1.             INSTALLATION OF INLET CONTROL DEVICES

 

INSTALLATION DES DISPOSITIFS DE CONTRÔLE DU DÉBIT

 

 

Committee recommendation

 

That Council direct City Construction Inspection staff to develop and implement protocols by January 2010 that require a professional engineer to certify that all required Inlet Control Devices are properly installed and inspected prior to permitting a new storm sewer to connect to the City’s existing storm sewer system.

 

 

Recommandation DU Comité

 

Que le Conseil dirige le personnel des inspections de chantiers de construction de la Ville d’élaborer et mettre en œuvre d’ici janvier 2010 des protocoles qui requièrent que des ingénieurs certifient que tous les dispositifs de contrôle du débit sont correctement installés et inspectés avant de permettre qu’un nouvel égout pluvial soit raccordé au réseau d’égouts pluviaux actuel de la Ville.

 

 

Documentation

 

1.      Coordinator, Planning and Environment Committee report dated 20 October 2009 (ACS2008-CCS-PEC-0024).

 

 

 


Report to/Rapport au :

 

Council / Conseil

 

20 October 2009 / le 20 octobre 2009

 

Submitted by/Soumis par : Carole Langford, Committee Coordinator / Coordonnateur du comité

 

Contact Person/Personne ressource : Carole Langford, Committee Coordinator

City Clerk’s Branch/Direction du greffe

(613) 580-2424 x28934, carole.langford@ottawa.ca

 

Stittsville-Kanata West (6), Kanata South (23)

Ref N°: ACS2009-CCS-PEC-0024

 

 

SUBJECT:

INSTALLATION OF INLET CONTROL DEVICES

 

 

OBJET :

INSTALLATION DES DISPOSITIFS DE CONTRÔLE DU DÉBIT

 

 

REPORT RECOMMENDATION

 

That Council direct City Construction Inspection staff to develop and implement protocols by January 2010 that require a professional engineer to certify that all required Inlet Control Devices are properly installed and inspected prior to permitting a new storm sewer to connect to the City’s existing storm sewer system.

 

 

RECOMMANDATION DU RAPPORT

 

Que le Conseil dirige le personnel des inspections de chantiers de construction de la Ville d’élaborer et mettre en œuvre d’ici janvier 2010 des protocoles qui requièrent que des ingénieurs certifient que tous les dispositifs de contrôle du débit sont correctement installés et inspectés avant de permettre qu’un nouvel égout pluvial soit raccordé au réseau d’égouts pluviaux actuel de la Ville.

 

 

BACKGROUND

 

At its meeting on 13 October 2009, the Planning and Environment Committee received a presentation by staff regarding the modeling for water levels in the Carp River.  After extensive discussion, the Committee approved the following motion brought forward by Councillor Feltmate:

 

Whereas the City of Ottawa’s Design Guidelines has been shown to provide a high degree of protection against flooding during storm events, and

 

Whereas Inlet Control Devices are one of the measures that City’s Design Guidelines utilizes to prevent against basement flooding, and

 

Whereas in new developments or city projects, where projects are still under construction, it is prudent to ensure that Inlet Control Devices are installed as early as possible;

 

Therefore be it resolved that City Construction Inspection staff develop and implement protocols by January 2010 that require a professional engineer to certify that all required Inlet Control Devices are properly installed and inspected prior to permitting a new storm sewer to connect to the City’s existing storm sewer system.

 

 

CONSULTATION

 

Planning and Legal Services staff were in attendance at the meeting and are aware of this motion.

 

LEGAL/RISK MANAGEMENT IMPLICATIONS

 

The installation of Inlet Control Devices is a measure that reduces the likelihood of basement flooding and other flooding related damage from occurring during a significant rain event.  Accordingly, the proper installation of Inlet Control Devices is a recommended risk management measure.

 

FINANCIAL IMPLICATIONS

 

There are no financial implications.

 

SUPPORTING DOCUMENTATION

 

Document 1 –   Carp River Model Update Presentation (Previously distributed and held on file.)

Document 2 –   Draft Minute Extract of the Planning and Environment Committee meeting on 13 October 2009

 

DISPOSITION

 

Following approval of the report, Planning staff to implement accordingly.

 

 

 


                                                                                                                       document 2

 

Update: modeling for water levels in the Carp River with updated data

MISE À JOUR DE la modélisation des niveaux d’eau de la rivière Carp avec des données à jour

             Stittsville-Kanata west (6)/ouest, kanata south/sud (23)

 

Written correspondence was received on 13 October 2009 from Ted Cooper and is held on file with the City Clerk.

 

Mike Wildman, Manager, Development Review (Suburban), provided a PowerPoint presentation, which is held on file with the City Clerk.  Don Herweyer, Project Lead for the Kanata-West Environmental Assessments and Don Moss, Professional Engineer, Greenland International accompanied him.  Also in attendance was Mr. Leman, a representative of the Mississippi Valley Conservation Authority (MVCA) attended to assist in answering committee’s questions.

 

By way of introduction, Mr. Wildman informed Members Mr. Moss’ employer; Greenland International specialises in environmental management, flooding impact, stormwater and water quality.  He has been assisting the City throughout the Third Party Review (TPR) and continues to assist in a number of exercises, including the model keeper role.

