. A boundary road defines
the boundary between two municipalities, and although it may not straddle the
precise boundary line, its identity as a boundary road remains.
The boundary roads surface types are as follows:
The road surface type impacts the type of equipment and strategies selected for regular maintenance, snow removal, and other operations. The life cycle analysis for rehabilitation strategies is also based on surface type.
A list of boundary roads, ward location, boundary municipality, road classification and surface type is included in Attachment 1.
Boundary Roads
Agreements
In accordance with S. 29(1) of the
Municipal Act, municipalities on either side of a boundary line have joint
jurisdiction over boundary roads. Both
are jointly responsible for its maintenance and repair.
The City of Ottawa has a number of verbal agreements with boundary municipalities regarding maintenance or capital renewal. The only formal written document covers 1.6 km of the 114 km of boundary roads. This agreement was recorded in the minutes of a site meeting 22 October 1981 for the South Gower Boundary Road in the Township of Osgoode.
A summary of the maintenance agreements with boundary municipalities is provided in Attachment 2. The following are key highlights:
·
City of Ottawa maintains year round and pays
100%: 20.8 km
·
Boundary Municipalities maintain year round and
pay 100%: 27.5 km
·
City of Ottawa maintains year round and charges
50% of the cost to the boundary Municipality:
58.5km
·
Boundary
Municipalities maintain year round and charges 50% of the cost to the City of
Ottawa: 2.2 km
·
City
of Ottawa maintains in the summer and adjacent Municipalities maintain in the
winter and no lateral invoicing takes place:
2.7 km
·
Un-maintained
(unopened) section of road: 2.2 km
During the exercise of searching for and reviewing boundary road agreements, 4 additional road maintenance agreements affecting non-boundary roads were identified (Attachment 2). These are also not documented in formal agreements:
For capital renewal or upgrade of boundary roads, historically cost sharing has been a 50/50 split between municipalities. Generally the City of Ottawa initiates the renewal project, informs the neighbour municipality, coordinates the project and recovers 50% from the other municipality. Typically, renewal projects are undertaken when both municipalities have approved their respective funding.
Boundary Roads Maintenance and
Capital Renewal
Summer Maintenance
·
Grass
Cutting
·
Road
Side Brushing
·
Litter
Pick-up - Trash and Debris
·
Drainage
- Ditching and Culverts
·
Bridge
Maintenance
·
Culvert
Flushing and Maintenance
·
Dust
Control
·
Shoulder
Grading
·
Road
Re-gravelling
·
Road
Grading
·
Asphalt
Patching
Winter Maintenance
·
Snow
Clearing – Scarifying
·
Snow
Clearing – Plowing
·
Snow
Clearing – Winging Back
·
Application
of Winter Abrasives (Grit Sand)
·
Application
of Winter Chemicals - Dry Salt
Capital renewal includes rehabilitation or replacement of structures and culverts, resurfacing and upgrade of gravel roads that involve major road improvements and in most instances hard surfacing. Prioritization of renewal activities for boundary roads is consistent with other city roads. As previously noted, these activities are generally initiated by the City of Ottawa with cost recovering from neighbouring municipalities.
Level of Service
A review of the maintenance standards applied to boundary roads
indicates that similar levels of service are applied, whether delivered by the
City of Ottawa or by the boundary municipality.
The reason is due to the ongoing dialogue between neighbouring
municipalities regarding maintenance issues and the fact that many maintenance
standards stem from Provincial Standards or have evolved over many years to a
level that is acceptable to both municipalities.
A key factor in the perceived level of service, whether delivered by the
City or the boundary municipality, is related to the physical condition of the
road and the adequacy of the drainage system.
Roads that are sub-standard in terms of condition or drainage are more
difficult to maintain and are often the source of resident complaints. These improvements are generally undertaken
as part of capital renewal activities and in some instances may involve
Municipal Drain provisions to address drainage concerns.
Next Steps
City staff will be seeking formal written agreements with all boundary municipalities pertaining to maintenance and capital renewal activities of boundary roads. These agreements will define roles, responsibilities and cost sharing arrangements. City staff have already initiated discussions with some boundary municipalities.
Boundary roads are located in the City’s rural wards,
including 5, 19, 20 and 21.
The affected Ward Councillors are aware of the report.
LEGAL/RISK MANAGEMENT
IMPLICATIONS
There are no legal/risk management implications to
this report.
