Report to/Rapport au:

Environmental Services Committee

Comité des services de l’environnement

 

and Council/et au Conseil

 

02 May 2003/le 02 mai 2003

 

Submitted by/Soumis par: Rosemarie Leclair, General Manager/Directrice générale

Transportation, Utilities and Public Works/Transports, services et travaux public

 

Contact/Personne-ressource:  Richard Hewitt, Director, Infrastructure Services Branch/ Directeur des services et travaux publics

580-2424, ext. 21268, Richard.Hewitt@ottawa.ca

 

 

 

Ref N°:ACS2003-TUP-INF-0007

 

SUBJECT:     MUNSTER HAMLET WASTEWATER TREATMENT FACILITY –

RE-EVALUATION OF ALTERNATIVES AND RECOMMENDED

SOLUTION

 

OBJET :         INSTALLATION POUR LES EAUX USÉES DE MUNSTER HAMLET – RÉÉVALUATION DES SOLUTIONS DE RECHANGE ET SOLUTION RECOMMANDÉE

 

 

REPORT RECOMMENDATIONS

 

That Environmental Services Committee recommend Council:

 

(a)        receive the “Munster Hamlet Wastewater Treatment Facility Re-Evaluation of Alternatives Final Report”, dated 16 December 2002, prepared by R.V. Anderson Associates Limited to comply with the decision of the Ontario Municipal Board to re-evaluate three treatment alternatives (mechanical treatment plant discharging to the Jock River (CMS), pipeline and Snowfluent®);

 

(b)        approve the implementation of the pipeline alternative as the recommended solution for Munster Hamlet Wastewater Treatment.

 

 


RECOMMANDATIONS DU RAPPORT

 

Le Comité des services de l’environnement recommandera au Conseil :

 

(a)        de recevoir le rapport Installation pour les eaux usées de Munster Hamlet – réévaluation des solutions de rechange du 16 décembre 2002, préparé par R.V. Anderson Associates Limited conformément à la décision de la Commission des affaires municipales de l'Ontario de réévaluer trois solutions de rechange pour le traitement des eaux usées (traitement mécanique déchargeant dans la Jock River (CMS), pipeline et Snowfluent®);

 

(b)        d’approuver la mise en œuvre de la solution « pipeline » comme solution  recommandée pour le traitement des eaux usées  de Munster Hamlet.

 

 

BACKGROUND

 

Munster Hamlet is a small residential community of approximately 1,300 people located in the west rural area of the City.  For several years, the existing lagoons and spray irrigation treatment system has experienced problems in managing the municipal sewage from the community.  In addition, there are concerns with the integrity of the lagoon cells.  Leakage has been documented by City staff and through various reports that have been prepared over the past several years.  Investigation and on-going monitoring has determined there are currently no impacts on adjacent wells or the two communal wells servicing the community.

 

In 1995, the former Region of Ottawa-Carleton (ROC) engaged the engineering firm of Totten Sims Hubicki Associates (TSH) to undertake an Environmental Assessment (EA) to determine the preferred means to remedy the problems with the existing lagoon and spray irrigation treatment system.  The results of the study, as documented in the “Munster Hamlet Sewage Treatment Environmental Study Report” (ESR) dated January 1996, recommended upgrading/expanding the existing facility.  There were several Phase 2 Order (formerly “bump-up”) requests submitted to the Ministry of Environment (MOE).  The Minister denied all requests in January 1997.

 

In 1997, the former ROC proceeded with the preliminary and detailed design for upgrading/expanding the existing lagoon and spray irrigation treatment system.  TSH was engaged to complete the work.

 

Prior to the implementation of this solution, the former ROC received an unsolicited proposal in early 1998 for an on-site proprietary treatment facility.  As a result, Regional Council, on 11 March 1998, directed staff to re-evaluate treatment options and prepare an addendum to the ESR.


 

In April 1998, the former ROC engaged the engineering firm of Conestoga-Rovers and Associates (CRA) to complete the re-evaluation, on an independent basis, take into account any new information and to solicit and identify other applicable treatment alternatives.

 

Design-build proposals were received by the former ROC in July 1998.  The submissions were used as a means to obtain information for price-guaranteed alternatives to be considered by CRA.

