1.             rEADY-TO-GO INFRASTRUCTURE PROJECTS FUNDING REQUEST:
UPDATED PRIORITY LISt

 

demande de financement DE PROJETS D’INFRASTRUCTURES PRÊTS
POUR LA MISE EN CHANTIER – liste prioritaire mise à jour

 

 

 

COMMITTEE RECOMMENDATIONS AS AMENDED

 

That Council :

 

a)      Approve the updated City of Ottawa Priority List of Ready-To-Go Infrastructure Projects, as detailed in Document 1 as amended by the following:

i)        An increase from $40,294,507 to $137,578,611 to the Social Housing Infrastructure Fund Project List for Ottawa Community Housing (March 23 Report: Ready-To-Go Infrastructure Projects Funding Requests);

ii)      The addition of the following projects to the Recreation Infrastructure Fund Project List (March 23 Report: Ready-To-Go Infrastructure Projects Funding Requests)

Projects in Priority

Cost ($M)

Operating Budget Pressures 2011 ($)

Approvals Required

Coyote Park Development

0.50

n/a

Community consultation required

Basketball Court at Stittsville Arena

0.06

minimum

Community contribution also committed in addition.

Splash Pad for Jackson Trails

0.06

8K

minimum

 

 

 

 

 

 

 

 

iii)  The addition of the incomplete components of the parks in Findlay Creek, including an outdoor rink and lighting, valued at approximately $90,000 to the Recreation Infrastructure Fund Project List; and

iv)  That the amount of the City of Ottawa’s share for the La Nouvelle Scène infrastructure project be revised from $1M to $1.7M;

b)      Direct staff to proceed with the official funding request for the projects identified on the Ready-To-Go-Infrastructure Projects list; and

c)      Direct the City Treasurer to report back with the identification of the sources of funding for the City's share of the projects for Council approval.

 

 


 

RecommandationS modifiÉeS du Comité

 

Que le Conseil :

 

a)   Approuve la liste actualisée des projets prioritaires d’infrastructure prêts à mettre en oeuvre, comme il est expliqué en détail dans le Document 1 modifié par ce qui suit:

 

i)    Une augmentation de 40 294 507 $ à 137 578 611 $ en ce qui a trait à la liste des projets de financement de l’infrastructure du logement social pour la Société de logement communautaire d’Ottawa (Rapport du 23 mars : demandes de financement des projets d’infrastructure prêts à mettre en oeuvre);

 

ii)   L’ajout des projets suivants à la liste de financement de l’infrastructure récréative (rapport du 23 mars : demandes de financement des projets d’infrastructure prêts à mettre en oeuvre)

 

Projets prioritaires

Coût (M$)

Pressions budgétaires de fonctionnement de  2011 ($)

Approbations requises

Aménagement du parc Coyote

0,50

s.o.

Consultation communautaire requise

Terrain de basket-ball à l’Aréna de Stittsville

0,06

minimum

Contribution communautaire engagée en plus.

Fontaine à jets douchants pour les sentiers Jackson

0,06

8 K

minimum

 

 

iii)  L’ajout des éléments incomplets des parcs du ruisseau Findlay, y compris une patinoire et l’éclairage extérieurs, d’une valeur approximative de 90 000 $, à la liste des projets de financement de l’infrastructure récréative;

 

iv)  Que le montant de la part de la Ville d’Ottawa concernant le projet d’infrastructure relatif à La Nouvelle Scène soit révisé de 1 M$ à 1,7 M$;

 

b)   demande au personnel de poursuivre le traitement des demandes de financement officielles pour les projets inclus dans la liste prioritaire de projets d’infrastructure prêts pour la mise en chantier; et

 

c)   demande à la trésorière de la Ville de faire rapport sur les sources de financement de la part de la Ville relativement aux projets aux fins d’approbation.