CITY
STRATEGIC PLAN
This report is consistent with the Service Delivery priority of the City Strategic Plan.
TECHNICAL IMPLICATIONS
There are no technical implications.
There are no financial implications associated with this report.
Document 1 – List of Boundary Roads and Description
Document 2 – Maintenance Agreements with Boundary Municipalities
Staff in Infrastructure Services and Public Works Departments will continue to work with boundary municipalities to formally document maintenance and capital renewal standards, strategies and municipal roles and responsibilities.
Document 1
List
of Boundary Roads and Description
Boundary
Road Name & Description
|
Length (Km) |
Ward #
|
Boundary
Municipality
|
Road
|
Road
Surface Type (see notes)
|
Gilroy Rd From Donnelly Drive North to Dead End |
1.5 |
21 |
Montague Township |
Collector |
Gravel |
Gregoire Rd - (Formerly Reg'l Rd 41) Victoria St
(Reg'l Rd 6) to Marionville Rd |
8.9 |
20 |
United Counties of Prescott - Russell |
Arterial |
High Class Bituminous (HCB) |
Boundary Rd - (Formerly Reg'l Rd 41) From Burton Rd
to Victoria St. |
6.8 |
19/20 |
United Counties of Prescott - Russell |
Arterial |
High Class Bituminous (HCB) |
Marionville Rd From Gregoire
Rd to Bisson Rd |
1.3 |
20 |
North Dundas Township |
Collector |
360m HCB 930m LCB |
Marionville Rd From Bisson Rd
to Bank St |
7 |
20 |
North Dundas Township |
Collector |
1360m HCB 5640m Gravel |
Belmeade Rd From Bank St West
to Dead End |
12.3 |
20 |
North Dundas Township |
11480 Collector 820 Local |
Gravel |
South Gower Boundary Rd From River Rd
to Gabert Rd |
1.6 |
20 |
North Grenville Township |
Collector |
Gravel |
South Gower Boundary Rd From Gabert Rd to Belmeade Rd |
1.1 |
20 |
North Grenville Township |
Local |
Gravel |
Herrick Dr - Connifer Lane |
1.2 |
5 |
Arnprior |
Arterial |
High Class Bituminous (HCB) |
Headpond Rd |
0.7 |
5 |
Mississippi Mills |
Local |
Low Class Bituminous (LCB) |
Highway 15 |
2.8 |
5 |
County of Lanark |
Arterial |
High Class Bituminous (HCB) |
Lunney Rd |
1.4 |
5 |
Mississippi Mills |
Local |
Gravel |
Walter Bradley Rd |
1.7 |
5 |
Mississippi Mills |
Collector |
High Class Bituminous (HCB) |
Boundary
Road Name & Description
|
Length (Km) |
Ward #
|
Boundary
Municipality
|
Road
|
Road
Surface Type (see notes)
|
Timmins Rd |
1.2 |
5 |
Mississippi Mills |
Collector |
Gravel |
Rock Coady Trail |
0.35 |
5 |
Mississippi Mills |
Local |
High Class Bituminous (HCB) |
Panmure Rd |
0.4 |
5 |
Mississippi Mills |
Collector |
Low Class Bituminous (LCB) |
Golden line Rd |
6.2 |
5 |
Mississippi Mills |
Collector |
4370 LCB 1830 Gravel |
Golden Line Rd |
3.05 |
5 |
Mississippi Mills |
Collector |
Low Class Bituminous (LCB) |
Ashton Station Rd |
7.9 |
5/21 |
Beckwith Township |
Collector |
3950 HCB 2460 LCB 1490 Gravel |
Ashton Station Rd |
8.4 |
5 |
Beckwith Township |
Collector |
150 HCB 8250 Gravel |
Beckwith Boundary Rd |
1.3 |
21 |
Beckwith Township |
Collector |
Gravel |
Montague Boundary Rd From Beckwith Boundary Rd to Roger
Stevens Dr |
6.8 |
21 |
Montague Township |
Gravel |
|
Canaan Rd From 174 to Willhaven Dr
|
1.9 |
19 |
Township of Clarence- Rockland |
Collector |
|
Canaan Rd From Willhaven Dr to Baseline
Rd
|
0.2 |
19 |
Township of Clarence- Rockland |
Collector |
|
Canaan Rd From Baseline to Colonial |
6.1 |
19 |
Township of Clarence - Rockland |
Collector |
1610 HCB 4490 Gravel |
Boundary
Road Name & Description
|
Length (Km) |
Ward #
|
Boundary
Municipality
|
Road
|
Road
Surface Type (see notes)
|
