Reference - Item No. 16
- Planning and Environment Committee Agenda 21 - 9 November 2004 |
Référence
– Point No 16 – Comité de l’urbanisme et de l’environnement Ordre du jour 21- Le 9
November 2004 |
Document 1
Submission to the Minister of Natural
Resources
Re-Investment in Ontario’s Conservation
Authorities
- Now and In the Future -
June
2004
Executive Summary
Conservation Ontario is a non-governmental organization that represents the common interests of the network of 36 Conservation Authorities across Ontario. The Ontario Ministry of Natural Resources is the lead Ministry for the Conservation Authorities Act under which the Conservation Authorities operate. This report has been prepared by Conservation Ontario to address a serious funding issue that affects all Conservation Authorities and the safety of the residents of Ontario. This report deals only with transfer payments from the Ministry of Natural Resources and does not address current or future funding relationships with other Ministries or other initiatives.
Historically, municipal and provincial governments supported Conservation Authorities by sharing the costs of the program. In 1992, the total transfer payment to the Conservation Authorities from the Ministry of Natural Resources was $58,900,000. Today, the provincial share has been drastically reduced. In total, sources of revenue for the 36 Conservation Authorities are: provincial (11%), municipal (40%), self-generated (47%) and federal (2%). At issue, and the subject of this report, is the total transfer payment available to Conservation Authorities administered by the Ministry of Natural Resources which currently totals $7,600,000.
This report formally requests that the Ministry of Natural Resources provide:
There is a significant shortfall in funding to Conservation Authorities by the Ministry of Natural Resources particularly as it relates to items deemed of provincial interest, and eligible for provincial funding, as outlined in the 1997 Policy and Procedures Manual for Conservation Authorities. Based on the 2002 audited financial statements of the 36 Conservation Authorities, the total expenditure for items eligible for 50% funding was $33,445,000. Based on the definition of eligibility this should have translated into a funding of $16,722,000. However, as only $7,600,000 had been allocated, there was a provincial shortfall of $9,122,000.
The 1997 Policy and Procedures Manual specifically exclude three activities that had previously been funded, defining them as being of “no provincial interest.” These are: Municipal Plan Review; Conservation Authority Act Section 28 Regulation; and Shoreline Management. Conservation Ontario believes these activities are of provincial interest as they are integral to a successful program of flood and erosion control both inland and on the Great Lakes shoreline. For this reason, there is an obligation on the
part of the Ministry of Natural Resources to financially support these functions, as a minimum, at the same rate as other items of provincial interest. The total expenditure by Conservation Authorities in 2002 on these programs that have provincial delegation of responsibility was $7,493,000. The total cost to the Ministry of Natural Resources in 2002 dollars should have been $3,746,000.
Sustainable funding is critical to successful program delivery. Key concerns of the Conservation Authorities are rising overhead costs and inflation, which are eroding the value of unchanged funds currently provided by the Ministry of Natural Resources. To address these concerns, an annual cost of living adjustment should be applied to transfer payments to the Conservation Authorities. It is recommended that the commonly used Consumer Price Index from Statistics Canada be the instrument for determining this adjustment.
The total estimated 2005 cost to the Ministry of Natural Resources using 2002 as a base year and applying the Consumer Price Index retroactive to 2002 is estimated at $21,421,000 (+ CPI Adjustment for 2005). This will increase the total transfer payment to Conservation Authorities in 2005 by $13,821,000 (+ CPI Adjustment for 2005). The total cost includes items eligible for 50% funding under the 1997 Policy and Procedures Manual as well as items of provincial interest that were previously excluded from provincial funding.
Conservation Authorities are committed to watershed management and to their long standing relationship with the Ministry of Natural Resources in natural hazards management. A re-investment in the Conservation Authorities will strengthen the Ministry partnership in the continued development of leading edge watershed management in Ontario. Such a re-investment will also enable Conservation Authorities to enhance their capacity to deliver existing programs and through the reapplication of other sources of revenue, further advance the protection of our natural environment and the health of our watershed communities.
Table of Contents
2.1 Policy and Procedures Manual (1997) Exclusions from
This Review
2.2 Operational Activities Eligible for Provincial
Transfer Payment
3.0
Re-investment of Funding to Items Currently Excluded from Provincial Transfer
Payment
3.1 Municipal Plan Review (Natural Hazards)
4.0 Annual
Consumer Price Index (CPI) Adjustments to Funding
Appendix 1 Chapter 3 – Policy and Procedures for Conservation Authorities: Policy and Procedures for Determining Eligibility for Provincial Grant Funding to Conservation Authorities……………..……………………………………15
Appendix 2 Chapter 4 - Policy and Procedures for Conservation Authorities: Business Plan For Determining Provincial Grant Funding to Conservation Authorities……............................................................................................27
Appendix 3 Letter
from the Minister of Natural Resources (dated April 1995) …….....37
Figure 1. 2002
Conservation Authority Expenditures
Figure 2. 2002 Conservation Authority Revenues
Figure 3. 2002 Cost Sharing for Operational Activities Eligible for 50%
Funding
Table 3. Annual Consumer Price Index Adjustments to Funding and Funding
Shortfalls
Table 4. Proposed Total Re-Investment to Ontario Conservation Authorities
in 2005
The Conservation Authorities, established by provincial legislation in 1946, are community-based resource management organizations working on a watershed basis. Almost 90% of Ontario’s population (approximately 10.5 million people in over 250 municipalities) is located within a Conservation Authority’s jurisdiction. These populated areas are where resource conflicts and degradation are greatest and where provincial investment is needed most.
Conservation Authorities deliver community-based, practical solutions on a wide range of natural resource issues (e.g. flooding, erosion, drought, wetland conservation, source protection, natural heritage protection). Conservation Authorities are also recognized globally for their watershed stewardship activities through the development and delivery of comprehensive science-based programs that work with nature and landowners to protect, restore and effectively manage Ontario’s water and land resources.
Conservation Authorities have a strong and publicly recognized track record of partnering with all levels of government, providing advice on decisions that directly affect the long term sustainability of our water and land resources. Their greatest ‘on the ground’ achievements have been realized through their working relationships at the provincial and municipal levels.
Figure 1 presents the
distribution of Conservation Authority expenditures in 2002. The majority (87%) of expenditures were for
water and land management programs. Water management programs include watershed
planning and management; environmental land use planning; flood and erosion
control; water quality and quantity management; agriculture and rural landowner
assistance; and protection of sensitive wetlands, floodplains and valley
lands. Land management programs include; reforestation and sustainable woodlot management; habitat
protection and restoration; environmental education; outdoor recreation; and
information management.