 

 

 

DOCUMENTATION

 

1.      Deputy City Manager of Infrastructure Services and Community Sustainability report dated 20 March 2009 (ACS2009-ICS-DCM-0002).


Report to/Rapport au :

 

Corporate Services and Economic Development Committee /

Comité des services organisationnels et du développement économique

 

and Council / et au Conseil

 

20 March 2009 / le 20 mars 2009

 

Submitted by/Soumis par : Nancy Schepers,

Deputy City Manager/Directrice municipale adjointe,

Infrastructure Services and Community Sustainability/

Services d’infrastructure et Viabilité des collectivités 

 

Contact Person/Personne ressource : Gary Craig, Manager / Gestionnaire

Deputy City Manager’s Office/ Bureau de la Directrice municipale adjointe

(613) 580-2424 x19037 Gary.Craig@ottawa.ca 

 

City Wide/À l'échelle de la Ville

Ref N°: ACS2009-ICS-DCM-0002

 

 

SUBJECT:

READY-TO-GO INFRASTRUCTURE PROJECTS FUNDING

 REQUEST: UPDATED PRIORITY LIST

 

 

OBJET :

demande de financement DE PROJETS D’INFRASTRUCTURES PRÊTS POUR LA MISE EN CHANTIER – liste prioritaire mise à jour

 

 

REPORT RECOMMENDATIONS

 

1.       That, at its meeting of 23 March 2009, the Corporate Services and Economic Development Committee receive and table this report for consideration at its subsequent meeting; and

2.       That, upon considering this report at its subsequent meeting, the Corporate Services and Economic Development Committee recommend Council:

a)      Approve the updated City of Ottawa Priority List of Ready-To-Go Infrastructure Projects, as detailed in Document 1;

b)      Direct staff to proceed with the official funding request for the projects identified on the Ready-To-Go-Infrastructure Projects list; and

c)      Direct the City Treasurer to report back with the identification of the sources of funding for the City's share of the projects for Council approval.

 


RECOMMANDATIONS DU RAPPORT

 

1.         Que, lors de sa réunion du 23 mars 2009, le Comité des services organisationnels et du développement économique reçoive et dépose le présent rapport aux fins d’examen lors de sa prochaine réunion;

 

2.         Qu’après avoir examiné le présent rapport lors de sa prochaine réunion, le Comité des services organisationnels et du développement économique recommande au Conseil :

 

a)      d’approuver la liste prioritaire à jour de projets d’infrastructure prêts pour la mise en chantier de la Ville d’Ottawa, telle que détaillée dans le document 1;

 

b)      de demander au personnel de poursuivre le traitement des demandes de financement officielles pour les projets inclus dans la liste prioritaire de projets d’infrastructure prêts pour la mise en chantier; et

 

c)      de demander à la trésorière de la Ville de faire rapport sur les sources de financement de la part de la Ville relativement aux projets aux fins d’approbation.

 

 

BACKGROUND

 

As part of its 2009 Budget, the federal government announced an economic stimulus package that will provide significant infrastructure funding opportunities for municipalities across Canada.

 

The stimulus package provides municipalities with funding above and beyond what is currently in place with the Building Canada Fund, gas tax revenues and the GST rebate.

 

On January 3, 2009, Corporate Services and Economic Development Committee passed the following motion:

 

THEREFORE BE IT RESOLVED that the Corporate Services and Economic Development Committee direct staff to work with Members of Council to develop a comprehensive, priority list of all City ready-to-go projects for consideration by Committee and Council, and report back on February 3, 2009, meeting; and

 

BE IT FURTHER RESOLVED that the report recommend that staff be delegated the authority to proceed with the identified infrastructure projects as federal funds are made available.

 

On January 27, 2009, the City Treasurer issued a memo to the Mayor and Council seeking input into the identification of projects. Several responses were received and were considered in the preparation of a report to Corporate Services and Economic Development Committee (ACS2009-CMR-OCM-0002), tabled on February 3, 2009.   This report contained a draft list of ready-to-go infrastructure projects that could be submitted for federal funding. 