Canaan Rd From Colonial south only to Dead End |
1.2 |
19 |
|||
Canaan Rd From Magladry to dead end |
2.2 |
19 |
Township of Clarence- Rockland |
Collector |
Gravel |
Canaan Rd From dead end to Russell Rd |
0.9 |
19 |
Township of Clarence - Rockland |
Collector |
Gravel |
Burton |
2.6 |
19 |
Russell Township |
Collector |
High Class Bituminous (HCB) |
Burton From Frontier to McVagh
|
4.3 |
19 |
Russell Township |
Collector |
High Class Bituminous (HCB) |
Russland Rd From Rockdale to Saumure
|
8.4 |
19 |
United Counties of Prescott -Russell |
Arterial |
High Class Bituminous (HCB) |
Saumure From Russland to Indian Creek
|
0.7 |
19 |
United Counties of Prescott - Russell |
Arterial |
High Class Bituminous (HCB) |
Indian Creek From Saumure to East Boundary
|
1.5 |
19 |
Nation Township |
Local |
High Class Bituminous (HCB) |
Notes:
High Class Bituminous (HCB) refer to
paved roads.
Low Class Bituminous (LCB) refer to
surface treated roads.
Document 2
Maintenance
Agreements with Boundary Municipalities
Boundary Road
|
Length (Km) |
Ward
|
Boundary
|
Current Maintenance Agreement
|
|
Written Agreement in place
|
Gilroy Rd From Donnelly Drive North to Dead End |
1.5 |
21 |
Montague Township |
Ottawa maintains in summer Montague Township maintains in winter |
No |
None on file |
Gregoire Rd - (Formerly Reg'l Rd 41) Victoria St (Reg'l Rd 6) to Marionville Rd |
8.9 |
20 |
United Counties of Prescott - Russell |
Ottawa maintains and charges 50% of employee hours, materials and equipment usage |
Yes |
None on file |
Boundary Rd - (Formerly Reg'l Rd 41) From Burton
Rd to Victoria St. |
6.8 |
19/20 |
United Counties of Prescott - Russell |
Ottawa maintains and charges 50% of employee hours, materials and equipment usage |
Yes |
None on file |
Marionville Rd From Gregoire Rd to
Bisson Rd |
1.3 |
20 |
North Dundas Township |
North Dundas maintains and charges 50% of employee hours, materials and equipment usage |
Yes |
None on file |
Marionville Rd From Bisson Rd to Bank St |
7 |
20 |
North Dundas Township |
Ottawa maintains and charges 50% of employee hours, materials and equipment usage |
Yes |
None on file |
Belmeade Rd From Bank St West to Dead End |
12.3 |
20 |
North Dundas Township |
Ottawa maintains and charges 50% of employee hours, materials and equipment usage |
Yes |
None on file |
South Gower Boundary Rd From River Rd to Gabert Rd |
1.6 |
20 |
North Grenville Township |
Ottawa maintains year round |
No |
Available on file |
South Gower Boundary Rd From Gabert Rd to Belmeade Rd |
1.1 |
20 |
North Grenville Township |
North Grenville maintains year round |
No |
Available on file |
Herrick Dr -
Connifer Lane |
1.2 |
5 |
Arnprior |
Arnprior maintains in the winter and Ottawa maintains in the summer |
No |
None on file |
Headpond Rd |
0.7 |
5 |
Mississippi Mills |
Mississippi Mills maintains year round |
No |
None on file |
Boundary Road
|
Length (Km) |
Ward
|
Boundary
|
Current Maintenance Agreement
|
|
Written Agreement in place
|
Highway 15 |
2.8 |
5 |
County of Lanark |
Ottawa maintains year round |
No |
None on file |
Lunney Rd |
1.4 |
5 |
Mississippi Mills |
Mississippi Mills maintains year round |
No |
None on file |
Walter Bradley
Rd |
1.7 |
5 |
Mississippi Mills |
Mississippi Mills maintains year round |
No |
None on file |
Timmins Rd |
1.2 |
5 |
Mississippi Mills |
Mississippi Mills maintains year round |
No |
None on file |
Rock Coady Trail |
0.35 |
5 |
Mississippi Mills |
Mississippi Mills maintains year round |
No |
None on file |
Panmure Rd |
0.4 |
5 |
Mississippi Mills |