Water Management – includes watershed planning and management; environmental land
use planning; flood and erosion control; water quality and quantity
management; agriculture and rural landowner assistance; and protection of
sensitive wetlands, floodplains and valley lands. Land Management – includes reforestation
and sustainable woodlot management; habitat protection and restoration;
environmental education; outdoor recreation; and information management
Note:
Based on total expenditures of $147,000,000 (as per 2002 audited financial
statements) of Ontario’s 36 CAs.
Conservation Authorities achieve their goals through partnerships. Historically, municipal and provincial governments supported Conservation Authorities by sharing the costs of the program. Every dollar invested by municipalities was matched by the province to ensure a fair and equitable sharing of the cost to deliver services that benefited the greater public good. In total, the provincial share has been drastically reduced. The current cost sharing is illustrated in Figure 2. In total, sources of revenue for the 36 Conservation Authorities are: provincial (11%), municipal (40%), self-generated (47%) and federal (2%). In addition, provincial supplementary grants (i.e. equalization payments), which were once made available to Conservation Authorities where the local property tax was insufficient to support the full municipal share, were withdrawn, making the financial hardship that much greater in rural, less populated areas.
It should be noted that Provincial funding is received through transfer payments from the Province of Ontario, administered by the Ministry of Natural Resources (under Section 39 of the Conservation Authorities Act) as well as “special project” funding from various provincial ministries, such as the Ministry of the Environment, for special projects (e.g. Provincial Groundwater Monitoring Network, Provincial Water Quality Monitoring Network, Low Water Response etc.). This report deals only with transfer payments administered through the Ministry of Natural Resources and does not address current or future funding relationships under source protection planning or other initiatives.
Note:
Based on total revenues of $149,000,000 (as per 2002 audited financial
statements) of Ontario’s 36 CAs.
The Ministry of Natural Resources is the lead ministry for the Conservation Authorities Act under which the Conservation Authorities operate. The Conservation Authorities have seen transfer payments administered through the Ontario Ministry of Natural Resources cut by 87% since 1992 when $58,900,000 was transferred. The most significant withdrawal of funding occurred in 1995.
It should be noted that the requirement for increased municipal support, as a result of reduced provincial funding, occurred without municipal consultation. The loss of this provincial support has resulted in increases to municipal contributions. For example, in the Lower Trent Conservation Authority, the provincial transfer payment in 1991 was 62% of the Conservation Authority’s budget and in 2003 it was 11%. In Maitland Valley Conservation Authority, the provincial transfer payment in 1993 was 59% of the Conservation Authority’s budget and in 2003, it was 4%. These examples are not isolated; similar funding shifts can be seen in all Conservation Authorities. As illustrated in Figure 2, in 2002 self-generated revenues represented a substantial source of revenue. It must be noted that self-generated revenues are market-driven and have been maximized.
In 1997, the Ontario Ministry of Natural Resources approved the new Policy and Procedures Manual for Conservation Authorities. This document not only defines those programs which are considered to be of provincial interest but also defines the amount of funding that the province is committed to providing to the Conservation Authorities.
This document has not been revisited nor updated since 1997.
Since 1995, Conservation Authorities have restructured, re-organized and re-focused their policies and programs to reflect these major cuts in provincial funding. This has been accomplished under the auspices of the provincial policy and procedures as well as under the direction of their Boards of Directors (comprised of local municipal representatives).
Over the last few years, the municipalities have requested, through their local Conservation Authorities and Conservation Ontario, that the Province of Ontario and more specifically, the Ministry of Natural Resources provide:
Although it has been determined that the reinstatement of a provincial equalization payment to those Conservation Authorities that lack a strong local property tax base is beyond the scope of this report, it must be noted that this issue also needs to be re-examined by the Ministry.
Chapter 3 of the Policy and Procedures Manual (PPM) (Appendix 1) forms the basis for the discussion on fair funding to Conservation Authorities for eligible activities.
It is not the objective of this paper to re-define the items eligible for provincial transfer payments except in those instances where it is the position of Conservation Ontario that present definitions exclude items of provincial interest. These are covered in Section 3.0 of this report.
This review excludes capital for major maintenance of existing flood and erosion control infrastructure. The role of the Province of Ontario in providing funding assistance to municipalities with respect to the capital construction of flood and erosion control projects was eliminated with the application of the PPM in 1997. Once again it must be emphasized that removal of provincial support was done unilaterally by the Province and without municipal consultation. The province did however, recognize its on-going responsibility for the regular maintenance and operation of those projects funded by the province in the past. The major maintenance of these same structures is the subject of a separate initiative of Conservation Ontario, working with the Ministry of Natural Resources, through the Water and Erosion Control Infrastructure Working Group.
The overall shortfall excludes costs associated with the upgrading of hazard mapping required in support of the Section 28 Regulation under the Conservation Authorities Act.
This mapping is critical in providing advice for the application of Section 3.1 of the provincial policy statement under the Planning Act. Decisions, reliant on the accuracy of this mapping, protect life, reduce property damage and minimize disaster and emergency response costs. It also promotes safe, economic, and timely development. Much of the current hazard mapping is 15 or more years old and was financed through MNR and in later years through the Flood Damage Reduction Program (FDRP). Conservation Ontario will be addressing the cost of updating this mapping and the associated modeling separately with the Ministry.
Section 3.1 of Chapter 3 of the PPM (see Appendix 1) lists the items eligible for transfer payment funding in order of provincial priority. It specifies the amount of funding available in 1997 as $8,000,000 (Section 3.2.1 of the PPM) and the funding rate as 50 % of the total approved costs (Section 3.2.2 of the PPM). It should be noted that the total funding to Conservation Authorities were unilaterally reduced by the Province in 2000 by a further 5% to $7,600,000.
At issue is the total dollars that are available to Conservation Authorities. Transfer payments administered through MNR currently total $7,600,000.
Using the 2002 approved audited financial statements of the 36 Conservation Authorities, the total expenditure by Conservation Authorities in 2002 for items eligible for 50 % funding was $33,445,000. According to the definition of eligibility this should have translated into funding of $16,722,000. However, as only $7,600,000 had been allocated, this leaves a shortfall of $9,122,000. Table 1 provides a summary of the above assessment.
Provincial transfer payments are therefore distributed more on the basis of availability rather than eligibility. In actual fact, 77% of the cost of these items that are deemed of a high priority provincially, are paid for by the Conservation Authorities (as illustrated in Figure 3). The Province is not maintaining its financial participation in equal sharing with the member municipalities.
