6.       LANSDOWNE PARK -
STRUCTURAL INSPECTION OF LOWER SOUTH SIDE STANDS

 

Parc Lansdowne -
Inspection structurelle des tribunes inférieures du côté sud


 

 

Committee Recommendation

 

That Council approve the demolition and removal of the lower south side grandstands at Frank Clair Stadium for the consideration of $1,200,000, subject to the requirements of a technical feasibility study and the development of a detailed demolition work plan

 

 

Recommandation du comité

 

Que le Conseil approuve la démolition et l'enlèvement des tribunes inférieures du côté sud du stade Frank-Clair pour la somme de 1 200 000 $, sous réserve des exigences relatives à l'étude technique de faisabilité et de l'élaboration d'un plan détaillé des travaux de démolition.

 

 

 

 

 

Documentation

 

1.   Executive Director's report (Business Transformation Services) dated 2 October 2007 (ACS2007-BTS-RPM-0041).

 

2.   Extract of Draft Minute, 2 October 2007.


Report to/Rapport au :

 

Corporate Services and Economic Development Committee

Comité des services organisationnels et du développement économique

 

and Council / et au Conseil

 

2 October 2007/ le 2 octobre 2007

 

Submitted by/Soumis par:  Stephen A. Finnamore, Executive Director, Business Transformation Services / Directeur exécutif, Services de transformation des activités

 

Contact Person/Personne ressource:

Doug Moore, Manager Venture Properties Division

Real Property Asset Management/Gestion des actifs des biens immobiliers

(613) 580-2424 x 41301, Doug.Moore@ottawa.ca 

 

 

Ref N°: ACS2007-BTS-RPM-0041

 

 

SUBJECT:

 

LANSDOWNE PARK – STRUCTURAL INSPECTION OF LOWER SOUTH SIDE STANDS

 

 

OBJET :

PARC LANSDOWNE - INSPECTION STRUCTURELLE DES TRIBUNES INFÉRIEURES DU CÔTÉ SUD

 

REPORT RECOMMENDATION

 

That the Corporate Services and Economic Development Committee recommend Council approve the demolition and removal of the lower south side grandstands at Frank Clair Stadium for the consideration of $1,200,000, subject to the requirements of a technical feasibility study and the development of a detailed demolition work plan.

 

RECOMMANDATION DU RAPPORT

 

Que le Comité des services organisationnels et du développement économique recommande au Conseil d'approuver la démolition et l'enlèvement des tribunes inférieures du côté sud du stade Frank-Clair pour la somme de 1 200 000 $, sous réserve des exigences relatives à l'étude technique de faisabilité et de l'élaboration d'un plan détaillé des travaux de démolition.

 

 

BACKGROUND

 

In 2007, Real Property Asset Management (RPAM) budgeted and commissioned a structural adequacy review of the lower south side grandstands at Frank Clair Stadium, continuing a repetitive assessment and remediation effort, which has been applied throughout the operational history of the site. The 2007 inspection, however, is the first to assess deterioration and incremental weathering of the structure relative to the updated 2006 Ontario Building Code and the 2004 concrete design code.

 

As a result of this inspection, and on the advice of the Consulting Engineering team, the City closed the lower South side grandstand on August 31, 2007 in the interest of public safety. On September 5, 2007, RPAM issued a memo to the Mayor and Members of Council advising of structural concerns with the lower South side grandstand. The Engineers provided their final report, including a summary of observations, conclusions and recommendations for risk mitigation on September 20, 2007.

 

 

DISCUSSION

 

The lower south side stands at Frank Clair Stadium were designed in 1960 and constructed circa 1961. The stands seat 6,648 spectators and represent approximately 25% of the overall stadium seating capacity.

 

As the oldest permanent stadium infrastructure within the City inventory, the design predates improved construction codes and practices introduced for seismic resistance in the early 1970’s. Further, the lower South side stands are a completely separate structure from the upper stands, which are mid 1970’s vintage and representative of a more robust design.

 

As a consequence of the recent inspection of the lower South side stands and a combination of key factors including; age (48 years), design, usage and observed distress, the Engineers have concluded that the lower South side stands have reached the end of their service life.

 

Based on the summary report issued by the Consulting Engineers, staff has determined that there are six (6) options for consideration. The cost estimates below have been presented in the absence of any detailed drawings, specifications or work plan assessment. The estimates are understood to be of limited precision and are considered to be “order of magnitude” only.

 

The six options are:

 

  1. “Mothball” the lower South side stands. This work entails the hoarding and decommissioning of the existing structure, restricting any and all public access. At an estimated cost of $100,000, this option does not preclude the requirement for eventual demolition of the structure or provide for complete mitigation of risk.

 

  1. Remediate and Retrofit. This option requires the reconstruction of the existing grandstands to satisfy all current code requirements, but retains significant elements of the original 1960’s era construction. The estimated cost of $5,000,000 is comparable to that of new construction, but limits the service lifespan to a maximum of 10 years.

 

  1. Demolition. This option provides for the demolition and removal of the lower South side stands. The estimated cost of $1,200,000 achieves full mitigation of risk.

 

  1. Demolition and Partial Replacement. This option considers the demolition and removal of the lower South side stands and provides for the reinstatement of certain amenity spaces such as washrooms, change-rooms and possible concession areas. The estimated cost of $3,500,000 provides full risk mitigation and restores limited amenities, which are appropriate to current programming.

