5.       APPLICATION FOR NEW CONSTRUCTION IN THE
BANK STREET HERITAGE CONSERVATION DISTRICT


DEMANDE DE NOUVELLE CONSTRUCTION DANS LE DISTRICT
DE CONSERVATION DU PATRIMOINE DE LA RUE BANK


 

 

Committee recommendation as amended

 

That Council approve the application received on April 4th, 2006 for new construction at 119-121, 125, 127 Bank Street and 215 Slater Street, received on April 4, 2006.

 

(Note: Approval to Alter this property under the Ontario Heritage Act must not be construed to meet the requirements for the issuance of the building permit.)

 

 

Recommandation modifiÉe du Comité

 

Que le Conseil approuve la demande de nouvelle construction aux 119-121, 125 et 127 de la rue Bank et au 215 de la rue Slater, reçue le 4 avril 2006.

 

(Nota : L’approbation de modification de la propriété aux termes de la Loi sur le patrimoine de l’Ontario ne signifie pas qu’elle satisfait aux critères de délivrance d’un permis de construire.)

 

 

 

 

 

Documentation

 

1.         Deputy City Manager's report (Planning and Growth Management) dated
18 April 2006 (ACS2006-PGM-APR-0097).

 

2.         Extract of Draft Minute, 9 May 2006.

 



Report to/Rapport au :

 

Local Architectural Conservation Advisory Committee

Comité consultatif sur la conservation de l'architecture locale

 

and / et

 

Planning and Environment Committee

Comité de l'urbanisme et de l'environnement

 

and Council / et au Conseil

 

18 April 2006 / le 18 avril 2006

 

Submitted by/Soumis par : Ned Lathrop, Deputy City Manager/

Directeur municipal adjoint,

Planning and Growth Management/Urbanisme et Gestion de la croissance 

 

Contact Person/Personne ressource : Grant Lindsay, Manager

Planning and Infrastructure Approvals/Approbation des demandes d’aménagement et d’infrastructure

(613) 580-2424 x13242, grant.lindsay@ottawa.ca

 

Somerset (14)

Ref N°: ACS2006-PGM-APR-0097

 

 

SUBJECT:

APPLICATION FOR NEW CONSTRUCTION IN THE BANK STREET HERITAGE CONSERVATION DISTRICT.

 

 

OBJET :

DEMANDE DE NOUVELLE CONSTRUCTION DANS LE DISTRICT DE CONSERVATION DU PATRIMOINE DE LA RUE BANK

 

 

REPORT RECOMMENDATION

 

That the Local Architectural Conservation Advisory Committee recommend that Planning and Environment Committee recommend that Council refuse the application for new construction at 119-121, 125, 127 Bank Street and 215 Slater Street, received on April 4, 2006.

 

(Note: Approval to Alter this property under the Ontario Heritage Act must not be construed to meet the requirements for the issuance of the building permit.)

 

RECOMMANDATION DU RAPPORT

 

Que le Comité consultatif sur la conservation de l’architecture locale recommande au Comité de l’urbanisme et de l’environnement de recommander à son tour au Conseil de refuser la demande de nouvelle construction aux 119-121, 125 et 127, rue Bank ainsi qu’au 215, rue Slater, reçue le 4 avril 2006.

 

(Nota : L’approbation de modification de la propriété aux termes de la Loi sur le patrimoine de l’Ontario ne signifie pas qu’elle satisfait aux critères de délivrance d’un permis de construire.)

 

 

Local Architectural Conservation Advisory Committee Recommendation - 27 April 2006

 

Contrary to the departmental recommendation, LACAC recommends approval of the proposed revised design.

 

 

BACKGROUND

 

This report has been prepared to allow for the construction of a new office building at the above address, which is included within the boundaries of the Bank Street Heritage Conservation District, designated under Part V of the Ontario Heritage Act (By-law 175-2000). The Ontario Heritage Act requires that new construction in a heritage conservation district be approved by City Council before a heritage permit and a building permit can be issued. (see Document 1).

 

The proposal for the Telus building involves the demolition of four buildings; 119-121 Bank Street, 125 Bank Street, 127 Bank Street and 215 Slater Street. City Council approved the demolition of these buildings under the Ontario Heritage Act on March 8, 2006.  At that meeting, City Council also approved the construction of a new building on the site with part of 119‑121 Bank Street restored and incorporated into the new design.  This report has been prepared in response to a new application submitted by the applicant that slightly alters the original design. 