The total provincial transfer payment dollars available has also led to a significant reduction in the ability of Conservation Authorities to undertake items 3.1.10 to 3.1.12 which by their very nature keep Authorities at the forefront of resource management. In 1999, because of the high demand for funds in the higher priority items (3.1.1 to 3.1.9) the Ministry reallocated 42.5% of the funding available for plan input (3.1.10), information (3.1.11), legal costs (3.1.12) and administration (3.1.13) to the higher priority items, further exacerbating the issue of lack of funds.
Business Plan Categories (see Appendix 1 for full description) |
A Total Project Cost 2002 ($) |
B Eligible Funding 2002 ($) |
C Funding Approved 2002 ($) |
D Funding Shortfall 2002 ($) |
|
3.1.1 |
Operation of Flood Control
Structures |
2,788,000 |
1,394,000 |
1,293,000 |
101,000 |
3.1.2 |
Routine Maintenance of
Flood Control Structures |
1,562,000 |
781,000 |
624,000 |
158,000 |
3.1.3 |
Preventative Maintenance of
Flood Control Structures |
1,451,000 |
725,000 |
452, 000 |
273, 000 |
3.1.4 |
Operation of Erosion
Control Structures |
199,000 |
100,000 |
100,000 |
0 |
3.1.5 |
Routine Maintenance of
Erosion Control Structures |
309,000 |
155,000 |
151,000 |
3,000 |
3.1.6 |
Preventative Maintenance of
Erosion Control Structures |
384,000 |
192,000 |
191,000 |
2,000 |
3.1.7 |
Flood Forecasting and
Warning - Operation |
4,047,000 |
2,024,000 |
1,718,000 |
306,000 |
3.1.8 |
Flood Forecasting and
Warning - Rationalization |
816,000 |
408,000 |
379,000 |
29,000 |
3.1.9 |
Ice Management |
596,0001
|
298,000 |
306,000 |
(8,000) |
3.1.10 |
Plan Input (Official Plan
and Official Plan Amendment input) |
2,098,988 |
1,049,494 |
602,745 |
446,749 |
3.1.11 |
Information (Watershed
Studies and technical studies) |
4,036,000 |
2,018,000 |
851,000 |
1,167,000 |
3.1.12 |
Legal Costs |
180,000 |
90,000 |
16,000 |
74,000 |
3.1.13 |
Administration (based
on total Administration costs for Conservation Authorities as per definition
in Section 4.9 of PPM) |
14,976,060
|
7,488,030 |
941,235 |
6,546,795 |
|
TOTAL |
33,445, 000 |
16,722, 000 |
(7,643, 000) 7,600,0002 |
(9,097, 000) 9,122,0003 |
Note: 2002 audited financial statements of the 36 CAs do not consistently
reference the categories in the PPM (MNR, 1997); however, best estimates were
applied. Values have been rounded to
the nearest thousand dollars.
1 2002 was an unusual year in terms of spring flows and
ice breakup and therefore 2002 expenditures for ice management were
significantly lower than normal.
2 2002 Funding Approved values differ between MNR and
CAs due to surpluses in previous years and/or differences in MNR/CA fiscal
year. Total 2002 Funding Approved by
MNR was $7,600,000.
3 Based on Total 2002 Funding Approved by MNR the
overall shortfall is $9,122,000.
Funding Shortfall
– paid by CAs (27%)
Administration is a critical component of the Conservation Authority program. The important partnership between the Conservation Authorities and the Province must be recognized in this regard, and the cost to properly administer programs must be acknowledged. Administration, as it is defined in the 1997 PPM, is currently being funded 90% by municipalities and 10% by the province. This is inequitable and a partnership must be reestablished.
Of particular concern is the variability of the application of the definition for administration (Section 4.9 of the PPM) which specifically states:
‘Overhead and support costs of the Conservation Authority which are not directly related to the delivery of a specific program (underlined for emphasis) and which typically include general management, clerical, financial and board staffing and expenses; office equipment and supplies; main office occupancy costs etc.’ (MNR, 1997)
This definition clearly identifies total administration costs associated with all Conservation Authority programs as eligible for funding of 50%. This is inconsistent with the business plan submission form (Chapter 4 of the PPM as seen in Appendix 2) which identifies only that portion of administration costs applicable to items 3.1.1 to 3.1.13 to be eligible for funding. A further variation in application was expressed in the budget allocation principles laid out by MNR in 2000 wherein it was stated that:
‘Administration expenditures should be in
the order of 15% of the total grant funded
program – in no case more than 20%.’
The lack of adequate funding by the province to meet its own definitions has led to the downloading of significantly higher costs onto the municipalities. The 50% funding partnership has been ignored and must be established.
There is a significant shortfall in funding to Conservation Authorities by the Ministry of Natural Resources particularly as it relates to items deemed of provincial interest, and eligible for provincial transfer payments, as per the Policy and Procedures Manual. This shortfall totals $9,122,000.
By defining them as being of “no provincial interest”, the 1997 Policy and Procedures Manual specifically excludes three activities that had previously been funded. In the opinion of Conservation Ontario, these activities are of provincial interest as they are integral to a successful program of flood and erosion control both inland and on the Great Lakes shoreline. These are:
Under its definition in the PPM, Municipal Plan Input (Section 4.6) only relates to the “Policy support…….through the Ministry of Municipal Affairs and Housing on matters of provincial interest relating to the Natural Hazards Policy……and focusing on the Official Plan and Official Plan Amendment stage at the upper tier municipal level.” As per Table 1, these plan input activities have a shortfall in funding of $447,000. In addition to this, the Conservation Authorities provide municipal plan review on zoning by-laws, draft plans of subdivisions, draft plans of condominiums, consents and variance applications, and site applications. In 2002, Conservation Authorities spent $4,359,000 in municipal plan review without provincial funding.
Municipal Plan Review activities undertaken by the Conservation Authorities are a critical component to ensuring consistent implementation of policy for the protection of life and property. Through their on-going participation in the process, Conservation Authorities are diligent in their responsibility to identify hazard areas and to ensure that these lands are properly avoided and addressed through the development process. The exclusion of the Conservation Authorities’ role in municipal plan review ignores the fact that plan review is perhaps the most powerful and cost effective non-structural flood and erosion damage prevention measure that one can implement. With the elimination of the capital program for the control of flooding and erosion, municipal plan review has also become the single most important tool in minimizing the need for future capital funding by the province. The delivery of plan review services will realize immeasurable benefit in the future. It ensures public safety through risk reduction and sound watershed management. The designation of Conservation Authorities as the ‘lead commenting agency’ under Section 3.1 of the Provincial Policy Statement relating to the Natural Hazards Policy warrants provincial cost sharing of this program.
