1. CONROY
Public Works Facility Installation de Travaux publics du chemin
Conroy |
That Council
approve:
1. The increase of the
capital authority for Heatherington Building Replacement (Conroy Development
Plan) from $4.64 M to $11.64 M to allow for the construction of a Public Works
facility at 3100 Conroy Road that will replace the existing facility at 1770
Heatherington Road; and,
2. The transfer of
$7.0 M of tax supported debenture financing from Capital Project Maple Grove
Facility Works Operation to Capital Project Heatherington Building Replacement
(Conroy Development Plan).
3. Receive the staff memo dated 3 March
2009 to this report
Que le Conseil approuver:
1. L’augmentation de l’autorisation de
dépenses d’immobilisations pour le remplacement de l’édifice Heatherington
(plan d’aménagement de Conroy) de 4,64 M$ à 11,64 M$ afin de permettre
l’aménagement d’une installation pour Travaux publics au 3100, chemin Conroy
qui remplacera l’installation actuelle située au 1770, chemin Heatherington;
2. Le
transfert de 7 M$ comme financement sous forme de débentures soutenu par les
taxes à partir du projet d’immobilisations de l’installation de dépôt Maple
Grove vers le projet d’immobilisation du remplacement de l’édifice
Heatherington (plan d’aménagement de Conroy).
3. Prenne connaissance de la note de
service du personnel en date du 3 mars 2009 qui accompagne le présent rapport.
Documentation
1. Deputy
City Manager, City Operations report dated 25 February 2009 (ACS2009-COS-PWS-0005).
2. General
Manager, Public Works Memo dated 3 March 2009
3. Extract
of Draft Minute 29, 4 March 2009
Report to/Rapport au :
and Council / et au Conseil
25 February 2009 / le 25
février 2009
Steve Kanellakos, Deputy City Manager /
Directeur municipal adjoint
City Operations / Opérations
municipales
Contact Person/Personne ressource:
John Manconi, General Manager /directeur
générale, Public Works/Travaux Publics
(613)
580-2424, extension/poste 21110, John.Manconi@ottawa.ca
SUBJECT: |
CONROY Public Works Facility |
|
|
OBJET
: |
REPORT
RECOMMENDATIONS
That the Transportation
Committee recommends that Council approve:
1.
The increase of the capital authority for Heatherington
Building Replacement (Conroy Development Plan) from $4.64 M to $11.64 M to
allow for the construction of a Public Works facility at 3100 Conroy Road that
will replace the existing facility at 1770 Heatherington Road; and,
2.
The transfer of $7.0 M of tax supported debenture
financing from Capital Project Maple Grove Facility Works Operation to Capital
Project Heatherington Building Replacement (Conroy Development Plan).
RECOMMENDATIONS DU RAPPORT
Que le
Comité des transports recommandent au Conseil d’approuver:
1. L’augmentation de l’autorisation de
dépenses d’immobilisations pour le remplacement de l’édifice Heatherington
(plan d’aménagement de Conroy) de 4,64 M$ à 11,64 M$ afin de permettre
l’aménagement d’une installation pour Travaux publics au 3100, chemin Conroy
qui remplacera l’installation actuelle située au 1770, chemin Heatherington;
2. Le transfert de 7 M$ comme financement
sous forme de débentures soutenu par les taxes à partir du projet
d’immobilisations de l’installation de dépôt Maple Grove vers le projet
d’immobilisation du remplacement de l’édifice Heatherington (plan d’aménagement
de Conroy).
BACKGROUND
The Surface Operations
Branch has been actively reviewing operational practices and service delivery
models for the past several years.
Facility rationalization and consolidation has been an intricate
component of the Branch review. On 23 May 2007, Council approved a report
(ACS2007-PWS-SOP-0003) seeking approval of a long-range plan for Facility and
Property Rationalization & Consolidation.
Contained in the report was an outline for a project entitled
Heatherington Road Replacement. This
project involved the complete replacement of the Public Works facility at 1770
Heatherington Road. The project was originally estimated at $5.5 M, and was
approved in the 2007 Capital Budget with $4.64 M allotted to facilitate the
design and construction of a replacement facility.