 

Committee directed staff to refine the list of projects and report back with an updated version of it that included adjustments to funding requirements, consideration of Councillors’ requests, and additional information about the eligibility criteria. 

 

On February 8, 2009, the Deputy City Manager, Infrastructure Services and Community Sustainability, sent the Mayor and Council an email, in which she requested further input on the priority list.  The projects identified were assessed by staff in the preparation of the list of projects included in this report.  

 

 

DISCUSSION

 

The economic stimulus package announced in the 2009 Federal Budget identifies four opportunities that the City of Ottawa can pursue:

 

  1. Infrastructure Stimulus Fund
  2. Social Housing Initiatives
  3. Recreational Infrastructure Fund
  4. Cultural Initiatives

 

A key condition for receiving money from the stimulus package initiative is that projects must be “ready to go” and would not otherwise proceed, which staff understand to mean projects must be able to:

 

·         Begin construction in either 2009 or 2010;

·         Be completed and commissioned by March 31, 2011; and,

·         Meet incremental funding requirements (Not already scheduled and funded in 2009).  

 

Subject to Council approval of the project list, the City will advance projects from the forecast years in 2010 and 2011 capital budgets.  The City’s funding share will come from the advancement of debt, development charges and rate supported reserve funds.  

 

The project listing does carry with it a certain amount of risk.  These risks are mainly associated with the ability to complete the required works by the March 2011 deadline.  In order to mitigate some of this risk, staff will be seeking the most expedient procurement processes available, such as sole sourcing or moving straight to design-build RFPs (where appropriate).

 

These procurement processes were discussed at the Mayor’s Infrastructure Roundtable held on February 13, 2009 and March 2009.  In attendance were the Mayor and his staff, representatives from NCHCA, OCA and CEO, City Manager Kent Kirkpatrick and various management staff from Infrastructure Services and Community Sustainability and City Operations.

 

One of the major benefits, however, of receiving stimulus funding and proceeding with projects is the creation of a significant number of jobs.  Based on a Federation of Canadian Municipality’s economic development formula that calculates jobs created per dollar spent on construction and infrastructure projects, the City could generate over 7,300 jobs through the stimulus funding initiative.

 

As mentioned, the Federal Budget identified four funds for which the City can apply.  Those funds are as follows:

 

1.  Infrastructure Stimulus Fund

 

This program is overseen by Infrastructure Canada and could have a total envelope of approximately $4 billion over two years.  The fund is designed to provide funding above what municipalities already receive from the Building Canada Fund, as well as providing them access to resources that will advance important infrastructure projects.  Allocation of funding is anticipated to be on a per capita basis. 

 

The federal government has stipulated that there is an expectation that municipalities will have to share in the cost (e.g. one-third municipal, provincial and federal).  With the City’s share of this fund estimated at $103M, the overall program would total $309M. 

 

In accordance with Council’s strategic priorities, a number of infrastructure projects have been identified to support Council’s priorities on investment in our transit system and the life cycle maintenance for the City’s assets.

 

Within this framework, the projects have been prioritized as:

·        Transit;

·        Pedestrian and cycling;

·        Renewal; and

·        Growth. 

 

The total estimated cost of these projects is approximately $496M.  (Refer to Document 1 for further detail.)

 

Priority 1 – Transit

 

Ottawa City Council recently approved the TMP and is proceeding to implement the long-term vision set out within this plan.  Council has identified this investment in the transit plan as its first priority.

 

Within the transit area of the priority list, eligible projects include:

·        Transitway expansion from Fallowfield Dr. to Barrhaven Town Centre;

·        The Baseline Station tunnel; and,

·        The Woodroffe Ave. pedestrian overpass connecting Baseline Station to Algonquin College.    