The Province of Ontario should provide 50% funding for plan review activities. This is the same rate as that applied to plan input. The total cost to the province, based on an assessment of Conservation Authority municipal plan review in 2002 dollars should have been $2,179,000.
Under the Conservation Authorities Act, the Section 28 regulation is a provincial regulation that is delivered by Conservation Authorities. The previously funded implementation and enforcement of Section 28 regulations is, as mentioned above, specifically excluded as an item of provincial interest in the PPM. Historically, the Ministry of Natural Resources encouraged and funded the preparation of fill and floodplain mapping, in accordance with its terms of reference and rigorous approval system. The registration of mapping as regulatory instruments was critical to successful enforcement. The enforcement of these regulations puts the Conservation Authorities front and centre in the protection of streams, rivers, lakes, valley lands and wetlands and hence water resource management.
The enforcement of these regulations by Conservation Authorities is also the first line of defense to prevent inappropriate development in the province of Ontario. This ensures that areas susceptible to flooding, erosion, unstable soils, unstable slopes, etc. are not developed. This loss prevention program significantly reduces the probability of future government expenditures for capital projects as well as the potential for loss of life and property damage.
The approval of the generic regulations by the province on April 19, 2004 confirms its relevance and importance in watershed resource management and enforcement is an integral part of maintaining regulatory integrity.
In 2002, Conservation Authorities spent $2,534,000 in enforcing the Section 28 regulation without provincial funding. As previously indicated, costs associated with the updating of hazard mapping (required in support of Section 28 Regulation) has been excluded from the overall shortfall, as this issue will be addressed separately with the Ministry. There is an obligation on the part of the Province of Ontario to provide funding for the enforcement of a provincial regulation that addresses issues of both provincial and local interest. At the 50% level of funding, the total cost to the province in 2002 dollars should have been $1,267,000.
In correspondence dated April 19, 1995, (Appendix 3), the Conservation Authorities were delegated the sole commenting responsibility on plan input and review matters related to natural hazard issues by the then Minister of Natural Resources, Howard Hampton. Delegated responsibilities from the Ministry of Natural Resources included dynamic beaches along the shorelines of the Great Lakes –St. Lawrence River System. This designation became effective March 29, 1995. The designation as outlined in the Minister’s letter has never been formally withdrawn, although funding was eliminated. The PPM is silent on shoreline matters either in its inclusion as a provincial interest or in its specific exclusion.
Consultation with Conservation Authorities that have shorelines in their jurisdiction indicates that, with the withdrawal of provincial funds in 1995/96, the Conservation Authority role in shoreline management has, for the most part, been rolled into the on-going plan review function in an effort to fulfill its obligations under the designation of responsibility. As well, with the transfer of funds from ‘information’ (3.1.11 of the PPM) by MNR (see section 2.2 above), efforts by Conservation Authorities and municipalities to do preventative management of Great Lakes shorelines have been compromised.
In 2002, Conservation Authorities spent $601,000 in shoreline management services. This is a very conservative record of costs as much of the costs are likely combined into the municipal plan review function.
Of critical importance is the fact that shoreline management is just as important today with lower lake levels as it was in the late 1980’s when water levels were significantly higher. Lake level fluctuations are a natural phenomenon that must continually be addressed. Preventative shoreline management, that aims to protect life and property from flooding and erosion hazards, is therefore necessary.
Conservation Ontario believes that there is an on-going obligation on the part of the Province of Ontario to financially support its designation of responsibility to the Conservation Authorities. For the province to meet its obligation in 2002 dollars, at a 50% funding rate, there needs to be an investment of $300,000. It is important that shoreline management be reviewed in its entirety to assess the real costs in delivering this program.
The total expenditure by Conservation Authorities in 2002 on programs that have provincial delegation of responsibility was $7,493,000. Conservation Ontario believes that there is an obligation on the part of the Province of Ontario and more specifically, the Ministry of Natural Resources, to financially support these functions as a minimum at the same funding rate as other items of provincial interest. The total cost to the Ministry of Natural Resources in 2002 dollars should have been $3,746,000. Table 2 summarizes the above assessment.
Items of Provincial Interest Currently Excluded from Provincial Funding |
Total Conservation Authority Cost in 2002* |
Funding at 50% |
Conservation Authority Commitment at 50% |
Municipal Plan Review (Natural Hazards) |
4,359,000 |
2,179,000 |
2,179,000 |
Section 28 Regulation Enforcement |
2,534,000 |
1,267,000 |
1,267,000 |
Shoreline Management |
601,000 |
300,000 |
300,000 |
|
|
|
|
TOTAL |
7,493,000 |
3,746,000 |
3,746,000 |
* Based on the 2002 audited
financial statements of the 36 Conservation Authorities. Values have been
rounded to the nearest thousand dollar.
Sustainable funding is critical to successful program delivery. A key concern is that rising overhead costs have resulted in the need for increased municipal funding at the same time as inflation is eroding the value of the limited provincial investment that is made to the Conservation Authorities. An annual cost of living adjustment should be applied to the transfer payments to the Conservation Authorities. It is further suggested that the commonly used Consumer Price Index (CPI) from Statistics Canada be the instrument for determining this adjustment.
The actual month for which the year over year change in the CPI is applied is open for discussion. However, for Conservation Authority budgeting purposes, and accounting for the difference in fiscal years between the province and the Conservation Authorities, it is recommended that August (information is available in late September) be the month of choice and that the CPI measure entitled by Statistics Canada as “All Items for Ontario” be the unit of adjustment for the next fiscal year. This would allow the Authorities to budget appropriately with ample time for the Ministry of Natural Resources to accommodate the adjustment. Table 3 illustrates application of the CPI adjustments to the 2002 Transfer Payment administered by the Ministry of Natural Resources, as well as the shortfall in funding for the existing eligible operational activities and the additional areas of provincial interest that are not currently funded.
This process is simple, rational and will greatly assist Conservation Authorities in addressing the “current” costs associated with undertaking all the aforementioned activities.
|
2002 Provincial Transfer Payment |
Shortfall for Eligible Operational Activities |
Shortfall for Items Currently Excluded from Provincial Transfer Payment Funding |
Total Dollars in 2002 |
$7,600,000 |
$9,122,000 |
$3,746,000 |
CPI
Adjustment for 2003 Aug
01-Aug 02 (2.9%)* |
$220,000 |
$265,000 |
$109,000 |
CPI
Adjustment for 2004 Aug
02-Aug 03 (1.7%)** |
$133,000 |
$160,000 |
$66,000 |
TOTAL |
$7,953,000 (+CPI Adjustment for 2005) |
$9,547,000 (+CPI Adjustment for 2005) |
$3,921,000 (+CPI Adjustment for 2005) |
Note: Values are rounded to the
closest thousand dollar.
