Modification
du tracé de la promenade Nixon sur une distance d’environ 300 mètres À la hauteur de la traversée abandonnée du
CP, située À 1,5 km au sud de la rue Main, dans l’ancien canton d’Osgoode
Committee
Recommendation As Amended
That this project be deferred
pending the outcome of the Rapid Transit Extension Study.
Recommandations du
ComitÉ modifiÉes
Que ce projet soit différé en attente du
résultat de l’Étude sur le prolongement du réseau de transport en commun
rapide.
Documentation
1. General
Manager, Transportation, Utilities and Public Works report dated 14 February
2002 is immediately attached (ACS2002-TUP-INF-0006).
2. A draft Extract of Minutes, 20 March 2002, immediately
follows the report and includes the voting record.
Report
to/Rapport au:
Transportation
and Transit Committee/
Comite des transports et des services de
transport en commun
and Council/et au Conseil
14 February 2002/le 14 février 2002
Submitted by/Soumis par: Rosemarie R.T. Leclair, General Manager/Directrice
généraleTransportation, Utilities and
Public Works/Transport, services et travaux publics
Contact/Personne ressource: Richard Hewitt,
Director of Infrastructure Services/Directeur des services et travaux publics
580-2424
ext. 21268, Richard.Hewitt@city.ottawa.on.ca
|
|
Ref N°: ACS2002-TUP-INF-0006 |
SUBJECT: |
The Realignment
of nixon drive for Approximately 300 metres at the abandoned cpr crossing
located 1.5 km south of main street in The Former Township of osgoode |
OBJET: |
MODIFICATION DU TRACÉ DE LA PROMENADE NIXON SUR
UNE DISTANCE D’ENVIRON 300 MÈTRES À LA HAUTEUR DE LA TRAVERSÉE ABANDONNÉE DU CP, SITUÉE À 1,5 KM AU SUD DE LA
RUE MAIN, DANS L’ANCIEN CANTON D’OSGOODE. |
REPORT RECOMMENDATIONS
That the Transportation and Transit Committee recommend Council approve:
1. the realignment of Nixon Drive for approximately 300 metres at the abandoned CPR Crossing as shown in Annex 3 (Drawing SM-3416-3);
2. that staff proceed with negotiations to acquire the property necessary to accommodate the proposed roadway realignment as shown in Annex 4 (Drawing SM-3416-4).
RECOMMANDATIONS
DU RAPPORT
Que
le Comité des transports et des services de transport en commun recommande au
Conseil municipal d’approuver :
1. la modification du tracé de la
promenade Nixon sur une distance
d’environ 300 mètres
à la hauteur de la traversée abandonnée
du CP, tel qu’il est indiqué dans l’annexe 3
(Plan SM‑3416‑3);
1. la modification du tracé de la
promenade Nixon sur une distance d’environ 300 mètres à la hauteur de la
traversée abandonnée du CP,
tel qu’il est indiqué dans l’annexe 3 (Plan SM‑3416‑3);
2. 2. que
le personnel entreprenne des négociations en vue de l’acquisition de la
propriété
nécessaire à la modification du
tracé proposée, tel qu’il est indiqué dans l’annexe 4
Plan SM-3416-4).
The current alignment of the road at the former CPR crossing consists of two back-to-back curves. This alignment is considered to be sub-standard. In the summer of 2001, the City of Ottawa engaged a consultant for the engineering design of the road realignment project. The final design was completed in the fall and presented at a Public Open House, which was held on 06 November 2001, at the Osgoode Community Centre.
In advance of
the meeting, a request was made by a resident, to have a multi-way stop control
installed, at the intersection of Nelson Street and Nixon Drive, which is
located just north of the proposed realignment. This request was made in anticipation of the realignment project
proceeding. The information was
forwarded to the Traffic and Parking Operations Branch for their review and
recommendation.