 

  1. Demolition and Temporary Seating. Under this alternative, the lower South side stands are demolished and removed with appropriate temporary seating provided through lease or purchase according to program need. The precise cost for temporary (bleacher-style) seating will be based on the projected number of events and the required seating capacity for each. A rough estimate of $1,400,000 is assumed.

 

  1. Demolition and Full Reconstruction. This option provides for the demolition and removal of the existing lower South side stands and their replacement with a new grandstand assembly constructed to current code. The estimated cost for this option is $6,200,000 and a service lifespan of 50 years is assumed.

 

In consideration of the key factors and the conclusions of the Engineering Report, it is the recommendation of RPAM that the existing lower South side grandstand at Frank Clair Stadium be subject to demolition and removal (Option 3, above). Staff will continue to investigate alternate dressing room arrangements as warranted to meet short-term programming needs.

 

 

ENVIRONMENTAL IMPLICATIONS

 

Planned demolition work will require the removal of all resulting debris from the site. The disposal of this debris may be subject to specific environmental regulations.

 

 

CONSULTATION

 

The Ward Councillor has been consulted and supports this recommendation. Further consultation may be required depending on the specific demolition methodology which is applied.

 

 

FINANCIAL IMPLICATIONS

 

An initial contribution of $1,200,000 from the City Wide capital reserve fund will be required in order to fund this expenditure.

 


 

SUPPORTING DOCUMENTATION

 

Document 1 – Lower South Side Stands at Lansdowne Park Frank Clair Stadium. Structural Adequacy Report 2007 (Adjelian, Allen, Rubelli Limited)

 

Document 2 – Lower South Side Stands – “Ball Park” Cost Estimates, Letter to City of Ottawa (Davis) ex. Adjelian, Allen, Rubelli Limited (Vopni) – September 20, 2007.

 

 

DISPOSITION

 

Following Council’s approval, Real Property Asset Management will initiate a technical feasibility review to establish an appropriate demolition work plan.



            LANSDOWNE PARK - STRUCTURAL
INSPECTION OF LOWER SOUTH SIDE STANDS

Parc Lansdowne - Inspection structurelle
des tribunes inférieures du côté sud

ACS2007-BTS-RPM-0041                                city-wide / À l’Échelle de la ville

 

Staff responded to Committee members’ questions on the report.  The following summarises the main points raised.

 

Mr. B. Robinson, Acting Director of Real Property Asset Management, explained that staff had considered the various options from three perspectives; due diligence and public safety; impact to clients in terms of programming requirements; and sensitivity to financial implications.  He maintained staff had narrowed the options down to one recommendation because it provided the most flexibility in terms of being responsible for the safety of users, being able to put in interim seating to accommodate events, and reducing the financial commitment to the City in terms of providing interim seating on an as needed basis.  Furthermore, he submitted that in light of potential impending changes at Lansdowne, this scenario provided the flexibility to be in accordance with whatever direction Council might decide to take.  

 

Mr. Robinson noted that by law, this structure did not specifically require regularly scheduled inspections, though he indicated the City’s program had been very pro-active.  He explained that shear load was unpredictable failure and that the stress cracks had become wider and more numerous over time.  He maintained this was a gradual deterioration based on use, age and design and that it had gotten to the point where they were recommending closure.  However, he indicated it was very difficult to say how long the stands had been in this state. 

 

In terms of the impact on adjacent facilities, Mr. Robinson explained that staff would be undertaking a technical assessment in terms of all the variables to be factored in; impact on adjacent facilities; safeguarding the upper deck; road allowances and load limits when removing materials from the site; programming impacts.  He indicated staff was currently developing the scope of the work, pending Council’s direction on this report, and that all the referenced issues would be presented in the technical review.

 

Mr. Robinson noted there were mechanical and electrical systems underneath the structure, which would be assessed as part of the technical review.  However, in terms of salvaging some components of the structure in order to offset costs, he referenced current demolition and labour costs and the challenges these posed and he indicated this had yet to be determined but that staff would be looking for the best value. 

 

Ms. Simulik confirmed that the costs would be paid out of reserves and would therefore not create a pressure for the 2008 budget, but that this would deplete the reserve fund. 

 

Mr. Robinson indicated inspections were done every five years, based on staff’s prudent decision-making, which was based on potential risks, funding availability and former law. 

 

With respect to getting to facilities in time to do remedial work before they were deteriorated to the extent where they had to be demolished, Mr. Robinson indicated staff was using a very effective tool called a condition assessment audit.  He explained this had been very beneficial in terms of being able to prioritize funding and deal with safety issues.  However, he acknowledged that there was not enough funding to inspect all facilities in a short period of time but that the program was progressing within the budget capacity.

 

Mr. P. Jolicoeur, Manager of Comprehensive Asset Management, indicated that in 2007, inspections were conducted on 12 to 15 buildings of a wide-span structure (i.e. arenas and pools).

 

In closing, Mayor O’Brien congratulated staff for their work on this project.  He indicated he believed staff was leading Council in the right direction in terms of their decision and he submitted that they had potentially saved lives. 

 

That the Corporate Services and Economic Development Committee recommend Council approve the demolition and removal of the lower south side grandstands at Frank Clair Stadium for the consideration of $1,200,000, subject to the requirements of a technical feasibility study and the development of a detailed demolition work plan.

 

                                                                                                            CARRIED