* Statistics Canada, 2004a
** Statistics Canada, 2004b
Since 1995, Conservation Authorities through their ongoing commitment to watershed management have absorbed the shortfall in provincial funding at the expense of local priorities. It is the position of Conservation Ontario that it is time for the province, and in particular the Ministry of Natural Resources, to meet its funding obligations as laid out in its own policies. It is time to re-invest in the Conservation Authority movement by re-instating at least three areas of provincial interest, and to establish an annual cost of living adjustment to Conservation Authority transfer payments.
The total estimated 2005 cost to the Province of Ontario using 2002 as a base year and applying the Consumer Price Index retroactive to 2002 is estimated at $21,421,000 (+ CPI Adjustment for 2005). This will increase the total transfer payment to Conservation Authorities in 2005 by $13,821,000 (+ CPI Adjustment for 2005). This is summarized in Table 4.
|
2002
Provincial Transfer Payment Administered by MNR ($) |
Eligible
Operational Activities ($) |
Items
Currently Excluded from Provincial Transfer Payment Funding |
Total MNR
Re-Investment In 2005 ($) |
Total dollars in 2002 |
7,600,000 |
|
|
7,600,000 |
Total New Dollars |
|
9,122,000 |
3,746,000 |
12,868,000 |
Total CPI Adjustments |
353,000 |
425,000 |
175,000 |
953,000 |
Total Proposed
2005 Transfer Payment Administered by MNR |
7,953,000 (+ CPI Adjustment for 2005) |
9,547,000 (+ CPI Adjustment for 2005) |
3,921,000 (+ CPI Adjustment for 2005) |
21,421,000 (+ CPI Adjustment for
2005) |
Conservation Authorities are committed to watershed management and to their long standing relationship with the Ministry of Natural Resources in natural hazards management. Conservation Ontario is committed to working with the Ministry on behalf of the network of Conservation Authorities to make positive change. A re-investment in the Conservation Authorities will strengthen the Ministry partnership in the continued development of leading edge watershed management in Ontario. Conservation Authorities could enhance their capacity to deliver existing programs and through the reapplication of other sources of revenue, further advance the protection of our natural environment and healthy watershed communities. This is a sign of our commitment. Now we need the same from the Province.
Ontario
Ministry of Natural Resources. 1997. Policies and Procedures for Determining
Eligibility for Provincial Grant Funding to Conservation Authorities.
Statistics Canada. 2004a. Consumer Price Index for Ontario from August 2001-August 2002. http://www.statcan.ca/Daily/English/020920/d020920a.htm (website accessed May 18, 2004).
Statistics Canada. 2004b. Consumer Price Index for Ontario from August 2002-August 2003. http://www.statcan.ca/Daily/English/030923/d030923a.htm (Website accessed May 18, 2004).
Appendix 1
Chapter 3 – Policy and Procedures for Conservation Authorities: Policy and Procedures for Determining
Eligibility for Provincial Grant Funding to Conservation Authorities
POLICIES
AND PROCEDURES
FOR DETERMINING ELIGIBILITY FOR
PROVINCIAL GRANT FUNDING
TO CONSERVATION AUTHORITIES
1.0 BACKGROUND
Since the formation of
Conservation Authorities over 50 years ago, the province has provided a
substantial financial contribution towards the construction and maintenance of
flood and erosion control structures.
These structures were constructed to reduce the risk of loss of life and
property damage from floods and erosion.
The provincial funding was largely provided through transfer payments
through the Ministry of Natural Resources, but also included funding from other
government agencies.
Recent reductions in
provincial transfer payments made Conservation Authorities no longer eligible
for grants to continue the construction of flood and erosion control
works. However, it was determined that
there was to be a continuing financial contribution for the routine operation
and maintenance of the flood and erosion structures, flood forecasting and
warning, plan input, acquisition of some supporting information, and some
related legal and administrative costs.
This policy identifies the
items that are deemed to be eligible for provincial grant funding to conservation authorities under Section 39
of the Conservation Authorities Act. A
separate policy addresses eligibility for provincial grant funding for taxes
for Provincially Significant Conservation lands and Agreement/Managed Forest
lands.
2.0 LEGISLATION
2.1 Section
24 of the Conservation Authorities Act states that “before proceeding with a
project, the authority shall file plans and a description thereof with and
obtain the approval of the Minister”.
This section applies where money is granted by the Minister under
section 39.
2.2 Section
39 of the Conservation Authorities Act provides for the Minister to provide
grants to Conservation Authorities from “...money appropriated therefor by the
Legislature in accordance with such conditions and procedures as may be
prescribed by the Lieutenant Governor in Council...”.
3.0 POLICY
This policy provides a
framework under which the provincial grant funding is allocated (excluding
provincial grant funding for taxes for provincially significant conservation lands
and Agreement/Managed Forest lands) to Conservation Authorities, pursuant to
Section 39 of the Conservation Authorities Act and the definitions of
eligibility are established.
3.1 Eligibility
The following items are
eligible for provincial grant funding (for definitions of eligibility see
Section 4.0):
3.1.1 Operation of Flood Control Structures (see 4.2.1)
3.1.2 Routine/Minor Maintenance of
Flood Control Structures (see 4.2.2)
3.1.3 Preventative Maintenance of Flood
Control Structures (see 4.2.3)
3.1.4 Operation of Erosion Control
Structures (see 4.3.1)
3.1.5 Routine/Minor Maintenance of
Erosion Control Structures (see 4.3.2)
3.1.6 Preventative Maintenance of
Erosion Control Structures (see 4.3.3)
3.1.7 Flood Forecasting and Warning -
System Operation (see 4.4.1)
3.1.8 Flood Forecasting and Warning -
Rationalization (see 4.4.2)
3.1.9 Ice Management (see 4.5)
3.1.10 Plan Input (see 4.6)
3.1.11 Information (see 4.7)
3.1.12 Legal Costs (see 4.8)
3.1.13 Administration (see 4.9)
3.2 Provincial
Grant Funding Allocation
3.2.1 The
total annual provincial grant funding available for Conservation
Authorities for items listed in 3.1 is
$8 million.
3.2.2 For
items 3.1.1 - 3.1.13 the provincial grant rate will be 50% of the total
approved cost.