 

Priority 2 – Pedestrian and Cycling

 

Pedestrian and cycling facilities are a critical part of achieving the City’s TMP vision.  Projects listed for pedestrian and cycling include new rural pathways, urban multi-use pathway construction, new sidewalks and St. Joseph Blvd. streetscaping.  Projects within this section also include sidewalk and curb renewal.  

 

Priority 3 – Renewal

 

Council has also identified financial sustainability and the maintenance of current assets as a priority, with the goal of closing the gap on the renewal of infrastructure.

 

The projects identified within this envelope include:

·        The Transitway improvement program;

·        O-Train capital works;

·        Rural road upgrades;

·        Integrated road water sewer program;

·        Road resurfacing;

·        Structures Program;

·        Traffic signal and sign renewal; and,

·        Real property renewal.

 

Real property renewal includes improvements to a number of facilities including Bellevue Manor, Aberdeen Pavilion, Carleton Lodge, Arts Court and Centre D’Accueil Champlain. 

 

Priority 4 - Growth

 

The growth projects identified within this report include Hazeldean, Earl Armstrong, Limebank, Mer Bleue, Trim, Innes, Terry Fox and Hunt Club.

 

Terry Fox Dr. and Hunt Club Rd. are identified as higher priority growth projects as a result of the following Council directions:

 

Terry Fox Dr. motion from October 24, 2007:

 

That the two immediate Near-Term investment options in the Mayor’s Task Force on Transportation, namely the Strandherd-Armstrong Bridge and the completion of Terry Fox Drive from Kanata Avenue to Flamborough Drive, as they are currently designed, be formally submitted to the Federal and Provincial Governments for cost sharing infrastructure funding; such funding not to come from funds identified for transit projects.

 

To date, Council has approved $2.5M for the Terry Fox Dr. project.  The 2009 Capital Budget and 9-year forecast included an authority requirement of $34.5M for 2010.  The amount identified within the Updated Priority List Report is $47.7M, which includes property acquisition. 

 

With respect to the Strandherd-Armstrong Bridge, it is anticipated that this project cannot be built within the funding guidelines; as such, it cannot be submitted as part of the Infrastructure Stimulus Fund.  Although the bridge is not part of this program, it should be noted that the Earl Armstrong Rd. extension is within the stimulus envelope and on the priority list.

 

Hunt Club Rd. motion from December 3, 2007:

 

BE IT RESOLVED that funding be advanced to 2009 to allow construction to be undertaken in 2010 and that staff be directed to make the adjustments necessary (in ‘09 budget) to accommodate this adjustment; and

 

THEREFORE BE IT RESOLVED that staff commence negotiations with the province for the provincial share of funding to complete the 417 interchange.

 

The 2008 Capital Budget identified $4M for design and land acquisition costs, based on a 50/50 cost share with the Province.  The City’s $2M share has been used to initiate the design work for this project.  The Updated Priority List identifies $51M for the extension from Hawthorne Rd. to Highway 417.  The inclusion of this project is dependant on expedited approvals and property acquisition. 

 

2.  Social Housing Initiatives

 

This funding envelope will encompasses three areas, including renovation and retrofits, low-income seniors, and persons with disabilities.  The total available funding could be approximately $1.475B over two years and is based on a 50-50 cost share with the Province, which is primarily responsible for providing social and low-income housing. As a result, no City contribution is required.

 

Renovation activities will include general improvements, energy efficiency upgrades or conversions, and supports for persons with disabilities. 

 

The following priorities represent the criteria for selection within this envelope.

 

Priority 1 - Infrastructure Renewal for Social Housing

 

The Housing Needs Report submitted to Council in 2007 outlined the need for repairs to, and the renewal of existing social housing. It identified an annual capital funding deficit of approximately $14M. Although the City, Provincial and Federal governments have contributed a total of $33.5M toward social housing repair since 2007, it remains a high priority to continue this project.