 

CRA completed their assessment of treatment alternatives for the Munster Hamlet Wastewater Treatment Facility and issued an addendum to the ESR documented in the “Addendum for the ESR Class EA Wastewater Treatment System Expansion/Upgrade” dated May 1999.  The addendum recommended that Munster Hamlet be connected to the central sewage collection and treatment system by means of a pipeline to Richmond.  There were several Phase 2 Order requests submitted to the MOE.  The Minister denied all requests in October 1999.

 

An amendment to the Regional Official Plan was required to implement the pipeline solution and provide servicing for Munster Hamlet.  The amendment was approved by Regional Council on 12 May 1999 but was appealed by several interested parties to the Ontario Municipal Board (OMB).

 

Regional Council, at its meeting on 26 January 2000, approved the award of a contract to Doran Contractors Limited to complete preliminary and detailed designs and project management for construction of the pumping station and forcemain.  The former ROC entered into a Professional Engineering Agreement with Doran Contractors Limited, dated January 2000, to complete the work.  Work under the agreement was suspended 02 June 2000, pending the outcome of the OMB hearings.

 

The OMB considered the appeal of the amendment to the Regional Official Plan from March to July 2000 and released its decision in June 2001.  The City was directed to re-evaluate three of the alternatives (CMS, pipeline and Snowfluent®).  In accordance with the OMB decision, the re-evaluation had to be completed to the satisfaction of City Council.  The OMB advised the City to consider the following factors:

 

“1.        The City is advised to consider retaining a qualified person or persons who has or have not been associated with the project so far to undertake a re-evaluation of the three treatment alternatives;

2.         The City is advised to consider instructing the evaluating person/s to critically assess the Weighted Additive Method and employ it with modifications if necessary and if found appropriate, and assess the treatment alternatives;

3.         The City is advised to consider instructing the evaluating person/s to also employ the standard qualitative assessment of merits and demerits of the alternatives;

4.         The City is advised to consider instructing the evaluating person/s to seek facts and opinions from the interested people, the CRA, and the proponents of the treatment alternatives to ensure a thorough canvassing of all the facts and opinions and take account of them in both the quantitative and qualitative methods of evaluation, including an explanation why certain facts and opinions were disregarded;

5.         The City is advised to consider instructing the evaluating person/s to make a recommendation based upon both the quantitative and qualitative methods.”

 

Corporate Services and Economic Development Committee, at its meeting on 03 July 2001, authorized the seeking of leave to appeal the OMB decision.  To minimize delays, staff also brought forward a report recommending an Action Plan to satisfy the OMB decision.  Environmental Services Report No. 6 was approved by Council on 11 July 2001.  The Action Plan included the retention of a consultant to conduct an independent re-evaluation of the three alternatives.

 

A Request for Proposal (RFP) was distributed to four consultants in October 2001.  The consultants were selected to submit proposals based on their experience in the environmental engineering field and their in-depth knowledge of the Environmental Assessment process, wastewater treatment technologies and municipal infrastructure systems.  The firms had no previous involvement in the matter.

 

On 29 October 2001, Divisional Court denied the leave to appeal the OMB decision.

 

Staff completed the review and evaluation of the consultant proposals, submitted in response to the RFP, in December 2001.  Each proposal was evaluated on the basis of the experience of the firm, experience and qualifications of key members, understanding of the objectives, approaches and methodologies to complete the assignment, availability to conduct the assignment and cost.

 

An Information Previously Distributed Memo dated 05 February 2002, listed on the Environmental Services Committee Agenda of 26 February 2002, advised the Department selected the engineering firm of R.V. Anderson and Associates Limited (RVA) and would enter into an agreement with them to complete the re-evaluation of three alternatives for the Munster Hamlet Treatment Facility.

 

RVA submitted a final work plan for the assignment dated 12 February 2002.  The work plan involved completing a detailed review of relevant background information, EA and methodology review of the addendum to the ESR completed by CRA, re-evaluation of the three treatment alternatives including completing sensitivity analyses, interviews and stakeholder consultation and preparation of a final report outlining their findings and recommendations.

 

The report was submitted to the City by RVA on 16 December 2002.  The results of the report were presented to the public in Munster Hamlet that evening.  RVA recommended the City proceed with the implementation of a communal wastewater treatment system (CMS or Snowfluent®) for Munster Hamlet.