4.0 DEFINITIONS
OF ELIGIBILITY
4.1 Minister - Minister of Natural Resources
4.2 Flood Control Structures - Structures which were approved by the Ministry of
Natural Resources and are owned, maintained and/or operated by Conservation
Authorities, which mitigate risk to life and property damage from flooding.
This includes dams, flood channel works and dykes.
4.2.1 Operation of Flood Control Structures - Activities, functions or requirements undertaken on a
daily, weekly, monthly or annual basis which are directly related to the
operation of a flood control structure.
This includes:
. staff time, vehicles, materials,
supplies
. dam/dyke
inspections (e.g., annual/semi-annual)
. property
taxes for area integral to the structure (e.g., dam, upstream reservoir,
roadway, roadway access, downstream channel, dyke, constructed channel)
. items
identified with health and safety concerns for both operator and public (e.g.,
safety harnesses)
. rent/insurance/utilities
4.2.2 Routine/Minor Maintenance of Flood Control
Structures - Activities, functions
or requirements undertaken on a daily, weekly, monthly or annual basis
to maintain a flood control structure.
This includes:
. measures
required to upkeep the structure, ensure that the flood control capability is
preserved, and/or to mitigate major maintenance
. debris
removal
. routine
painting
. parging/minor
repair to concrete surfaces
4.2.3 Preventative Maintenance of Flood Control
Structures - Activities, functions
or requirements undertaken on an irregular, greater-than-annual basis to
maintain a flood control structure.
This includes:
. replacement
of valves/gates/stop logs
. painting (complete
stripping/repainting of main spillway gates)
. replacement
of functional components (i.e. heating/cooling plants, backup power units,
generators, motors, cables, gears, etc.)
. security
items to reduce vandalism (i.e. fences, electronic security systems)
. preparation
and upgrade of operation/maintenance manuals and schedules
. maintenance of channels and emergency
spillways
. engineering
studies or assessments associated with determining structural integrity
4.3 Erosion Control Structures - Structures which were approved by the Ministry of
Natural Resources and are owned, maintained and/or operated by Conservation
Authorities, which mitigate risk to property damage from erosion or bank
instability. This includes erosion channel works.
4.3.1. Operation of Erosion Control Structures - Activities, functions or requirements undertaken on a
daily, weekly, monthly or annual basis and which are directly related to the
operation of an erosion control structure.
This includes:
. staff time, vehicles, materials,
supplies
. erosion/slope
stability inspections (annual/semi-annual)
. property
taxes for area integral to the structure (i.e., erosion works, slope works,
roadway access)
. rent/insurance/utilities
4.3.2 Routine/Minor Maintenance of Erosion Control
Structures - Activities, functions
or requirements undertaken on a daily, weekly, monthly or annual basis
to maintain an erosion control structure.
This includes:
. measures required to upkeep the
structure, ensure that the erosion prevention or slope stability capability is
preserved, and/or to mitigate major maintenance.
. maintenance of erosion and slope stability
works
4.3.3 Preventative Maintenance of Erosion Control
Structures - Activities, functions
or requirements undertaken on an irregular, greater-than-annual basis to
maintain an erosion control structure.
This includes:
. engineering
studies or assessments associated with determining structural integrity
. maintenance
of erosion and slope stability works.
Sections 4.2 (Flood Control Structures) and 4.3
(Erosion Control Structures) do not include works associated with major maintenance of flood or
erosion control structures, such as:
. deck
replacement
. rebuilding
of control structure beyond the replacement of individual
. stop
logs (i.e. replacement of stop log gains, replacement of gate)
. structural
modifications
. rehabilitation/restoration
. major
repairs/reconstruction of structures
. channel
lining, (i.e. placement of gabions, concrete)
. structural
enlargements (i.e., increasing height of dykes, enlarging spillway capacity of a dam)
. staff
time associated with the above functions
Also excluded are the following:
. Operation
and maintenance of structures where no flood control function is performed
(i.e. recreational, low flow augmentation dams)
. Implementation
of other non-structural flood control measures (i.e. municipal plan review,
fill, construction and alteration to waterways regulations, education)
4.4 Flood Forecasting and Warning - Procedures, undertaken by Conservation Authorities,
required to reduce the risk of loss of life and property damage due to flooding
through the forecasting of flood events and the issuing of flood warnings,
alerts and advisories to prepare those who must respond to the flood
event.
4.4.1 Flood Forecasting and Warning - System
Operation - Development and
implementation of a comprehensive system developed to guide and implement flood
forecasting and warning activities, to effectively manage flood control
structures and to provide guidance during the response to a flood. Basic components include:
4.4.1.1 Data
Collection
. operations and maintenance of
existing and purchase of upgraded equipment (i.e. streamgauge stations for
water levels and flow, meteorological sensors)
. snow survey station operation and
monitoring equipment
. ice monitoring
. data
collection software for real‑time data access to those items listed above
. access
to MNR Water Resources Information System which includes
purchase/maintenance/operations of a computer and backup (such as a portable)
and associated equipment to access the above and to operate the procedure(s)
under flood forecasting
. localized
river/flood damage monitoring including after the event assessment (i.e. field
trips, ice jam monitoring, flood response monitoring).
4.4.1.2 Flood
Forecasting
. approved
forecasting models,
. calibration
of an accepted procedure(s) and its implementation in order to quantify the
flood/damage potential
. training costs for staff
. computers
to run models
4.4.1.3 Communications
. purchase/operations/maintenance
of communications equipment such as fax machines/software (backups) for the
issuance of flood warning messages and the reception of field related
information,
. pagers/cell phones to contact local
flood duty officer
. preparation
of annual response plan and meeting to response agencies (i.e. municipal staff,
OPP)
. issuing
flood warnings to municipalities
4.4.1.4 Operations Centre
. work
area in which the flood operations take place
. backup
equipment
4.4.1.5 Systems
Plan
. a
feasibility study/plan to determine resources necessary to deliver local flood
warning messages
4.4.1.6 Response
to a Flood
. field
trips to assess flood damages, ongoing reporting, provision of advice to
municipalities during the event
. assistance in the development of
local flood contingency plans
. flood
event termination/follow up
This
does not include:
. Costs
for actual flood response, e.g. flood combat is a municipal responsibility
. Flood
response equipment (i.e. sandbags, boats and pumps) is also not eligible
4.4.2 Flood
Forecasting and Warning - Rationalization
Currently,
the ministry is considering a number of options which address the operation and
administration of the provincial flood forecasting and warning function. One of
the options involves rationalization of certain components of the program with
Conservation Authority roles and responsibilities. The overall objective of potential rationalization is to improve
efficiency of weather forecasting and information dissemination, to remove any
duplication of effort and optimize costs.