Reduction in Capital
envelope, escalation in construction costs, inflation, requirement of site
servicing and amenities and the need to accommodate growth pressures has
impacted the original project estimate.
The revised project estimate to complete the new facility at 3100 Conroy
Road is $11.4 M. Increased authority of
$7.0 M is required to commence with the relocation of the works garage from
1770 Heatherington Road to 3100 Conroy Road.
Surface Operations
has an approved Capital Project (Ref.
No. ACS2007-BTS-RPN-0006) for the reconstruction and consolidation of a
facility located at 1655 Maple Grove Road.
The project authority is $10.8M for design and construction of the new
garage. Construction was expected to
start in 2009.
The 1655 Maple Grove
Road site is located within the boundaries of the Kanata West Development
Plan. Council has imposed a moratorium
on all planned construction within the Kanata West Development lands due to a
revised Ministry of Environment Assessment for review of the Carp River flood
plain. Given the delay of this project and
unknown restrictions that could result from a revised Environmental Assessment,
the Branch is proposing a transfer of $7M from the Maple Grove Project to the
Conroy Road construction plan. The Department will resubmit a budget request in
the 2010 Budget for the construction requirements of the Maple Grove facility.
CONSULTATION
Public consultation was conducted during the Zoning Amendment process required to facilitate construction at the 3100 Conroy Road site. Additional input will be obtained during the Site Plan Approval process for the building design and site layout for the new Works Yard at 3100 Conroy Road.
FINANCIAL IMPLICATIONS
With approval of the recommendation contained
in this report project authority in the amount of $7.0 M will be transferred
from capital project Maple Grove Facility to capital project Heatherington
Building Replacement..
Construction of the Maple Grove Facility will
be delayed until new authority is established. The request will be made in the
Draft 2010 Capital Budget.
LEGAL/RISK MANAGEMENT IMPLICATIONS
There are no legal/risk management impediments
to implementing the recommendations in this report.
Document 1 – Aerial Photograph of 1770 Heatherington
Document 2 - Aerial Photograph of 3100 Conroy Road
Document 3 – Aerial Photograph of 1655 Maple Grove Road
DISPOSITION
Following Council’s approval, Public Works staff will finalize the design and construction project for a Public Works facility at 3100 Conroy Road. Upon completion of the new facility, Public Works staff will disengage from the existing site at 1770 Heatherington and make the property available for disposal and redevelopment.
Public Works staff will review implications of the revised Ministry of Environment Assessment of the Carp River flood plain on the proposed redevelopment of 1655 Maple Grove Road Works Yard. Revised budget estimates will be submitted as part of the 2010 Capital Budget plan.
M E M O / N O T E D E S E R V I C E |
|
To / Destinataire |
Members of the Transportation Committee |
File/N° de fichier: |
From / Expéditeur |
General Manager |
|
Subject / Objet |
Conroy Public Works Facility |
Date: March
3, 2009 |
The purpose of
this memo is to address some items raised by Councillor Qadri with respect to
the Conroy Public Works Facility report, which will be tabled at the
Transportation Committee meeting on March 4, 2009, specifically clarification
relating to the impact on the Maple Grove facility.
In the last
paragraph of the DISCUSSION section of the report, the use of the words
“unknown restrictions” were not intended to create the impression that staff
were anticipating that the Carp River 3rd Party Review study will result in any
negative impacts on property owners.
The results of that study are simply unknown at this time. This has been reviewed by Legal staff.
The report also
indicates that the Department will be including in the 2010 Capital Budget
estimates for the required funding to complete the Maple Grove Works project as
originally approved by Council.
Finally,
Councillor Qadri enquired about the potential for delaying the Conroy Public
Works facility project. Specifically,
he asked if it was possible to request the additional funding for the Conroy
project through the 2010 Capital budget rather than out of the existing Maple
Grove works project. The Councillor was
advised that staff are not in favour of delaying the Conroy Road project. Citywide Public Works facilities are under operational
stress due to the fire that destroyed the Maple Grove facility in 2006, the new
fire at the Catherine works facility and the restrictions at the Heatherington
site.