Ottawa maintains year round |
No |
None on file |
Golden line Rd |
6.2 |
5 |
Mississippi Mills |
Ottawa maintains year round |
No |
None on file |
Golden Line Rd |
3.05 |
5 |
Mississippi Mills |
Mississippi Mills maintains year round |
No |
None on file |
Ashton Station
Rd |
7.9 |
5/21 |
Beckwith Township |
Ottawa maintains year round |
No |
None on file |
Ashton Station
Rd |
8.4 |
5 |
Beckwith Township |
Beckwith maintains year round |
No |
None on file |
Beckwith
Boundary Rd |
1.3 |
21 |
Beckwith Township |
Beckwith maintains year round |
No |
None on file |
Montague Boundary Rd From Beckwith
Boundary Rd to Roger Stevens Dr |
6.8 |
21 |
Montague Township |
Montague maintains year round |
Yes |
None on file |
Canaan Rd From 174 to Willhaven Dr |
1.9 |
19 |
Township of Clarence- Rockland |
Ottawa maintains 100% |
No |
None on file |
Boundary Road
|
Length (Km) |
Ward
|
Boundary
|
Current Maintenance Agreement
|
|
Written Agreement in place
|
Canaan Rd From
Willhaven Dr to Baseline Rd
|
0.2 |
19 |
Township of Clarence- Rockland |
Ottawa maintains and charges 50% of employee hours, materials and equipment usage |
No |
None on file |
Canaan Rd From Baseline to Colonial |
6.1 |
19 |
Township of Clarence - Rockland |
Ottawa maintains and charges 50% of employee hours, materials and equipment usage (Recently adopted to improve operational efficiencies) |
Yes |
None on file |
Canaan Rd From Colonial south only to Dead End |
1.2 |
19 |
None on file |
|||
Canaan Rd From Magladry to dead end |
2.2 |
19 |
Township of Clarence- Rockland |
Unmaintained section of road. |
No |
None on file |
Canaan Rd From dead end to Russell Rd |
0.9 |
19 |
Township of Clarence - Rockland |
Clarence-Rockland maintains and charges 50% of employee hours, materials and equipment usage |
Yes |
None on file |
Burton |
2.6 |
19 |
Russell Township |
Ottawa maintains and charges 50% of employee hours, materials and equipment usage |
Yes |
None on file |
Burton From Frontier
to McVagh
|
4.3 |
19 |
Russell Township |
Ottawa maintains and charges 50% of employee hours, materials and equipment usage |
Yes |
None on file |
Russland Rd From Rockdale
to Saumure
|
8.4 |
19 |
United Counties of Prescott -Russell |
Ottawa maintains and charges 50% of employee hours, materials and equipment usage |
Yes |
None on file |
Saumure From Russland
to Indian Creek
|
0.7 |
19 |
United Counties of Prescott - Russell |
Ottawa maintains and charges 50% of employee hours, materials and equipment usage |
Yes |
None on file |
Boundary Road
|
Length (Km) |
Ward
|
Boundary
|
Current Maintenance Agreement
|
|
Written Agreement in place
|
Indian Creek From Saumure
to East Boundary
|
1.5 |
19 |
Nation Township |
Nation Township maintains with no charge back. |
No |
None on file |
Boundary Road
|
Length (Km) |
Ward
|
Boundary
|
Current Maintenance Agreement
|
|
Written Agreement in place
|
Malloch Lane From Ashton Station to Dead End (West) |
0.7 |
N/A |
Beckwith Township |
Ottawa maintains in summer Beckwith maintains in winter |
No |
None on file |
Douglas St
|
0.7 |
N/A |
Beckwith Township |
Ottawa maintains in winter Beckwith maintains in summer |
No |
None on file |
Roger Stevens
Drive
From Montague
Boundary Road to Dwyer Hill Rd
|
2.9 |
21 |
Lanark County |
Ottawa maintains in the summer Lanark County maintains in winter |
No |
None on file |
March Road
From Golden
Line to the Town of Almonte
|
2.9 |
N/A |
Lanark County |
Lanark County maintains in the summer City of Ottawa maintains in winter |
No |
None on file |