 

RVA concluded that, based on their evaluation of the EA process followed by CRA in the preparation of the addendum to the ESR, the requirements of the “Municipal Engineers Association (MEA) Class Environmental Assessment for Water and Sewage Projects” were met for Munster Hamlet.

 

 

DISCUSSION

 

Based on the quantitative analysis completed by RVA, the December 2002 Report concluded that, from an environmental perspective, any one of the three alternatives could be considered as a viable and acceptable solution and have merits and issues associated with them that would need to be overcome if any of them were to be successfully implemented.

 

It is important to recognize the December 2002 RVA Report was prepared under a specific set of constraints or guidelines in response to the OMB ruling directing the City to undertake the re-evaluation.  These included only re-evaluating three specific alternatives identified in the OMB ruling (CMS, pipeline and Snowfluent®) and completing the re-evaluation with exactly the same criteria and weighting as the original matrix evaluation completed by CRA.  The challenge of the assignment for RVA was to determine a rationale for recommending one of the three alternatives in the face of an inconclusive quantitative re-evaluation.  This was consistent with the OMB Hearing, which in spite of significant efforts, was unable to confirm the selection of one of the alternatives.

 

The RVA report identified the following qualitative issues associated with each alternative:

 

 

The 2002 December RVA Report made a recommendation in favour of a communal wastewater treatment system largely because of the cost differential determined for the pipeline in consideration of comparable environmental issues.  The report also identified the need to investigate a number of issues with the MOE and further aspects of implementing the recommended alternative to ensure cost and time impacting issues were sufficiently understood.

 

Additional investigations and consideration of these issues were completed following the receipt of the December 2002 RVA Report to ensure due diligence prior to recommending an appropriate solution for Council approval.  These issues included regulatory and procedural requirements of the Environment Assessment Act; conditions that may be imposed by the MOE to obtain a Certificate of Approval (C of A); the need and availability of additional land that may be required for the communal systems; timing of implementation; associated costs; risks and environmental impacts.

 

Since RVA was very familiar and knowledgeable of the issues associated with the implementation of each alternative, they were engaged to assist the City in completing the additional investigations.

 

RVA submitted a Technical Memorandum dated 30 April 2003 providing supporting information to outline the implications of implementing each of the three alternatives (reference Annex A).

 

 

ANALYSIS

 

RVA conducted additional investigations including more substantive discussions with the MOE, CMS, Northern Watertek (Snowfluent®) and Doran Contractors Limited (pipeline), to provide a clearer understanding of the implications of implementing each of the three alternatives.

 

The CMS (now owned by Seprotech) alternative is a mechanical treatment plant with discharge to the Jock River (reference Annex A, Figure 3).  The treatment system proposed by CMS involves flow equalization, primary and secondary treatment using the ROTORDISK™ process (rotating biological contractor), tertiary treatment using dual point chemical addition and sand filtration (Dynasand filter), and ultra violet (UV) disinfection prior to discharge to the Jock River.  The discharge options include discharge to a dry ditch to the Jock River or a pipeline directly to the Jock River.  The spray irrigation system and all but one lagoon would be decommissioned.  The lagoon would be used for temporary storage of peak flows and on an emergency basis.  CMS, in their design/build submission, proposed the existing lagoons be converted to a constructed wetland that could be used as an emergency bypass in the event of an unexpected upset condition at the treatment plant.

 

The pipeline alternative involves the upgrade/expansion of the pumping station at Munster Hamlet and construction of a forcemain to Richmond via Munster Side Road and Franktown Road (reference Annex A, Figure 2 and Annex B).  The spray irrigation system and all but one lagoon would be decommissioned.  The lagoon would be used for temporary storage of peak flows and on an emergency basis.  The pipeline route was selected based on the “Wastewater Pipeline Route Alternative Evaluation” dated April 1999 completed by CRA as part of the addendum to the ESR in 1999.  The addendum identified that further investigation is required to specifically route the pipeline in Richmond for connection to the Richmond Pumping Station.  The design phase would include public involvement to finalize the route within Richmond.

