5. public-private
partnership (p3) for new indoor sports field dome at ben franklin park partenariat
public-privÉ pour un dÔme de terrain de sport intÉrieur au parc ben franklin |
That Council authorize staff to issue a request for proposals for the provision of an indoor sports field dome at Ben Franklin Park per the framework attached in Appendix A.
RECOMMANDATIONS
DU COMITÉ
Que le Conseil autorise le personnel
à lancer une demande de propositions pour l’aménagement d’un dôme de terrain de
sport intérieur au parc Ben-Franklin, conformément au cadre décrit à l’annexe
A.
DOCUMENTATION
1.
Deputy City Manager, Community and Protective Services report dated 9
January 2006 (ACS2006-CPS-PAR-0001).
2.
Extract of Draft Minutes, 19 January 2006.
Report
to/Rapport au :
Health, Recreation and Social Services Committee
Comité de la santé, des loisirs et des
services sociaux
and Council/et au Conseil
9
January 2006 / le 9 janvier 2006
Submitted
by/Soumis par : Steve Kanellakos, Deputy City Manager/Directeur
municipal adjoint,
Community and Protective Services/Services communautaires et de
protection
Contact
Person/Personne ressource : Aaron Burry
Director,
Parks and Recreation
(613)
580-2424 x23666, Aaron.Burry@ottawa.ca
SUBJECT: |
Public-Private partnership (P3) for
new indoor sports field Dome at ben Franklin Park |
|
|
OBJET : |
Partenariat
public-privé pour un dÔME DE TERRAIN DE SPORT INTÉRIEUR AU PARC BEN FRANKLIN |
REPORT RECOMMENDATION
That the Health Recreation and Social Services Committee recommend that Council authorize staff to issue a request for proposals for the provision of an indoor sports field dome at Ben Franklin Park per the framework attached in Appendix A.
RECOMMANDATION DU
RAPPORT
Que le Comité de la
santé, des loisirs et des services sociaux recommande au Conseil d'autoriser le
personnel à lancer une demande de propositions pour l'aménagement d'un dôme de
terrain de sport intérieur au parc Ben-Franklin, conformément au cadre décrit à
l'annexe A.
Ben Franklin Park is a large,
21.55 hectare park, located in the north-east corner of the intersection of
West Hunt Club Road and Greenbank. The site's master plan (December 2000)
foresaw a premium sports field development with indoor and outdoor sports
fields and park amenities. The park is divided into two major parcels of land,
seperated by Knoxdale Road. Phase 1 (12.6 hectare portion east of Knoxdale) was
City funded through Nepean's Reserve Fund and constructed in 2004. Phase 1
includes four (4) sports fields, which will be ready for play in the Spring of
2006. Basic amenities such as a parking lot and a fieldhouse are in place and a
play structure will be constructed in 2006.
Phase 2 of the development (west
side of Knoxdale Road at 12.6 hectares) per the Master plan was intended to
house an indoor sports facility, as well as outdoor fields, parking, play areas
and landscape features.
Since the development of the City's Public-Private
Partnership policy framework and completion of the new P3 Indoor dome at
Hornet's Nest, various sports groups and the private-sector have expressed
interest in developing the site under a P3.
Funds in the amount of $2,079,000 were approved as part of the 2006
capital budget and the Department, in conjunction with Supply Management
Division, proposes to issue a request
for proposals in keeping with the framework attached in Appendix A.
The
framework calls for a high quality, enclosed (year-round) dome/structure with
artificial turf, able to accommodate sports groups such as soccer, ultimate
frisbee, rugby. In addition to the structure, additional, high quality
(irrigated) outdoor sports fields would be an added asset to any proposal. The site should be self-sustaining and
provide for users parking requirements on-site and amenity services for the
outdoor fields. The framework being
recommended requests that the indoor and outdoor facilities be managed and
maintained by the successful P3 proponent.
Following review of the submitted
proposals, the Department will report back to Committee and Council with a
recommendation to Committee and Council on the private sector partner(s)
recommended to pass on to Stage 2 – Negotiations and Final Agreement. A negotiation framework, including a public
consultation component, will also be recommended at that time.