The Catherine
site is undergoing repairs to restore it to full operational capacity, which
will help, the Maple Grove facility and the Heatherington replacement are
critical to ensuring effective and efficient operations. In addition, any further delays will result
in increased costs of the overall project.
It is imperative that the work at the Conroy site commences this
year. Since the Maple Grove Works project
cannot proceed in the immediate future, it was considered reasonable to take
the approach that is being proposed and recommended by Finance staff.
Staff did
consider proceeding with the project using the current funding envelope,
however the design team does not recommend this, as it would result in
increased costs and the inability to commit to the entire facility construction
in the tender call.
Councillor Qadri
is not pleased with the transferring of funds, but accepts the proposal based
on the condition that funding would be requested by staff in the 2010 budget for the Maple Grove
facility. The Councillor also requests
this memo be attached to the report as an attachment to further direct staff to
include Maple Grove facility in the 2010 budget
The facilities at
Heatherington works yard have reached the end of their service life. The extent of the problems with these
facilities became evident in 2002 when, in response to Health and Safety
concerns, the Ministry of Labour issued orders to cease use of some of the
buildings and restricted use in others.
Some buildings were subsequently demolished and replaced with temporary
trailers until a new facility can be built.
In 2004, Surface
Operations included a new project for the redevelopment of Heatherington yard
in the Long Range Financial Plan with a projected budget of $5.5M for
2006/2007. During the preparation of
the 2007 budget, the projected cost of $5.5M was reduced to $4.64M to fit
within the available funding envelope.
That amount was included in the 2007 Capital budget that was
subsequently approved by Council.
Following that,
in May of 2007, City Council approved the Department’s strategy of
rationalizing and consolidating of its works facilities. Part of the strategy included relocating the
Heatherington works yard to city owned property on Conroy Road. It also included the closure of the works
yard on Leitrim Road and consolidating those operations into the existing
Rideau Valley yard and the proposed Conroy Works facility.
On March 1, 2009,
Transportation Committee Members received an e-mail from a resident, Mr. Klaus
Beltzner, regarding the increased costs of the Conroy facility. Following is information in response to Mr.
Beltzner questions.
As indicated
above, the original estimate in 2004 was for redevelopment of the Heatherington
yard at its existing location.
Relocating to the Conroy Road site does result in some increased costs,
however, there are also offsetting benefits derived from the disposal of the
Heatherington property and redevelopment into more suitable for the area. The initial estimate in 2004, for
redevelopment of Heatherington yard was $5.5M.
Inflated to current dollars, the new project cost is $6.9M. In addition, there are some premium costs
due to relocation to a new site, such as the need for new material storage
buildings, cold storage building, site servicing, development costs, etc. Geotechnical reports also identified the
need for additional foundation work due to the soil conditions.
The increased
costs are summarized in the table below.
|
|
ORIGNAL DESIGN ($000) |
REVISED DESIGN ($000) |
1 |
Design |
500 |
500 |
2 |
Construction |
5,000 |
5,000 |
3 |
Inflation on
original design & construction |
|
1,400 |
4 |
Site Servicing |
|
2,000 |
5 |
Material
storage buildings |
|
400 |
6 |
Cold storage
buildings |
|
1,000 |
7 |
Development
Charges |
|
800 |
8 |
Project
Management |
|
500 |
|
TOTAL |
$5,500 |
$11,600 |
Items 4, 5 and 7
in the Table above are premiums associated with locating to a new site versus
rebuilding on an existing site. Site
servicing includes site grading, drainage, utility services (water, sewer,
hydro, telephone), fencing, security, additional foundation works as a result
of geotechnical findings, etc.
Development Charges includes such things as obtaining zoning changes,
permit fees, development charges, environmental assessments, signage, etc Item 6 is the result of needs identified
through the Facility Rationalization and Consolidation study.
Should you have
any questions, please do not hesitate to contact me at ext. 21110.