Part of this review involves examination of funding support for the
hydro-met network within Conservation Authority jurisdiction and possible
transfer of systems operations to the Conservation Authorities program.
Pending
further review and consultation with the Conservation Ontario, activities associated with this review may
be deemed eligible.
4.5 Ice Management - Preventative measures,
supported by a current ice management plan, associated with the removal of
sediment from channels or the control of ice in areas where there is a chronic
problem occurring annually, where there
is an increase in the risk to life and property, and where there is a method to reduce the possible adverse
effects of the sediment or ice. This
includes:
. removal
of sediment
. standby
equipment (e.g., ice breaker) necessary to be placed upstream of the ice
problem prior to winter freeze-up
This
does not include:
. emergency
response measures (including staff time) to deal with unanticipated flood risk
due to ice jam or debris jam conditions
4.6 Plan
Input - Policy support provided by
Conservation Authorities, through the Ministry of Municipal Affairs and Housing
(MMAH), on matters of provincial interest relating to the Natural Hazards
Policy (Section 3.1 under Public Health and Safety made under the Provincial
Policy Statement) and focusing on the Official Plan and Official Plan Amendment
stage at the upper tier municipal level.
This
includes:
. broad policy interpretation
. transfer of data, information and
science to municipalities
. provision
of advice on matters relating to natural hazards policy to MMAH
4.7 Information - The portion
of watershed planning projects and technical studies as defined below
which provide input into the Official Plan and Official Plan Amendment stage of
the municipal planning process at the upper tier municipal level with respect
to the provincial hazards policy , including:
. delineation
of hazard areas
. development
of policies to guide appropriate management and use of hazard lands
4.7.1 -
Watershed Planning Projects - Projects undertaken by Conservation
Authorities to provide a broad understanding of ecosystem function and status
and to make recommendations for appropriate environmental resource management,
land use change, land management change, or redevelopment and restoration, on a
watershed basis. This includes:
. Project
management - e.g., project scoping, terms of reference, report preparation,
scheduling
. Background
data collection - pulling together existing data
. Analysis/interpretation
. Development
of recommendations
. Public
consultation - e.g., newsletters, workshops
. Implementation
- ensuring information is transferred to appropriate Official Plans, resource
management programs and other implementation mechanisms
. Monitoring
- ensuring information is being implemented as expected, and that
recommendations are current
4.7.2 - Technical Studies - to support the preparation and monitor the
effectiveness of watershed planning projects (4.7.1); and Section 28 environmental regulation programs.
. Hydrology/Hydraulics
- the study of surface water flows and levels (e.g., low/peak flow, water
budget, surface/groundwater interactions, flood hazard)
. Stream
Morphology - the study of mechanisms that operate as a result of water flow
within a stream channel (e.g. erosion, sedimentation)
. Mapping
and Data Management - The use of systems to collect and store data and to
provide spatial geographical representations of data
This
does not include:
. Aquatics
- The application of aquatic ecology and biology and the study of aquatic
systems and communities
. Terrestrial
- the application of terrestrial ecology and biology, or the study of
terrestrial systems and communities
. Groundwater
- the study of sub-surface water, its occurrence, movement and chemistry and
the factors that influence it including interactions with surface flow systems
4.8 Legal Costs - Legal costs for law suits where the Conservation
Authority/Province is named pertaining to Conservation Authority capital
projects where the province has had significant financial involvement.
4.9 Administration - Overhead and support
costs of the Conservation Authority which are not directly related to the
delivery of a specific program and which typically include general management,
clerical, financial and board staffing and expenses; office equipment and
supplies; main office occupancy costs; etc.
5.0 PROCEDURES
5.1 Conservation
Authorities are to prepare an annual business
plan outlining eligible activities and anticipated eligible costs. The plan should include a confirmation that
the Conservation Authority has complete records for these program areas which
are accessible to the province for audit purposes.
The business plan is to be updated annually
and submitted by October 31 by the Conservation Authority to Conservation
Ontario and to MNR at the following
address:
Director
Lands and Natural Heritage Branch
Ministry of Natural Resources
300 Water Street
P.O. Box 7000
Peterborough, Ontario
K9J 8M5
The business plan will be used to
establish original allocations and future refinements, and for a reference for
future audits. A sample business plan form is attached as
Appendix A.
5.2 Conservation
Ontario/MNR will jointly determine Conservation Authority allocations under
this policy.
Each
year by December 15, Conservation Ontario must submit to MNR for review, a
report that proposes next year allocations to Conservation Authorities, under
this policy.
5.4 Each
year Conservation Authorities will receive one cheque for the total grant
amount from the Province together with the Section 39 funding approval
form. Approval under Section 24 of the
Conservation Authorities Act will be coincident with Section 39 approval.
At
year end by January 31, Conservation Authorities must submit a year end
expenditure report (see appendix B) for all grants received, together with a
report indicating actual work accomplished with the grants received.
At
year end by February 15, Conservation Ontario must submit to MNR for review, a
report that proposes year-end reallocations among Conservation Authorities.
If
the surplus can be spent between January 1 and March 31 the Conservation
Authority will be allowed to retain the surplus and should not return it to the
Province. Approved year-end
reallocations will be adjusted with the next year original allocations.
5.5 MNR
reserves the right to audit Conservation Authorities for adherence to this
policy. Audits may be done by a
Conservation Ontario/MNR peer-review process.
Appendix 2
Chapter 4 - Policy and Procedures for Conservation Authorities:
Business Plan For Determining Provincial Grant Funding to Conservation
Authorities
Annual Budget
For Determining Provincial Grant Funding
to Conservation Authorities
Note: This must be read in conjunction with the Policies
and Procedures for Determining Eligibility for Provincial Grant Funding to
Conservation Authorities. Numbering
between documents is consistent.