 

The Snowfluent® alternative (owned by Northern Watertek) is a land application process using the Snowfluent® system in the winter and intermittent sand filtration followed by spray irrigation in the summer (reference Annex A, Figure 1).  The proponent has proposed using the same equipment and land area for both summer and winter operating modes.  Each mode uses two cells of the existing lagoons, which would be refurbished to provide storage of 100 days for an average flow of 575 m3/day.  Wastewater would be stored in the lagoons between the winter and summer operations and when the Snowfluent® snow making system or intermittent sand filtration/spray application processes were not operating.  During winter, wastewater from the lagoons would be pumped to towers where it would be converted to snow using a process known as “atomizing freeze-crystallization”.  The snow is dispersed in piles over a dedicated land area.  The snow making system would operate from November to March.  Based on an existing facility located at Westport, it is expected the snowmelt would occur during the warmer weather, typically from April to the end of June.  During summer, the proponent has proposed that effluent from the intermittent sand filter would be spray irrigated from June to October to the same land used for Snowfluent® snow applications.  Operations would be carried out at off-peak energy cost periods for both operating modes.

 

The three alternatives were further assessed in the following areas:

 

Environmental Assessment Approvals

 

From an Environmental Assessment Act perspective, the pipeline is an approved solution and can proceed to implementation.  The MOE has confirmed, in a letter to the City dated 18 March 2003 (reference Annex C), that a pipeline solution can proceed under the existing addendum to the ESR in 1999.

 

If either of the communal treatment alternatives (CMS or Snowfluent®) is to be implemented, an addendum to the ESR is required. The MOE has advised that any selection of an alternative solution must be undertaken in accordance with the requirements of the Environmental Assessment Act.  As a minimum, this would entail re-evaluation of all six alternatives, as identified in the addendum to the ESR prepared by CRA in 1999.

 

The EA approval process (addendum) could be completed in approximately 6 months; however, if Phase 2 Order requests are submitted to the Minister for review, the process could be extended to 12 or more months.

 

Discharge Requirements for Certificate of Approval (C of A)

 

The CMS alternative requires a discharge to the Jock River.  MOE has confirmed that any discharge to the Jock River would need to meet the requirements of their Abatement Policy for Point Discharges to the Rideau system.  This means it would need to meet the Provincial Water Quality Objectives for Total Phosphorus (TP) of 0.03 mg/l.  A similar system has been approved by the MOE for the Village Walk development in Manotick.  The C of A was issued in 1997 and has a design objective of 0.03 mg/l TP and a compliance TP of 0.04 mg/l, based on a monthly average.  This criterion is expected to be similar for Munster Hamlet.  The discharge criterion would be the same whether the plant has a dry-ditch discharge or is piped directly to the Jock River.  The ability of the CMS alternative to meet the discharge criterion for TP has not been demonstrated.  Although the proponent has guaranteed the criterion can be met, a full-scale plant using dual sand filtration after the ROTORDISK™ process has not been identified which demonstrates the design objective (0.03 mg/l) and compliance monthly average (0.04 mg/l) for TP can be consistently achieved.  The C of A would likely contain a condition that a back-up system be constructed should the discharge criterion for TP not be met.

 

The C of A for the pipeline alternative would not be an issue since the forcemain directly discharges to an existing pumping station and ultimately to the R.O. Pickard Environmental Centre (ROPEC) and the Ottawa River.  The existing requirements of ROPEC’s C of A would be the applicable discharge criteria to be met.

 

The MOE guidelines for Snowfluent®, relative to C of A reviews, identifies the technology as an experimental process.  While the process is not necessarily viewed in that way today, the issues in the guidelines are those with which an application for approval is evaluated.  The requirements for information and additional studies from the proponent, in support of a C of A application to the MOE, include:

 


 

In accordance with the MOE guidelines on land application rates and buffer zones, additional land is required if the MOE does not accept the same land can be used for summer and winter operations.  The specific requirement will not be known until the MOE reviews the C of A application and supporting studies are provided addressing soil permeability, etc.  Preliminary studies by the proponent suggests no new land is required.  This would need MOE approval before it is accepted.

 

Regulatory Compliance

 

The City is required to operate the Munster Hamlet Treatment Facility in accordance with the C of A issued under the Ontario Water Resources Act.  The compliance requirements of the existing C of A are currently not being met.