Le parc
Ben-Franklin occupe une superficie considérable, soit 21,55 hectares, à l'angle
nord-est de l'intersection des chemins West Hunt Club et Greenbank. Le plan
directeur de l'emplacement (décembre 2000) prévoyait l'aménagement d'un parc
sportif de premier plan, comprenant des terrains de sport intérieurs et
extérieurs et les commodités afférentes. Le parc est divisé en deux grandes
parcelles par le chemin Knoxdale. L'étape 1 de l'aménagement (la parcelle de
12,6 hectares à l'est du chemin Knoxdale), financée par la Ville à partir du
Fonds de réserve de Nepean, a été réalisée en 2004. L'étape 1 comprend quatre
(4) terrains de sport, qui seront utilisables à partir du printemps de 2006.
Les équipements de base, comme le terrain de stationnement et le pavillon, sont
en place et une structure de jeux sera construite en 2006.
L'étape 2 de l'aménagement (la parcelle de 12,6
hectares à l'ouest du chemin Knoxdale) devait, selon le plan directeur,
comprendre un terrain de sport couvert, ainsi que des terrains extérieurs, un
stationnement, des aires de jeux et des éléments paysagers.
Depuis la mise en place du cadre stratégique de
la Ville sur les partenariats publics-privées (PPP) et l'achèvement du dôme à
Hornet's Nest en vertu d'un PPP, différents groupes sportifs et le secteur
privé se sont montrés intéressés à aménager le site en vertu d'un PPP. Un
montant de 2,079,000 $ a été approuvé à cette fin dans le budget
d’immobilisations de 2006, et les Services communautaires, en conjonction avec
la Division de la gestion de l’approvisonnement, se proposent de lancer une
demande de propositions, conformément au cadre décrit à l'annexe A.
Ce cadre prévoit la construction d'un dôme ou
d'une structure fermée (toutes saisons) abritant un terrain couvert de gazon
synthétique et se prêtant à des activités sportives comme le soccer, le jeu
Ultime et le rugby. Outre cette structure, des terrains de sport extérieurs
supplémentaires de haute qualité (irrigués) constitueraient, pour toute
proposition, un atout avantageux. Le parc sportif devrait être financièrement
autonome et offrir sur place le stationnement à ses utilisateurs, ainsi que les
services et commodités pour les terrains extérieurs. Le cadre recommandé
prévoit que les installations intérieures et extérieures seront gérées et
entretenues par le promoteur du P3 retenu.
À la suite de l'examen des propositions
reçues, les Services communautaires présenteront au Comité et au Conseil un
rapport contenant une recommandation quant au(x) partenaire(s) du secteur privé
à retenir pour la deuxième étape du processus (négociation et accord final). Un
cadre de négociation, y compris son volet de consultation du public, fera
également l'objet d'une recommandation dans le même rapport.
BACKGROUND
In the Branch's Community Infrastructure Strategy and its Long Range Financial Plan 2, three (3) Indoor Sports Domes were identified as a requirement over the next 10 years. The intent is to see additional domes strategically located throughout the City that would offer an "enhanced" level of service for indoor sport participants. Because this is beyond our basic level of service (outdoor fields) and restrained financial resources, domes are deemed to require substantial outside funding in order to be successfully built in the near future. In 2004, the City's first indoor dome partnership was developed at Hornet's Nest on Bearbrook Road. As an "added value" to sports users, an indoor sports component was added in the City's P3 partnership with the four-plex arena at the Sensplex.
DISCUSSION
Since there have been several inquiries and expressions of interest in developing an indoor sports dome at the site by the private-sector and sports groups, an opportunity exists to initiate an open Request for Proposals to all that are interested in pursuing a partnership with the City. In order to clearly establish the requirements and expectations of the City, including the limitation of site, the Framework (attached as Appendix A) identifies the parameters of the project that the City is prepared to entertain and evaluate.
The framework calls for a high quality, enclosed (year-round) dome/structure with artificial turf, able to accommodate sports groups such as soccer, ultimate frisbee, rugby. In addition to the structure, additional, high quality (irrigated) outdoor sports fields would be an added asset to any proposal. The site should be self-sustaining and provide for users parking requirements on-site and amenity services for the outdoor fields. The framework requests that the indoor and outdoor facilities be managed and maintained by the third party proponent.
Following a review of the
submitted responses to the RFP, staff will make a recommendation to Committee
and Council on the private sector partner(s) recommended to pass on to Stage 2
– Negotiations and Final Agreement. A
negotiation framework, including a public consultation component, will also be
recommended at that time.
It is possible, that following
the evaluation of the proposals, no respondents are recommended to proceed to
the next stage.
It should be noted that Coliseum Inc., the operators of the dome at Lansdowne Park, in the amended agreement arising out of the settlement of the dispute involving scheduling conflicts with late season football games, were given the right to remain at Lansdowne Park until March 2015, unless there was a bona fide redevelopment plan for Lansdowne Park that would preclude their seasonal operation.