 

 

ANALYSIS

 

The new application for construction on the site is essentially the same as previously approved, however, the historic mansard roof element to be removed and reinstated at 119-121 Bank Street is not included in this version (please refer to Document 2). When the original plans were presented at the Local Architectural Conservation Advisory Committee (LACAC) meeting of February 8, the discussion focussed on whether or not the reinstatement of the roof element was heritage preservation and whether its retention enhanced or detracted from the rest of the building and from the streetscape.  In its discussion, LACAC considered the comments of the Downtown Ottawa Urban Design (DOUDS) team on the proposal. The comments, included here as Document 3,  did not support the removal and reinstatement of the historic roof element stating that:

 

The panel is of the view that the gesture to heritage conservation shown in the project weakens the urban design of the project while not making a significant contribution to the maintenance of the City's heritage.

 

After the meeting, given that LACAC did not establish a recommendation, and the opinion of the DOUDs team, the applicant submitted the current application for the building.  The restoration architect for this project included the reasons for the re-submission in a document included as Document 4.  In summary, the architect states:

 

This is not a major redesign, but rather an evolution from the previous design.  We have taken the time to do these revisions and refinements because the previous design was not embraced by either of the City’s design review committees [LACAC and the DOUDS].  It is our belief that the current revisions reflect a broader consensus on how to best marry the past, present and future of this prominent site.

 

The new plans show the building to be essentially the same as the previously-approved structure but instead of a two storey projecting bay with a mansard roof, the current version has a two storey projecting bay that features the same fenestration pattern and materials as the rest the building and sloping windows above the sign band.

 

The Planning and Growth Management Department does not support the new submission. The Department believes that the mansard roof is a meaningful fragment from Bank Street's past and ought to be preserved in the context of the Bank Street Heritage Conservation District. The Department believes the previously approved removal and reinstatement of the historic mansard roof  and the setbacks of a the new building will make a positive contribution to the character of Bank Street immediately north of Slater Street, and the eight-storey curtain wall structure, with its clean contemporary design and new storefronts will animate the corner of Bank and Slater Streets. This position is consistent with the staff recommendation on the previous application approved by Council on 08 March 2006.

 

 

CONSULTATION

 

Adjacent property owners and residential tenants were notified by letter of the date of the Local Architectural Conservation Advisory Committee and Planning and Environment Committee meetings and were provided with comment sheets to be returned to LACAC.

 

The Councillor is aware of this application under the Ontario Heritage Act.

 

Councillor Holmes reviewed the initial plans for the project and her comments were:

 

"On the matter of the retention of the mansard roof, I have some problems with this approach to preservation."

 

 

FINANCIAL IMPLICATIONS

 

N/A

 

 


SUPPORTING DOCUMENTATION

 

Document 1      Location Map

Document 2      Elevations

Document 3      Comments, Downtown Ottawa Urban Design Team

Document 4      Comments, Julian Smith, Architect

 

 

DISPOSITION

 

The Corporate Services Department, Council and Committee Services Branch, to notify the applicant/ agent Richard Chmiel (Richard Chmiel, Architect and Associates, 109 Bank Street, Ottawa, Ontario, K1P 5N5) and the Ontario Heritage Trust ) 10 Adelaide Street, 3rd Floor, Toronto, Ontario, M5C 1J3) of  City Council's consent for demolition and new construction.


DOCUMENT 1

 

LOCATION MAP                                                                                                                            


DOCUMENT 2

 

ELEVATIONS                                                                                                                                  

 



DOCUMENT 3

 

COMMENTS, DOWNTOWN OTTAWA URBAN DESIGN TEAM                                          

 

Heritage Response

 

The panel is of the view that the gesture to heritage conservation shown in the project weaken the urban design of the project while not making a significant contribution to the maintenance of the City's heritage. The unfortunate reality is that the scale of the heritage buildings is too small to be translated into the new scheme, and the saving of small portion takes them too far out of context to maintain their credible use. The panel finds that reuse of the portion of mansard roof on Bank St. and the introduction of the frame structure on Slater distracts from the development of improved grade conditions.