 

The City is currently working under a voluntary abatement program to address the environmental problems.  The program, agreed to between the City and MOE, includes the provision for annual trucking of excess sewage from the Munster Lagoons to ROPEC, monitoring of groundwater in the areas adjacent to the lagoons, an extension to the period of time that spray irrigation is permitted, and increase in spray irrigation application rates.  Staff have increased the level of maintenance on all equipment associated with the facility to minimize the likelihood of equipment failures having an adverse effect on the surrounding environment.

 

Voluntary abatement programs do not affect the ability of the MOE to proceed with prosecution for ongoing or past non-compliance.  The program for Munster was last modified in 1998 to address delays resulting from the decision to re-evaluate alternatives for the Munster Hamlet Wastewater Treatment Facility.

 

The MOE advised the adequacy of the voluntary abatement program to achieve compliance with Ministry legislation and policy is currently under review by the Ministry (reference Annex C).  The MOE has requested the City provide an updated action plan for the resolution of the environmental problems at Munster Hamlet.

 

The MOE has received an application for an investigation under the Environmental Bill of Rights for alleged contraventions of the Environmental Protection Act and the Ontario Water Resources Act in relation to the Munster Hamlet Wastewater Treatment Facility.  It is alleged the City is in non-compliance with the C of A for Munster Hamlet and the current sewage system is impairing the quality of the Jock River.  The Ministry will inform the City, the applicants and the Environmental Commissioner of Ontario of the decision on the application by 21 June 2003.

 

Penalties under the Environmental Protection Act and Ontario Water Resources Act for non-compliance and risk of adverse effect could range from $100,000 - $500,000 for first and second offences and $10,000 per day for administrative penalties.  If the Corporation is found guilty of impairing Jock River water quality, additional fines up to $6,000,000 could be imposed.

 


Timing

 

Timing is extremely important as it relates to the approval process and implementation of each alternative.  The most significant impact is associated with the additional costs to haul sewage from the Munster Lagoons to ROPEC, in accordance with the voluntary abatement program (approximately $500,000 per year).  The MOE has advised the time required to develop, approve and implement any alternative should be given full consideration in the decision-making process (reference Annex C).

 

It is extremely likely that a Phase 2 Order request will be submitted to the Minister should another addendum be prepared to implement an alternative solution to the approved pipeline.  There were several Phase 2 Order requests submitted regarding the ESR by TSH in 1996 and the addendum to the ESR by CRA in 1999.  Although, all requests were denied by the Minister, delays of approximately 5-9 months were experienced in both cases.  It is anticipated, due to the controversial nature and extensive history of this project, the EA approval process, including addressing Phase 2 Order requests, could take approximately 12-18 months to complete.

 

It is anticipated the time period for all alternatives to complete the design and preparation of tender documents and/or preparation of design/build documents is approximately 10 months.  Construction and commissioning is anticipated to be completed in an additional 12 months.

 

An estimated implementation timeline comparing the three alternatives is shown in Annex D.  This includes the impact of 12 month and 18 month periods to obtain EA approvals for the communal alternatives.

 

Costs

 

It is important to compare costs for each alternative as consistently and fairly as possible.  The challenge associated with the cost information prepared in previous reports is the technology proponents prepared actual “design/build” proposal costs with expectations that one of the alternatives would be implemented.  These costs were subsequently used as part of the EA process.  As time has progressed, proponents, in varying degrees, updated these costs and challenged consultant efforts to normalize the costs for comparison of each alternative.

 

Subsequent to the December 2002 RVA Report, additional comments and input have been received from the proponents and given appropriate consideration.

 

RVA has revised the capital cost and 20-year life cycle costing, for the pipeline, to reflect an inconsistency of accounting for costs associated with the hauling of sewage, not included in the other alternatives.

 

Other costs have been considered to reflect the anticipated actual costs of the implementation of each alternative.  These costs include technical requirements to secure a C of A (i.e., additional studies, investigations, etc.) and costs for hauling sewage based on timing of implementation.