 

In response to questions from Committee Members, staff supplied the following responses:

 

·    A model begins with a design drawing, with various elevation drawings that are inserted into the model, and then they display alternate effects on a stormwater pond.

·    Build up of sediment can occur over time on the bottom of a pond, causing water levels to rise. As with all of the City’s maintenance structures, a maintenance schedule is in place for stormwater ponds with regular monitoring to identify ponds that may need cleaning or high water levels caused by sediment build up.

·    Set flood levels for flood mapping is provincially mandated and states that if a summer rainfall is used, it is assumed that it is uniform over the entire watershed.

·    In the original study of the Carp River watershed and sub-watershed, spring melt was incorporated into the scenario.

·    During the TPR, various locations were reviewed to determine the most effective and efficient placement of monitoring equipment. Presently, there are five City rain gauges to calibrate the radar data. Going forward two more gauges will be in operation within the Carp area, along with the current one located at Richardson Side Road. Poole Creek and the upper end of the Carp River were two additional proposed locations.

·    The gauges currently being installed, including the one in the Carp River, measure both velocity and water levels, the gauges used in the past only measured water levels. A reason for switching to a different type of gauge was that electronic components were being damaged by sediment in the river. The initial finding of this alternate equipment has been positive and it is the belief that it will help resolve some of the problems being faced.

·    Velocity measurements are important when trying to establish features within the models, such as timing of flow entering from various points into a corridor. If water flows reach the point of velocity of zero, the result is the creation of a lake.

·    If the proposed future model were run, TPR identified it would have higher water levels through the corridor. Subsequently, as part of the model keeper role, continuous work is being done, including the investigation of widening alternatives, a mandate within the City’s recommendations.

·    The Glen Cairn Pond did not overflow, high water marks in the pond were staked at 95.2, the rim of the pond is at 96; the pond still had a lot of capacity during the storm. Water levels were staked from Eagleson Road down through Glen Cairn to the Village of Carp.

·    The current model begins with the Glen Cairn Facility and does not model upstream from the facility. The upstream work was done independently with another consultant in 2003.

·    There are two levels of models that are created for this type of studies, the planning level model in which all that is looked at is what is going to flood the Carp River and the corridor and the model which looks at roads and sewers going through new developments.

·    The models reviewed under the TPR were specifically designed to ensure that the corridor would not have higher water levels than the existing model.  The new development that was proposed for Kanata West took this model and created a second series of models to look at roads and sewers.

·    When the Glen Cairn community and its facility were developed, they did not have computers or the technology that exist today. Currently the City’s design standards are better or exceed most of the provincially mandated ones. 

·    When updating the model, the stormwater management facilities and the drainage areas were added. The consultants, who produced the subdivision, did a hydraulic analysis that runs through the pipe network.

·    The corridor widening and retrofit proposed for the Carp River restoration plan is set to approximately 500 metres downstream to Richardson Side Road.

·    27 clusters were identified in the flooding areas, among them Westwood, west of Stittsville, the majority of the rainfall fell on Amberwood area; however, the Westwood area suffered worst flooding effects. Instances such as this were reviewed and investigated by Mr. Newall’s staff. Some of the areas had a number of different occurrences that caused flooding, including not experiencing a major system, no control devices, and others were due to backwater valves not working.

·    The Glen Cairn Facility was not reviewed originally. In light of what happened in July, they took the opportunity to study the Glen Cairn neighbourhood, looking at road patterns and other features. The Glen Cairn Facility is unique, the City’s stormwater management facilities was originally a conservation authority Facility. The Glen Cairn Detention Basin is owned by the conservation authority. 

·    The Glen Cairn Facility was originally constructed with the assistance of the Township of Goulbourn and the MVCA acquired the property to have the facility constructed. It is unclear whether or not there was an agreement with the municipality with respect to additional work.

·    The facility was constructed according to the standards that were appropriate in mid-1970s; it was designed to accommodate the 100-year storm from the area upstream of it.

 

In summation, Mr. Wildman ensured that the Carp is performing as it was intended to function in the original models and in the TPR.

 

Moved by P. Feltmate

 

Whereas the City of Ottawa’s Design Guidelines has been shown to provide a high degree of protection against flooding during storm events, and

 

Whereas Inlet Control Devices are one of the measures that City’s Design Guidelines utilizes to prevent against basement flooding, and

 

Whereas in new developments or city projects, where projects are still under construction, it is prudent to ensure that Inlet Control Devices are installed as early as possible;

 

Therefore be it resolved that City Construction Inspection staff develop and implement protocols by January 2010 that require a professional engineer to certify that all required Inlet Control Devices are properly installed and inspected prior to permitting a new storm sewer to connect to the City’s existing storm sewer system.

 

                                                                                                CARRIED

 

That the Planning and Environment Committee receive a presentation on the above-noted subject.

 

                                                                                                RECEIVED

 

DIRECTION TO STAFF

Infrastructure Services and Community Sustainability staff to provide Councillor Feltmate with a report showing when the Glen Cairn pond was cleaned out.