 

Deletion of the heritage elements of the project would shift the emphasis on the Bank St. elevation away from the second floor line, to the ground floor expression and the fourth floor line, which is the roofline of the northern portion of the block and to some degree the block immediately to the south. This more accurately represents the development of the street facade. The rhythm of the punched openings at the ground floor facades of the buildings to the immediate north is suggested as an appropriate element for repetition. The treatment of the upper floor facades of the same buildings is also of interest and to some degree is reflected in the Slater St. facade treatment.

 

The panel recommends that the comments provided above be addressed by LACAC in their review of the project design and in their recommendations to Council for this project. The panel further recommends that the City, through the site plan approval process address the comments of the panel that relate specifically to site development matters, most notably the streetscape and roof top terraces.

 

 

Respectfully Submitted.

 

DOUDS Review Team:

Robert Matthews

David Leinster

Stephen Pope


DOCUMENT 4

 

COMMENTS, JULIAN SMITH, ARCHITECT                                                                           

 

Julian Smith & Associates, Architects

206 James Street, Ottawa, ON  K1R 5M7

Tel: (613) 234-3338

Fax: (613) 234-7778

julian@juliansmitharchitects.ca

 

 

Statement: Burkholder Building

 

Richard Chmiel Architect & Associates have worked closely with the developer, Toth Equity Limited, with City of Ottawa heritage staff, and with heritage consultant Julian Smith & Associates, to develop an appropriate and sensitive design for the Telus Building project at 199 Slater Street.  We had initially developed two possible approaches to the heritage of the Burkholder Building, identified in previous studies as the one element on the site worthy of attention.

 

The first option was to remove, repair and reinstate the mansard roof element of the Burkholder Building, the one surviving fragment of the original building with heritage interest.  The other option was to reinterpret the two-storey façade of this heritage property in a contemporary idiom, respecting the urban design heritage but accepting the fact that most of the original façade had been lost.

 

In consultation with the heritage staff at the City, we developed the first option in our design presentations to the Design Review Panel and to the Local Architectural Conservation Committee.  Both those committees seemed to agree that the resulting heritage element was not strong enough to warrant inclusion in the overall scope of the project.  The Design Review Panel recommended against it; the LACAC Committee was divided and made no recommendation.

 

The following is the comment of the Design Review Panel:

The gesture to heritage conservation shown in the project weakens the urban design of the project while not making a significant contribution to the maintenance of the City’s heritage.  The unfortunate reality is that the scale of the heritage buildings is too small to be translated into the new scheme, and the saving of small portions takes them too far out of context to maintain their credible use.

 

The LACAC did not support the project as submitted, nor did they propose an alternative.  Among other comments were those comparing the approach to “a bit of Disneyland”. 

 

In view of these responses, the owner and the consultants have modified the design to move it closer to the second option.  Rather than reinstating a fragment of the original building, the façade with its mansard roof has been reinterpreted within the overall design. The revised proposal has the following features:

 

·          The design element is distinct from the main massing of the building, and located on the site of the original building

·          The design repeats the two-storey, three-bay pattern of the original façade and the arrangement of ground floor retail and upper level offices – these are the key elements of the urban design history of this site

·          The original mansard roof design is referenced in the idea of a sloped element above a vertical element.  The bell-shaped profile of the original mansard roof is further referenced in the projecting vane at the base of the sloped elements

·          The glazing divisions in the three bays reflect the proportions of the original historic elements, with two narrower panels flanking a wider central panel

 

Even with these clear references to the history of the site, the design element is closely integrated into the overall contemporary design vocabulary of the project.  It speaks to the history of the site without making an artificial pastiche. 

 

This is not a major redesign, but rather an evolution from the previous design.  We have taken the time to do these revisions and refinements because the previous design was not embraced by either of the City’s design review committees.  It is our belief that the current revisions reflect a broader consensus on how to best marry the past, present and future of this prominent site. 



            APPLICATION FOR NEW CONSTRUCTION IN THE
BANK STREET HERITAGE CONSERVATION DISTRICT

DEMANDE DE NOUVELLE CONSTRUCTION DANS LE DISTRICT
DE CONSERVATION DU PATRIMOINE DE LA RUE BANK

ACS2006-PGM-APR-0097                                                                  SOMERSET (14)

 

Grant Lindsay, Manager, Development Approvals, Planning and Infrastructure Approvals Branch (PIA), Planning and Growth Management Department (PGM), introduced Ms. Sally Coutts, Planner, who made a PowerPoint slide presentation providing the Committee with an overview of the staff report.  A copy of this presentation is held on file with the City Clerk.