If there is a bona fide redevelopment of Lansdowne Park, "the City agrees at that time to grant Coliseum Inc. an option to lease a portion of Ben Franklin Park. If Ben Franklin Park is at the time of exercise of the option to lease, the subject of any bona fide redevelopment plan which precludes the installation of an inflatable dome structure of the kind currently operated by Coliseum Inc., then the City agrees to grant an option to lease to Coliseum for a similar City-owned property within a 10 kilometer radius of Frank Clair Stadium".
The Department considers the above to be low risk scenarios and the Parks and Recreation branch is prepared to examine alternate sites should the need arise.
CONSULTATION
This report has not been the subject of a public consultation, but the proposal will be subject to a consultation process, undertaken by the preferred proponent, in conjuction with the City.
FINANCIAL IMPLICATIONS
The 2006 capital budget includes $2,079,000 in funds available to meet City obligation in the partnership.
SUPPORTING DOCUMENTATION
Appendix A - Request for Proposal (RFP) Framework
DISPOSITION
Upon
approval of this report, the Parks and Recreation Branch will form a team of
Departmental representatives, to implememt the project, including Parks and
Recreation, Planning and Growth Management and Corporate Services, with Supply
Management Division taking the lead in
the procurement process.
Appendix A
PROPOSED P3
FRAMEWORK
The
rapidly increasing popularity of a number of sports such as soccer and ultimate
frisbee, as an example, and the impressive increase in population over the past
few years have created significant pressures on the need for additional outside
playing facilities. Equally important
is the need for domed/indoor playing facilities to allow for winter access. Implicit with these facilities is the need
for artificial turf, similar to the surface installed at Hornet's Nest.
There
has been significant interest shown by the private sector and sports leagues to
partner with the city to advance the construction of these types of facilities
and it is recommended that this project proceed as a public-private
partnership. The process has been designed to offer the potential partners the
opportunity to bring forth innovative solutions, which meet the City’s overall
objectives.
1.0
Site Specific Parameters
1.1
Site Infrastructure
The
City-owned site in question is undeveloped lands, with no existing services
on-site. The development proposal will need to include service connections from the Gibbard Street
Right-of-Way, as well as storm water attenuation requirements. A traffic plan
will need to be persued, looking closely at access and egress and with possible
works required as a consequence.
1.2
Zoning
The
proposed partnership would seek to entertain proposals that will respect the
existing zoning, which is identified as Parks and Recreation (Public) under the
existing Nepean Zoning By-Law. The designation allows for City-owned sports
facilities or P3 development of the same. In order to respect the zoning, the
commercial development portion within the project must only support the
recreational facility and if deemed to go beyond the scope, a re-zoning would
be required. The City's preference is to maintain the existing zoning.
1.3
Required Elements
The
City's intent is to develop in partnership, a high quality, enclosed
(year-round) dome/structure with artificial turf, able to accommodate sports
groups such as soccer, ultimate frisbee, rugby. In addition to the structure,
additional, high quality (irrigated) outdoor sports fields would be an added
asset to any proposal.The site should be self-sustaining and provide for users
parking requirements on-site and amenity services for the outdoor fields.
1.4
Operational Elements
The
City is not interested in managing or maintaining the indoor and outdoor
facilities, nor the purchase of time on behalf of sports group. Proponents may
wish to consider the newly-developed (4) outdoor fields on the east portion of
the park as part of a comprehensive partnership proposal to the City. Presently
the City maintains and will be allocating the outdoor fields.
2.0
Selection of Preferred P3 Partner
2.1
The selection process will consist of two stages:
Stage
1 – Request for Proposal (RFP): The
objectives of the RFP are to:
This
process will validate the feasibility of the concept from a financial,
operational and “fit” perspective. The
evaluation will take into consideration the amount of risk retained by the City
and the value of the facility to the City’s overall programming ability on that
site.
Generally
the city will evaluate the responses based on the following elements:
Corporate
Overview
Project
Overview
Business
and Financial Plans
Design,
Development and Construction Plans
Operations
and Maintenance Plans
Customer
Service and Community Relations
Value
Added Elements
The
RFP will be developed in conjunction with Supply Management Division . It will include the standard requirements
plus specifics to this project such as:
Following
the RFP process, staff will make a
recommendation to Committee and Council on the outcome of the P3 process, and
if successful, the preferred private sector partner(s) recommended to pass on
to Stage 2. It is also possible,
however, that following the evaluation of the proposals, no respondents are
recommended to proceed to the next stage.