 

The economic analysis completed by CRA, as part of the addendum process to the ESR, was based on a 20-year life cycle period.  RVA conducted their re-evaluation on the same basis, in accordance with the decision of the OMB.  Additional life cycle costing analyses for 60 and 90-year periods was subsequently conducted as a comparison assessment based on the following life expectancy and/or assumptions:

 

 

Based on the actual life expectancy of the infrastructure and implementation costs for each alternative, it is more appropriate to use a 60-year life cycle costing (including other costs) for comparison purposes.

 

A summary of capital costs and life cycle costing comparisons is shown on Annex E.

 

 

CONCLUSIONS

 

As indicated in the December 2002 RVA Report, from an environmental perspective, any of the three alternatives could be considered as a viable and acceptable solution.  RVA recommended the implementation of a communal wastewater treatment system.  The pipeline alternative was not selected as the preferred option primarily based on higher capital costs.

 

Based on a 60-year total life cycle costing (reference Annex E), the costs become very close for all alternatives and could be considered a neutral issue.

 

It comes down to two issues: timing of implementation and risks.

 

The City is currently at high-risk given the existing Munster Hamlet Wastewater Treatment Facility is in non-compliance with the C of A.  The receipt of an application for an investigation under the Environmental Bill of Rights for alleged contravention of the Environmental Protection Act and the Ontario Water Resources Act and the pending decision by the MOE heightens this risk.  The MOE has requested an updated action plan for resolution of the environmental problems at Munster.  The action plan must contain specific milestones and projected dates against which progress can be measured.  The adequacy of the existing voluntary abatement program is in question and under review by the Ministry.

 

There are high risks associated with the implementation of the communal alternatives.  It is anticipated the EA approval process could take approximately 12-18 months to complete.

 

There are risks associated with the ability to acquire additional land, as required for the Snowfluent® alternative in accordance with the MOE guidelines, and the potential for delays if expropriation procedures are necessary.

 

If the CMS alternative cannot meet the stringent MOE discharge criterion, the City would be out of compliance and be required to implement a plan to make the necessary changes.  The City would be at risk and could be charged under the provisions of the Environmental Protection Act and the Ontario Water Resources Act.  The extent of risk would be dependent upon how well the proponent protects the City by ensuring compliance.

 

If additional or unknown delays associated with obtaining approvals under the Environmental Assessment Act or obtaining a C of A, risks will escalate and costs incurred for additional hauling of sewage (approximately $500,000 per year).

 

There are low risks associated with the implementation of the pipeline alternative.  This alternative is 12 months and possibly 18 months ahead of the communal systems from the perspective that it is currently approved under the Environmental Assessment Act and does not require further process under this legislation.  The project can proceed to implementation.  The pipeline alternative is a secure and reliable option and can be designed and constructed to minimize risks of failure.

 

The pipeline alternative is recommended as the preferred solution for Munster Hamlet Wastewater Treatment.  The pipeline is a viable and effective solution that can be implemented in the shortest time period, at a reasonable cost and minimizes the overall risk to the City.  This will enable the City to resolve the environmental problems at the Munster Hamlet Wastewater Treatment Facility to the satisfaction of the MOE and OMB.

 

 

ACTION PLAN

 

Staff proposes to move forward with implementation of the pipeline solution immediately following Council approval.

 

Work under the existing agreement for Professional Engineering Services between the former ROC and Doran Contractors Limited, dated 18 January 2000, for completion of preliminary and detailed designs and project management for construction of the pumping station and forcemain, was stopped on 02 June 2000, pending the results of the OMB Hearing.  The agreement would need to be re-negotiated to ensure the scope of work addresses all issues that have been identified as time has gone on.  Some preliminary design has been done by Doran Contractors Limited.

 

It is recommended the project be completed using the traditional design, tender and construction method.  This type of project is typically delivered on this basis.  The uncertainty of rock quantities makes this a difficult type of contract to prepare on a “design/build” basis and there is minimal opportunity for innovation and potential cost savings that may be achieved through a “design/build” process.  The City is very experienced in delivering pipeline projects using traditional methods.  Pipeline installations are well prescribed by City standards and Provincial specifications.  Proceeding otherwise could introduce other unknown risks.  Assuming overall control and responsibility for the project by the City, at this time, will increase the likelihood of ensuring all related issues are appropriately assessed during the design and construction phases.