ANALYSIS
Existing
Conditions
There are no sidewalks along either side of the road. An eight-hour pedestrian/vehicle survey was conducted previously. Throughout the duration of this survey there was no pedestrian traffic identified south of Main Street on Nixon Drive.
There
are currently no special provisions for bicycles on this roadway. Bicycles must share the road with
vehicles. During the above-noted survey
one cyclist was observed on Nixon Drive.
Transit
There
is no transit service in this area.
The traffic count also indicated that 568 vehicles used Nixon Dive during the eight-hour survey timeframe. Between 01 January 1998 and 01 January 2002, one accident was reported within the section of roadway where the curves are located.
DISCUSSION
Design
Proposal
The
design that was selected provides the most appropriate solution, andwhile deliversing an
improved level of service, in a cost-effective manner. In essence, the proposed design allows for
the roadway to be realigned, in order to eliminate the existing curvature. The proposed straightened section of roadway
would will by-pass
the two existing sub-standard curves, as shown in Annex 3.
To
accommodate the realigned section of roadway, property on both sides of Nixon
Drive must be purchased. The property
acquisition requirements are shown in Annex 4.
Design
Features
Removal
of the back-to-back curves along this section of roadway will provide
significant improvements in sight distances and roadway safety.
CONSULTATION
The proposed roadway realignment modifications fall under Schedule “A”
of the Class Environmental Assessment for Municipal Road Projects.
As required by the “ Municipal Act of Ontario”, a notice of the proposed
roadway modifications has been placed in Le Droit and the Ottawa Citizen
newspapers, for four consecutive weeks, starting on 22 February 2002.
This
report has been circulated to the area Ward Councillor
for comments.
In addition, notice of the Open
House, which was held on 06 November 2001 at the Osgoode Community Centre, was
mailed to local residents. Display
boards that showed the proposed realignment details, were on hand for the
public to view and comment on.
Many residents submitted written
comments, which were compiled and sent to the local Councillor, as well as to
the Traffic and Parking Operations Branch.
Many of the residents were concerned that the proposed removal of the
curves in the roadway would be an unnecessary measure and would lead to higher
vehicle speeds along Nixon Drive in this area.
A suggestion was made, by several local residents in attendance, that the installation of a multi-way stop control at Nixon Drive and Nelson Street would help to reduce the anticipated higher speeds that would be expected from the roadway realignment.
The City has recently completed a
traffic survey at the intersection and found that the warrants were not met for
the installation of a multi-way stop control.
The warrant criteria for the installation of all-way stop controls, is
based on guidelines recommended in the Ontario Traffic Manual.
In summary,
based on current vehicle and pedestrian volumes, collision experience and
visibility conditions, the installation of an all-way stop control is not being
recommended at this intersection.
The total estimated cost for the
construction of the realignment, including engineering, construction
supervision and property acquisition, is $200,000 (this includes G.S.T.). The 2001 Capital Budget approved $100,000 in
funding for this project. Additional
funds in the amount of $100,000 has been will be requested
in the 2002 Capital Budget.
DISPOSITION
Subject to approval of the
recommendations contained in this report by Council, and barring any
significant delays in acquiring property, construction willcould begin
in the summer of 2002 and be completed by the fall.
ATTACHMENTS
Annex 1 - Key Plan
Annex 2 - Existing Geometry
Annex 3 - Proposed Geometry
Annex 4 - Required Property
Extract
of Draft Minutes 22 20
March 2002 |
|
Extrait de l’ébauche du procÈs-verbal
22 - 20 mars 2002 |
The Realignment of nixon drive for Approximately
300 metres at the abandoned cpr crossing located 1.5 km south of main street in
The Former Township of osgoode – PUBLIC HEARING
MODIFICATION DU TRACÉ
DE LA PROMENADE NIXON SUR UNE DISTANCE D’ENVIRON 300 MÈTRES À LA HAUTEUR DE LA
TRAVERSÉE ABANDONNÉE DU CP, SITUÉE À 1,5 KM AU SUD DE LA RUE MAIN, DANS
L’ANCIEN CANTON D’OSGOODE – AUDIENCE PUBLIQUE
ACS2002-TUP-INF-0006
David
Glastonbury, Transportation Task Force, Greater Ottawa Chamber of Commerce
highlighted the importance of protecting abandoned railway corridors for future
transit development. The realignment of
Nixon Drive affects one of these corridors.