 

Ottawa Community Housing Corporation recently completed a building condition assessment that identified a 5-year capital expenditure plan for the repair and renewal of properties.  It exceeded $340M. As well, other housing providers have also identified a need for infrastructure renewal.

 

The list of projects submitted by OCHC, totalling $40,294,507, represent a 2-year capital summary of projects that can be completed in their 2009 and 2010 budget timeframes.  (Refer to Document 1 for further detail.)

 

The amount requested for repair and renewal of social housing for other housing providers, totalling $7.4M consists of:

 

 

Many of these repairs will increase both the buildings’ energy efficiency and their longevity.

 

Priority 2 - Acquisition and Rehabilitation

 

There are over 9,500 households on the waiting list for social housing. Increasing the housing stock, especially with supports, is a key element in increasing affordable housing options.  City staff has identified two acquisition and rehabilitation projects that could require up to $5M in capital funding.

 

3.  Recreational Infrastructure Fund

 

This fund could provide $500M over two years to municipalities across Canada.  The fund is designed to support the construction of new community recreational facilities and upgrades to existing facilities.  This initiative will support up to 50 percent of the total costs of eligible projects, with the balance to be provided by the Provincial and Municipal governments. 

 

Priority 1 – Facility Sustainability and Service Continuity

 

Investment in existing facilities ensures sustainability and service continuity.  The projects considered to be within this category include:

 

·         Merivale and Bell Arenas - due to risk of closure of the facilities without the capacity in City of Ottawa inventory to provide alternative ice time.

 

·         Gloucester Splash and Nepean Sportsplex Pools – these investments would address temporary solutions to aging facility.

 

·         Carlsbad Springs Community Centre – loss of St. Laurent School due to closure/aging school board infrastructure.

 

·         Other lifecycle items:                

o       Nepean Sportsplex parking lot;

o       Hintonbourg Park Wall Replacement;

o       City Park Redevelopment; and

o       McKellar Park Field House – needs replacement.

 

 

Priority 2 - Solutions to Recreational Facility and Programming Needs

 

The remaining projects are listed in order of priority based on the following criteria:

 

1.      Changing demographic and make-up of communities and therefore changing recreational needs; and

2.      Validated projects that are waiting for funding from the strategic initiatives envelope.

 

These projects will include renovations, rehabilitation and new construction for both City and community-based initiatives.  The projects considered to be within this category include:

 

·         City Park Rehabilitation;

·         Greenboro Community Centre Expansion;

·         Greenboro Tennis court construction;

·         Albion Heatherington Recreation Centre parking lot;

·         Tom Brown Arena;

·         Hintonburg Community Centre;

·         Parkdale Urban Park Redevelopment and Fieldhouse;

·         Lighting of existing ball field in Fitzroy Harbour;

·         Potvin Park - 3 mini soccer fields;

·         Hornet's Nest Field House Expansions;

·         Westboro Beach Mitigation (gull wiring);

·         New Twin Pad Arena;

·         Parkdale Market - expand & improve; and

·         Sharlotte Birchard Centre.

 

(Refer to Document 1 for further detail.)

 

4.  Cultural Initiatives

 

This fund could provide up to $60M over two years.  This money will support infrastructure-related costs for local and community cultural and heritage institutions, such as theatres, libraries and small museums.  Similar to the Infrastructure Stimulus Fund, it is expected that this fund will be cost-shared with both Provincial and Municipal governments. 

 

The 2003 Ottawa 20/20 Arts and Heritage Plan (AHP) provides the broad strategic directions for culture, with the development of new and improved spaces cited as critical to the plan’s goals.

 

Beyond being ready-to-go for completion by March 2011, the following criteria for selection were used for this section.  

 

Priority 1 – Legacy Initiatives

 

Completion of legacy initiatives to address outstanding cultural facility needs was identified as a priority.  For example, the Centrepointe Theatre Expansion plan was identified by the former municipality of Nepean to respond to the demand for rehearsal and performance space.  The former municipality levied applicable development charges to support the project at that time.  (A ticketing surcharge was implemented to support a fundraising campaign for the capital project, which raised over $325,000 – now held in a reserve fund.) 