Conservation Authority
4.2 Flood Control Structures Complete table for each flood control structure. Name of Structure: Location (Watercourse and Municipality): |
||||
|
Total Eligible Costs |
|||
|
Budget Actual |
Budget Proposed |
% Change |
|
4.2.1 Operation of
Flood Control Structures |
|
|
||
Wages/Benefits |
|
|
|
|
Materials/Expenses |
|
|
|
|
Subtotal |
|
|
|
|
4.2.2
Routine/Minor Maintenance of Flood Control Structures |
|
|
||
Wages/Benefits |
|
|
|
|
Materials/Expenses |
|
|
|
|
Subtotal |
|
|
|
|
4.2.3
Preventative Maintenance of Flood Control Structures |
|
|
||
|
|
|
||
Wages/Benefits |
|
|
|
|
Materials/Expenses |
|
|
|
|
|
|
|
|
|
Subtotal |
|
|
|
|
Total -Flood Control Structure |
|
|
|
|
4.3 Erosion Control Structures Complete table for each erosion control structure. Name of Structure: Location (Watercourse and Municipality): |
||||
|
Total Eligible Costs |
|||
|
Budget Actual |
Budget Proposed |
% Change |
|
4.3.1 Operation of Erosion Control Structures |
|
|
||
Wages/Benefits |
|
|
|
|
Materials/Expenses |
|
|
|
|
Subtotal |
|
|
|
|
4.3.2
Routine/Minor Maintenance of Erosion Control Structures |
|
|
||
Wages/Benefits |
|
|
|
|
Materials/Expenses |
|
|
|
|
Subtotal |
|
|
|
|
4.3.3
Preventative Maintenance of Erosion Control Structures |
|
|
||
Wages/Benefits |
|
|
|
|
Materials/Expenses |
|
|
|
|
Subtotal |
|
|
|
|
Total - Erosion Control Structure |
|
|
|
|
|
4.4
Flood Forecasting and Warning |
|||||||
|
|
Total Eligible Costs |
||||||
|
|
Budget Actual |
Budget Proposed |
% Change |
||||
|
4.4.1 System
Operation 4.4.1.1 Data Collection |
|
|
|||||
|
Wages/Benefits |
|
|
|
||||
|
Materials/Expenses |
|
|
|
||||
|
Subtotal |
|
|
|
||||
|
4.4.1.2
Flood Forecasting |
|
|
|||||
|
Wages/Benefits |
|
|
|
||||
|
Materials/Expenses |
|
|
|
||||
|
Subtotal |
|
|
|
||||
|
4.4.1.3
Communications |
|
|
|||||
|
Wages/Benefits |
|
|
|
||||
|
Materials/Expenses |
|
|
|
||||
|
Subtotal |
|
|
|
||||
|
4.4.1.4 Operations Centre |
|
|
|||||
|
Wages/Benefits |
|
|
|
||||
|
Materials/Expenses |
|
|
|
||||
|
Subtotal |
|
|
|
||||
|
4.4.1.5 Systems Plan |
|
|
|
||||
|
Wages/Benefits |
|
|
|
||||
|
Materials/Expenses |
|
|
|
||||
|
Subtotal |
|
|
|
||||
|
4.4.1.6 Response to a Flood |
|
|
|||||
|
Wages/Benefits |
|
|
|
||||
|
Materials/Expenses |
|
|
|
||||
|
Subtotal |
|
|
|
||||
|
Total - System Operation |
|
|
|
||||
4.5 Ice
Management |
||||||||
Complete table for each chronic
ice management location. |
||||||||
Location
of Ice Management Activity (Watercourse and Municipality):
|
||||||||
|
Total Eligible Costs |
|||||||
|
Budget Actual |
Budget
Proposed |
|
|||||
Wages/Benefits |
|
|
|
|||||
Materials/Expenses |
|
|
|
|||||
Total - Ice Management |
|
|
|
|||||
Explain why each ice
management situation is chronic/recurring on annual basis and please include
your ice management plan(s).
4.6 Legal Costs |
|
|
|
|
|
Total Eligible Costs |
|
|
Budget Actual |
Budget
Proposed |
% Change |
Total - Legal Costs |
|
|
|
To
support this request, provide a brief description of the legal activities
including the name of the flood/erosion capital project(s) which was previously
supported by the Province (through S. 24 & S.39 of the Conservation Authorities
Act).
Project Details: New Carryover
Year Started
Projected Completion
Date Total
Cost to Date $
Explain Request for Legal Costs:
4.7
Watershed Management |
|
4.7.1 Watershed
Planning Projects Complete table for each
watershed plan. Name of Watershed Plan: Project Details: New Carryover Year Started Projected Completion
Date Total
Cost to Date $
Location (Watercourse and
Municipality):
|
|
A. Total Project Cost |
|
B.
Hazard Component of Total Project Cost eligible as indicated in 4.7 of
the Policies and Procedures for Determining Eligibility for Provincial
Grant Funding to Conservation Authorities |
|
C. % of Project that is Eligible
(B/Ax100) |
|
|
|
|
Total Costs |
Project Management |
|
Background Data Collection |
|
Analysis/interpretation |
|
Development of
Recommendations |
|
Public Consultation |
|
Implementation |
|
Monitoring |
|
Total |
|
x % Eligible (C, from
above) |
|
Total Eligible |
|
To support this request,
provide a brief description of the proposed watershed planning project(s)
including the name and rationale of the new Official Plan, revised Official
Plan or Official Plan Amendment; as well as scheduling information.
4.7.2 Technical Studies Complete table for each
technical study. Name of Technical Study: Project Details: New Carryover Year Started Projected Completion
Date Total
Cost to Date $
Location (Watercourse and
Municipality): |
|
|||
|
Total Eligible Costs |
|
||
|
Budget Actual |
Budget
Proposed |
|
|
Hydrology/Hydraulics |
|
|
|
|
Stream Morphology |
|
|
|
|
Mapping/Data Management |
|
|
|
|
Total - Technical Studies |
|
|
|
|
To support this request,
provide a brief description of the proposed technical study project(s)
including the name and rationale of the new Official Plan, revised Official
Plan or Official Plan Amendment; watershed plan or Section 28 environmental
regulation project; as well as scheduling information.
4.7.3
Plan Input Natural Hazard Components
only - priority to Upper Tier Municipality Project Details: New Carryover Year Started
Projected Completion
Date Total
Cost to Date $ Project |
|||
|
Total Eligible Costs |
||
|
Budget Actual |
Budget Proposed |
% Change |
Wages/Benefits |
|
|
|
Expenses |
|
|
|
Total - Plan Input |
|
|
|
To support this request,
provide a brief description of the proposed plan input project(s) including the
name and rationale of the new Official Plan, revised Official Plan or Official
Plan Amendment; as well as scheduling information.
4.8 Administration |
Budget Actual |
Budget Proposed |
A. Total administration cost for the authority |
|
|
B. Total **eligible costs for items 4.2
- 4.7 |
|
|
C.
Total authority budget (less large capital expenditures) |
|
|
D. C. - A. |
|
|
E. Total Administration ( AxB/D) |
|
|
**Eligible costs to be
clarified in consultation with Conservation Ontario
Appendix 3
Letter from the Minister of Natural Resources (dated April 1995)