The Chamber of Commerce therefore asks that the City to be guardians of
these transit corridors and to closely examine all incursions on their future
integrity and, if not already done so, the City should take steps to protect
this corridor for future transit use.
While he agreed that attempts to straighten out Nixon Drive makes sense,
Mr. Glastonbury wanted to ensure that committee was aware of the value of these
future transit corridors.
Chair
Meilleur noted the City will be entering into a study regarding the expansion
of public transit and would not want to endanger expansion of the O-Train in
different corridors. She asked whether
it would be possible to approve the report today, but that construction not
begin until the Rapid Transit Expansion Study is completed. The Director of Infrastructure, Richard
Hewitt, advised that this project would not preclude the use of the rail
corridor for the O-Train or other transit purposes. He confirmed that the proposed realignment utilizes more of the
corridor than the existing crossing does, so if the City were to proceed, at
the time of a future use, the design would take into account the new geometrics
of a crossing. He could see no reason
the project could not be deferred pending the outcome of that study.
Some
committee members believed that should the committee proceed with the
realignment now, it would be more costly to grade separate in the future, if
the O-Train were to be brought through this corridor. Mr. Hewitt explained that even if the rail corridor were
developed, it would not be a simple matter of just looking at the existing
roadway, because that substandard alignment would have to be corrected at that
time. In either event, therefore, the
City would have to deal with the road at such time as the rail corridor is
developed. He added that whether or not
the road is realigned this year, if the rail corridor is used for transit
purposes in the
future, a grade separation would be required and detailed design would have to
be undertaken in order to develop specifically how that crossing would occur.
Extract
of Draft Minutes 22 20
March 2002 |
|
Extrait de l’ébauche du procÈs-verbal
22 - 20 mars 2002 |
David
Jeanes, Transport 2000 fully supported the comments made by the
representative of the Chamber of Commerce.
He was very concerned, however, that the City is missing an opportunity
to consider this matter properly. As a
member on the Public Advisory Committee for the Rapid Transit Expansion Study,
he disagreed that a grade separation would be required in the future, because
this is not the practice in other major cities that have light rail
systems. In this regard, he believed
the consultant hired to conduct the study would have the necessary expertise
and should be able to comment on what the cost of future grade separation of
level crossings would be. He suggested
that with such a narrow crossing angle, the length of any grade separation
would make it far more expensive than a grade separation that would have to be
done with the present alignment. It
would also be a very dangerous crossing because of that shallow angle. He was disappointed that none of these
issues were addressed in the report before committee.
While he understood there are
safety concerns that need to be addressed with respect to the existing
alignment of the road, Mr. Jeanes suggested that the impact of those should be
addressed by the aforementioned Study, whose recommendations may be precluded
by the decision made today. He
suggested, therefore, that committee wait before making a decision on the
realignment, until the Rapid Transit Expansion Study has been completed, noting
this is anticipated to be done in 8-10 months.
The
General Manager advised it is possible to delay the construction of the
realignment until the completion of the study, at which time the future of the
corridor would clearly be defined.
Depending on the decision re grade separation requirements, there may be
a need to redesign the road realignment and construction could proceed early in
2003.
Councillor
Thompson indicated that while there is a bad curve on Nixon Drive, which will
have to be addressed sooner or later, he recognized it is not a high profile
issue and was not concerned about delaying the work for several months. Staff confirmed the funding for this
realignment would be set aside for this project.
Moved by A. Cullen
That this project be deferred
pending the outcome of the Rapid Transit Extension Study.
CARRIED
ANNEX 1
ANNEX 2
ANNEX 3