 

In reply to Councillor Alex Cullen’s question, Ms. Coutts advised that the Local Architectural Conservation Advisory Committee (LACAC) failed to make a decision on the first application.  The applicant has re-applied under the Heritage Act to remove the mansard roof parcel from the proposed building.  Ms. Coutts indicated that staff are opposed because retaining that parcel would add to the heritage aspect of Bank Street.

 

The Committee heard from Mr. Julian Smith, of Julian Smith and Associates, Architects.  He indicated that both the Urban Design Committee and LACAC had serious reservations about the initial project, the former saying the façade was too small a fragment and would look dislocated and the latter saying the approach was artificial and the fragment too small to be convincing.

 

Chair Peter Hume asked Mr. Smith to explain why the older façade was thought inappropriate and what it was about the second proposal that would improve the streetscape.  Mr. Smith stated that the current façade commences 14 feet above the sidewalk.  The new project would commence higher, making the second floor habitable because the façade would not be there.  The second issue relates to the condition of the steel cladding on the façade, which is rusted out completely on the lower eave line and in need of replacement: this would mean having to replace the rotten wood underneath it.

 

Louise Lalande, a member of LACAC, explained that the Committee had been unable to agree on the first proposal, and made no recommendation.  She stated that the rationale behind the new proposal makes more sense, because LACAC was opposed to a reproduction of the façade.

 

Richard Chmiel and Elaine Yee, Architect.  Mr. Chmiel spoke of working with Julian Smith, heritage consultants and the Heritage Committee to try to retain the heritage façade.   As work progressed, it became apparent that retention of this fragment in a $24 million development didn’t make sense.  He posited that the new proposal maintains a heritage feel without restoring the façade.  Ms. Yee added that the proposed design complements the existing streetscape by repeating the three-storey element of adjacent buildings.  This is in keeping with the City’s desire to maintain the urban design feel.

 

John Toth, of Toth Equity Ltd, spoke about being fortunate in securing Telus to develop the property because they were aware of the heritage aspect of the area and cooperated with the various heritage design committees.  He admitted to never have liking the first design, which he felt detracted from the development and the neighbourhood.  Mr. Toth said the second design retains the current rhythm and scale of the street, and makes it pedestrian friendly.  The sides of the building will be indented and sidewalk cafés will be built on both Bank Street and Slater Street.  He asked for the Committee’s approval of the second design.

 

Chair Hume advised that Councillor Holmes had moved the LACAC recommendation of 27 April 2006, i.e., approval of the new concept. 

 

Councillor Holmes recalled that the establishment of the Bank Street Heritage District resulted in appeals by property owners, and contributed to the City’s inability to retain buildings, leaving it only the ability to retain elements, as is now the case, and not generally very successfully.  The Councillor said that many property owners don’t see heritage as an asset but as a liability.  She called the proposed building a successful, modern building with no heritage aspect to it, but nonetheless, as it will contain retail and pedestrian spaces, the Committee should support it.

 

Councillor Alex Cullen thought it was sad there is not much Canadian history to celebrate and this is partly because older buildings keep getting demolished.  He felt that the façade should be retained otherwise future generations would never know there was anything other than buildings like the Telus Building along Bank Street.  The Councillor did not feel the mansard roof would detract from the building, and that including it was entirely feasible.

 

Councillor Georges Bédard pointed out that Council approved the demolition of the buildings that were there before and he did not agree with incorporating heritage value in a new building.  The Councillor pointed out that, unless staff recommends the buildings be retained and properly maintained, the Committee is “stuck” with what it has and has to go with what is being proposed. 

 

Moved by D. Holmes

 

That the Planning and Environment Committee recommend that Council approve the application received on April 4th, 2006 for new construction at 119-121, 125, 127 Bank Street and 215 Slater Street, received on April 4, 2006.

 

(Note: Approval to Alter this property under the Ontario Heritage Act must not be construed to meet the requirements for the issuance of the building permit.)

 

                                                                                                            CARRIED as amended

 

YEAS (7):     B. Monette, G. Hunter, P. Feltmate, M. Bellemare, G. Bédard, D. Holmes, P. Hume.

NAYS (2):    A. Cullen, J. Harder