Original signed by
John Manconi
cc: Deputy City Manager, City Operations
Coordinator, Transportation Committee
Director, Infrastructure Services
District Manager, Roads, Parks and Trees
CONROY PUBLIC WORKS FACILITY
Installation de Travaux publics du chemin Conroy
ACS2009-COS-PWS-0005 Gloucester-SouthGate (10)
All members of Council received a memo dated 3 March
2009 from the General Manager, Public Works.
John Manconi,
General Manager, Public Works and Ray Yantha, District Manager, Roads Parks and
Trees were present to answer questions of Committee.
Councillor Qadri
posed a series of questions regarding the transfer of funds from the Maple
Grove facility account to the Conroy facility account. In response, Mr. Manconi provided the
following details:
·
Due to a third party review (MOE), construction of the Maple Grove
facility could not be initiated this year; therefore, staff decided to transfer
the money in order to proceed with Conroy, with funding for the former to be
reinstated in 2010
·
If the money was not available from the Maple Grove facility, staff
were not in support of waiting until the 2010 budget because of the deplorable
conditions at the existing facility on Heatherington Road and escalating costs
as a result of lease and alternate arrangements
Councillor Qadri
spoke briefly to the memo that was previously circulated and which he and staff
had prepared. He expressed the view
that while he did not object to transferring the funds from a facility in his
ward to another, he was concerned that he had not been consulted in that
arrangement. In future, when similar
circumstances deem it necessary to move funds from one account to another, he
suggested that all affected ward councillors be involved in that process.
Mr. Manconi
offered his apologies, and confirmed that this is the arrangement that should
have been followed.
The Chair noted
the request in the memo to attach it to the staff report when it rises to
Council and asked how that could be done.
Ernest McArthur, Legal Counsel, suggested that such direction be added
as a third recommendation to receive the memo.
The Chair made
further reference to details in the memo which responded to concerns posed by a
public delegation about the increased costs of the Conroy facility. She asked that the General Manager advise
how he intends to proceed on that concern.
Mr. Manconi advised that he would be meeting with the member of the
public to review and clarify the information provided in the memo.
Councillor
Wilkinson was concerned that staff are proposing to add $7M to the budget which
had previously never been anticipated.
She felt it showed a lack of good planning and that staff were doing
this on an ad hoc basis. Mr. Manconi
explained that the approach staff took, was what is best thing to do in the
long term. He suggested the
Heatherington facility could have been reconstructed, but it would be situated
in the middle of a neighbourhood on developable land. And so, staff determined to move that facility to a piece of
property already owned by the City. The
councillor made note of the fact that no money had been put into the previous
or current budget to address this and such an expenditure should be dealt with
at budget time, not after the fact. She
was also concerned that removing it from one project to another will put
pressure on the 2010 budget.
Councillor
Legendre was of the opinion that budgetary matters can and should be dealt with
throughout the year.
Klaus Beltzner thanked staff
for addressing his concerns in the memo dated 3 March. He indicated that his main concern was not
just a question of public due diligence, but also (for purposes of
transparency) the level of detail in the staff report, so the public can
understand exactly what is being requested.
He explained that his only unanswered question is the cost escalations
for capital projects. A copy of his
e-mailed submission dated 1 March is held on file.
The Chair
reiterated staff’s offer to meet with Mr. Beltzner to discuss his concerns
further.
Moved by A.
Cullen
That the Committee receive the staff memo dated 3
March 2009 to this report.
CARRIED
That the Transportation
Committee recommends that Council approve:
1. The increase of the
capital authority for Heatherington Building Replacement (Conroy Development
Plan) from $4.64 M to $11.64 M to allow for the construction of a Public Works
facility at 3100 Conroy Road that will replace the existing facility at 1770
Heatherington Road; and,
2. The transfer of $7.0 M of tax supported debenture financing from Capital Project Maple Grove Facility Works Operation to Capital Project Heatherington Building Replacement (Conroy Development Plan).
3. Receive the staff memo dated 3 March 2009 to this report.
CARRIED, as amended, with Councillors
Bloess and Wilkinson dissenting on Recommendations 1 and 2.