A
negotiation framework, including a public consultation component, will also be
recommended at that time.
Stage
2 – Negotiations and Final Agreement:
The purpose of this phase is to formalize the agreement with the
respondents.
The
City is seeking partners who will provide the best value solution in a manner
that recognizes the importance of fitting that solution within the community
within which they operate. They will
operate the facility in a way that reflects the image of the City and provide a
quality service to the users. They will
support the City on issues management and by being responsive to the City’s
needs, adjusting to an environment that may change over the course of the
partnership. The partner will also seek
to provide value-added services during the term of the agreement, continuing to
apply best practices in this area of activity.
3.0 Timelines
HRSS
and Council approval for RFP Authority - Jan 19 & Feb 8, 2006
Request
for Proposal Release Date - Mar 15, 2006
Proposal
Due Date
Apr 12, 2006
Selection
of Preferred Partner
Apr 26, 2006
Report
to CSED and Council - Preferred Partner Negotiate Jun 6 & Jun 14 (or 28) 2006
Negotiation
(estimated completion date) July /
August 2006
Report
to CSED and Council - Agreement First Available dates in September 2006
Construction
- Anticipated Opening Date
September 2007
PUBLIC-PRIVATE PARTNERSHIP (P3) FOR NEW INDOOR SPORTS FIELD DOME AT BEN FRANKLIN PARK
PARTENARIAT PUBLIC-PRIVÉ POUR UN DÔME DE TERRAIN DE SPORT INTÉRIEUR AU
PARC BEN FRANKLIN
ACS2006-CPS-PAR-0001 KNOXDALE-MERIVALE (9)
Aaron Burry, Director of Parks and
Recreation, provided Committee with a brief overview of the report.
In reply to a number of questions
from Vice Chair Alex Cullen, Mr. Burry confirmed that the evaluation of the
capital and operating elements were consistent with that of other projects, as
well as the ability of the City to deliver these services. He also reaffirmed that the City was not
interested in managing or maintaining the indoor and outdoor facilities, nor
the purchase of time on behalf of sports groups.
Councillor Cullen put forward a
Motion asking that staff be directed to develop a capital project for the
facility at Ben Franklin Park, to be considered as part of the 2007 Capital
budget process. The Councillor put
forward the view that a public process was the most efficient model, as has
been demonstrated over the past one hundred and fifty years in the City of
Ottawa.
Councillor Georges Bedard asked
that, in future, projects like this be prioritised to help in the
decision-making tool. The Councillor
also asked Mr. Burry whether the City was obligated to accept any of the
Requests for Proposals and whether developing this project could be
reconsidered at any time. Mr. Burry
confirmed this was the case in both scenarios.
Speaking to Councillor Cullen's
replacement Motion, Councillor Gord Hunter (Knoxdale Ward), felt it was
important to see what the private and not-for-profit sectors could come up with
and too early in the process to decide that a P3 model was not suitable. He asked that staff indicate how it would
respond to a group interested in developing a domed facility at an existing
facility as opposed to Ben Franklin Park.
Mr. Burry advised that the first P3 project evaluation for a facility at
Minto Park had been deemed not appropriate, and that staff would have to also
look at how much more the Sportsplex site is able to accommodate.
Councillor Jan Harder (Bell-South
Nepean) pointed out that the location of Ben Franklin Park makes it a city wide
facility, and will benefit from the extension of Hunt Club Road to Highway 417
later this year. She averred that staff
have a window of opportunity and need to move on this proposal. The Councillor reminded the committee that
this was part of the Nepean Legacy Fund and paid for by residents of that
former municipality.
In reply to a question from Chair
Diane Holmes, Mr. Burry said it was difficult to estimate the cost of this
project if the City were to completely fund it, citing unknown factors such as
capital and operating costs at the back end.
At this juncture, the committee considered the
following amending Motion:
That the
Health, Recreation and Social Services Committee direct staff to develop a
capital project for an indoor sports field dome at Ben Franklin Park for the
2007 Capital budget.
LOST
NAYS (4): G. Bedard, P. Feltmate, J. Stavinga,
D. Holmes
YEAS (1): A. Cullen
That the Health Recreation and Social
Services Committee recommend that Council authorize staff to issue a request
for proposals for the provision of an indoor sports field dome at Ben Franklin
Park per the framework attached in Appendix A.
CARRIED