 

Accordingly, staff intends to terminate the agreement with Doran Contractors Limited.  Legal Services has advised the agreement can be terminated and without additional costs, in accordance with the terms and conditions.

 

Staff will proceed with the selection of an engineering consultant to complete the design and preparation of tender documents.  The design would include the following:

 

 

The project would be tendered in late winter 2004.  Construction would commence spring 2004 and be completed, including commissioning, by late spring 2005.  There are opportunities for reducing the overall construction period by tendering in multiple phases or imposing tight timelines to require contractors to fully utilize their maximum resources.

 

CONSULTATION

 

The project has involved extensive evaluations of treatment alternatives and public consultation carried out in accordance with the MEA Class Environmental Assessment process.

 

An information session was held on 16 December 2002 at the Munster Elementary School to discuss the results of the December 2002 RVA Report.

 

Further public consultation will be conducted as part of the design of the pipeline routing in Richmond.  The public will also be provided updated information regarding construction of the project by means of Public Notices and Public Information Sessions.

 

 

FINANCIAL IMPLICATIONS

 

The total estimated capital costs (reference Annex E) to implement the pipeline solution is $7,100,000 - $8,100,000.  Funding, in the 2002 Capital Budget, Order No. 900221, Munster Hamlet Wastewater Treatment Facility is as follows:

 

Approved Budget to Date

$12,642,000

Total Paid and Committed

$6,207,088

Balance Available

$6,434,912

 

By termination of the agreement with Doran Contractors Limited, an additional $1,025,587 will be available, for a revised Balance Available of $7,460,499.

 

Sufficient funds are available to proceed with the design and preparation of tender documents.  The 2004 Capital Estimates will identify additional funds for the project, if required, within the approved 2003 Capital Budget and four-year forecast, under the Waste Water Collection Program.

 

 

ATTACHMENTS

 

Annex A - Munster Hamlet Wastewater Systems Review Technical Memorandum by R.V. Anderson Associates Limited, dated 30 April 2003

Annex B - Pipeline Route from Munster Hamlet to Richmond

Annex C - Ministry of Environment (MOE) letter dated 18 March 2003

Annex D - Estimated Implementation Timelines

Annex E - Cost Comparisons for all Alternatives

 

DISPOSITION

 

Staff will proceed with the implementation of the pipeline solution, subject to Council approval.

 


ANNEX ‘E’

COST COMPARISON

 

 

No.

Cost Considerations

Alternative

 

 

Snowfluent®

(Northern Watertek)

Pipeline

 

CMS

(Seprotech)

 

1.

Capital (per Dec 2002 RVA report)

 

$3.3 - $3.7 M

$6.6 - $7.6 M

$3.5 - $4.3 M

2.

20-year life cycle (per Dec 2002 RVA report)

 

$5.0 - $5.4 M

$7.6 - $8.6 M

$5.7 - $6.4 M

3.

Capital (updated following review of Dec 2002

RVA report)

 

$3.3 - $3.7 M

$6.1 - $7.1 M

$3.5 - $4.3 M

4.

20-year life cycle (updated following review of Dec 2002 RVA report)

 

$5.0 - $5.4 M

$7.1 - $8.1 M

$5.7 - $6.4 M

5.

Other costs:

 

(a)   Technical requirements to complete EA,

       obtain C of A, etc.

 

(b)   Additional hauling costs based on timing of implementation.

 

 

 

$0.8 M

 

 

 

 

$1.5 M

 

 

(included in above capital costs)

 

 

 

        $1.0 M

 

 

$0.08 - $0.1 M

 

 

 

 

$1.5 M

6.

Total anticipated Capital

cost (incl. other costs)

 

$5.6-$6.0 M

$7.1 - $8.1 M

$5.1 - $5.9 M

7.

Total life cycle costing (including other costs):

 

(a)   20-year life cycle

 

(b)   60-year life cycle

 

(c)   90-year life cycle

 

 

 

 

$7.3- $7.7 M

 

$9.4 - $9.8 M

 

$9.5 - $9.9 M

 

 

 

$8.1- $9.1 M

 

$9.2 - $10.0 M

 

$8.9 - $9.7 M

 

 

 

$7.3 - $8.0 M

 

$9.4 - $10.2 M

 

$9.5 - $10.3 M