Rec # |
Recommendation |
Management Response |
Est
Comp Date |
Status Updates (In Progress; Pending; Complete; Requires Resolution) |
3 3 |
That
the service level agreements between DWS and COEs be reviewed jointly by both
parties on an annual basis as part of the budgeting cycle and adjusted to
document actual or expected service levels. |
Management
agrees with this recommendation. This review will be initiated in conjunction
with the work related to Recommendation 24. |
Q3
2006 |
December 2009: In
Progress. The
corporation continues with its implementation of the recent organizational
realignment, and the Environmental Services department is initiating its own
reorganization process. Phase III of the Shared Services Review is underway.
A Steering Committee of the shared services Directors will guide
implementation of new SLAs, funding models and reporting frameworks.
Completion is anticipated by Q1 2010. The Operational Plan is a key service
delivery document for Drinking Water Services involving the Environmental
Services department's main partners, Planning and Growth Management and
Infrastructure Services. The Plan provides for infrastructure, rehabilitation
and the provision of management reviews, completed regularly as part of the
operating Top Management review processes. More work will be done on
inter-departmental relationships subject to outcomes of the corporate shared
services review. June
2009: The corporation is starting its
implementation of the recent organizational realignment, and the
Environmental Services department is initiating its own reorganization
process. Phase III of the Shared Services Review is underway. A Steering
Committee of the shared services Directors will guide implementation of new
SLAs, funding models and reporting frameworks. Completion is anticipated by
Q1 2010. The Operational Plan is a key service delivery document for Drinking
Water Services involving the Environmental Services department's main
partners, Planning and Growth Management and Infrastructure Services. The
Plan provides for infrastructure, rehabilitation and the provision of
management reviews, completed regularly as part of the operating Top
Management review processes. More
work will be done on inter-departmental relationships subject to outcomes of
the corporate shared services review. |
11 11 |
Procedures
to reconcile water accounts with property tax accounts (VTAX), meters
installed (ITX/IIMS) and building permits issued should be developed to help
mitigate the risk of incomplete billings. |
Management
agrees with this recommendation. This initiative will assist in ensuring that
all customers are being billed. Currently, this cannot be accommodated within
existing resources. Additional resources will need to be identified as part
of the 2007 Corporate Services Departmental work plan and budget. |
Q4
2007 |
December 2009:
In Progress. The development of the Building Permits Tracking
System is complete and implementation will start in January 2010. June
2009: The Building Permits tracking system is in the process of being scoped
with programming to start in Q3 2009. Deployment is expected in Q4 2009. |