 

The AHP identified the lack of theatres and facilities as the largest gap in Ottawa’s literary, media and performing arts spaces.  These facilities make the creation, development and presentation of local work, as performed by local artists, a priority.  The Centrepointe Theatre Expansion project was captured as an underway-development within this plan.  The project ceased in 2003, following completion of the design development phase.

 

The proposed expansion would include an ancillary mid-sized venue accessible to local community non-profit groups and emerging artists.

 

Priority 2 –  Cultural Infrastructure Stimulus Fund Community Projects

 

Aimed at providing funding to non-profit arts and heritage organizations for capital projects that provide a solution to outstanding cultural facility needs in the community, this funding will be disbursed to the highest-priority community-based projects administered by the City of Ottawa using existing criteria of the Major Capital Cultural Facility Funding Program.  This is a self-help program, whereby the City of Ottawa, in partnership with a cultural group, assists in the funding of eligible capital projects.

 

The assessment criteria for the disbursement of funds are:

 

Project Merit

 

This is the principal assessment criterion, which identifies clear cultural goals and objectives, requisite ability and means to achieve the project, high standards in programming, professional standards in cultural leadership, and a solid track record.

 

Community Impact

 

This evaluates local support and participation, assessing the contribution each applicant organization makes to: 1) the general public (community participation, volunteerism, audience development, accessibility of programs, partnerships, etc.); and, 2) the cultural discipline.

 

Organizational Effectiveness

 

This speaks to effective planning, fiscal responsibility, track record (including past successes and alternate funding capabilities, like fundraising, sponsorship, self-generated, in-kind donations, etc.), professional standards and active leadership by the Board of Directors.

 

The following organizations could benefit from this Cultural Facilities Stimulus Fund[1]:

 

·         Ottawa Heritage Workers Centre House  - Restoration of exterior fabric of the Gamman house (project cost $100,000);

 

 

·         Watson’s Mill - Ongoing windows and doors restoration project; ceiling whitewashing of this historic mill (project cost $10,000);

 

·         La Nouvelle Scéne (LNS) - In 2008, LNS commissioned a study on the condition of the building. The building requires $450,000 in mechanical, electrical and architectural upgrades to resolve several building deficiencies.  

 

The organization has decided that it would be more cost-effective to incorporate the upgrades into an expansion project that would add a second storey to the building and has recently commissioned an architect and construction firm to provide a total cost breakdown.  Preliminary estimates for the total project are $5M and LNS has requested $1M from the City.

 

 

 

CONSULTATION

 

All projects identified in Document 1 that required an Environmental Assessment (EA) were subject to public consultation in accordance with Provincial and City requirements.  Where an EA was not required, the projects identified have been subject to other council discussions and priority setting, with appropriate public input sought. 

 

 

FINANCIAL IMPLICATIONS

 

The 2009 Federal Budget calls for immediate action to simulate the economy by building and renewing infrastructure within our communities.

 

The financial implications are outlined in this report.  Based on our estimates of the four Stimulus Programs, the City may require an additional $110.88M to fund the supporting projects. The City’s share will come from the advancement of debt, and the combination of development charges and rate supported reserve funds.

 

 

SUPPORTING DOCUMENTATION

 

Document 1: Priority List of Ready-To-Go Infrastructure Projects

 

 

DISPOSITION

 

Once approved by Council, staff will begin working with the federal and provincial governments to identify which projects may go forward, what timelines will be involved, and what funding formulas will be required.  

 

Once the specific details of the federal funding eligibility and application process become available, staff will develop and submit applications, in order of priority, for the projects that are eligible.

 

 



[1] Projects listed in no particular order; only previously identified projects listed; eligible organizations subject to application and evaluation to ensure a transparent process.