2
2
|
That
the City Manager ensure there is a review to update the Centres of Expertise
Service Level Agreements, including definition of performance levels,
monitoring requirements and approach for identifying and resolving issues or
disputes.
|
Management
agrees with this recommendation. A draft proposed process, addressing all of
these elements, will be presented to Senior Management Team (SMT) at the
January 2006 meeting. This project is a priority identified in the 2006
Corporate Services departmental business plan and will be included in the
2006 workplan of the Office of the Chief Corporate Services Officer.
|
Q4 2006
|
December 2009: In
Progress.
Service
levels between client departments and Shared Services departments will be
negotiated and documented in the departmental Service Excellence Plans to be
completed by the end of Q2 2010. Three options for post-implementation
governance of the Shared Services Model have been developed. The options include an approach for
identifying and resolving issues or disputes.
These options will be reviewed by the Steering Committee in Q1 2010
and implementation will continue throughout 2010.
June
2009: Shared Services Review - Phase II: Completed on March 25, 2009 as part
of the realignment exercise. A new integrated management framework was
established for shared services and new management organizational structures
were defined for each of the shared services departments. These changes were
made to respond to the results of the Phase I assessment.
Shared Services Review - Phase III: Currently underway. A steering committee
of the shared services directors has been established to guide the
implementation of new service agreements, funding models and reporting
frameworks. The implementation is also supported by a dedicated project team
and a working group made up of both representatives from the shared services
departments and the client departments. A more detailed project plan has been
developed for this phase of the implementation, which includes a significant
stream of work focussed on implementation of a service excellence culture. As
part of this scoping and planning exercise, the timelines have been reviewed
and adjusted. The anticipated completion date is now Q1 2010.
December 2008: Shared Services Review - Phase I: Completed in November 2008.
A consultant was engaged to work with EMC and other key stakeholders to
define the service delivery principles for the City. Phases two and three of
the project will be led by the Director, Organizational Development &
Performance and will involve the development and implementation of mechanisms
to achieve the principles and concepts endorsed by EMC.
Shared Services Review - Phase II: Currently underway, to be complete by Q1
2009. This scope of this project is to design and implement an improved
service delivery model for shared services that builds on Phase 1 findings and
recommendations and fully supports the corporate realignment that is
currently underway. It will define the management organizational structure
for the “Centres of Expertise” and will identify the roles and functions that
will be need to be included in the organizational structures of the service
areas.
Shared Services Review - Phase III: will complete the full implementation of
the Shared Services Model including a review of service level agreements,
funding models, and reporting frameworks. The implementation plan for Phase
III is expected to be complete by the end of Q2 2009.
August 2008: The BTS Department initiated a project to refine the shared
services model so that it supports the City’s commitment to service
excellence and meets client service values. The project will be undertaken in
three phases and will run over the course of a year. A request for proposal
was issued in July to engage the services of an external consultant that will
work with EMC and other key stakeholders to define the service delivery
principles for the City. Phases two
and three of the project will be led by the Executive Director, BTS and will
involve the development and implementation of mechanisms to achieve the
principles and concepts endorsed by EMC.
May 2008: A briefing note went to EMC in April outlining a proposed
methodology and timelines to examine and resolve outstanding issues related
to shared services (COEs) including the development of new service level
agreements (SLAs). The shared services
branches are in the process of reviewing how their service delivery models
will complement the new corporate guidance and service excellence
initiatives. New SLAs are expected to be developed in 2009 once the service
delivery model reviews are completed.
January 2008: EMC discussed this January 14, 2008. Action: COE Branch Directors to prepare a
Briefing Note to address the following questions: Outline Audit
recommendations specific to their branch and management responses re COE model
and its components; Outline branch issues that came out of 2006 COE review
work and assessment of what is required to be done to address; Outline of
work that has occurred since 2006 and work yet to occur with respect to
branch plans to address outstanding COE issues; Associated timelines and
proposed process to implement. Briefing Notes to be considered at the
February 25, 2008 EMC meeting.
|
4
4
4
4
|
That
the CCPR Officer introduce integrated risk management within the City, as
part of the planning and performance management cycle. This would include such activities as:
a) development of an integrated risk management policy,
b) development of tools and approaches for risk management, and
c) provision of risk management training.
|
Although
Management agrees with the Auditor General’s recommendation in principle,
Management does not believe it would be practical to implement this
recommendation at this point. The cost/benefit of implementing a full blown,
organization-wide risk management initiative, as suggested by the Auditor
General, is not clear, nor is it clear that this is a widely accepted best
practice in municipal governance. Recent implementation of these types of
programs in the private sector has been driven to a considerable extent by
Sarbanes-Oxley requirements in the U.S.
To Management’s knowledge, in the few cases where Canadian
municipalities have experimented with them, implementation has not been
successful.
Management’s priority at this point, from a management control framework
perspective, is on rolling out the planning framework and developing and
implementing the performance measurement and reporting framework, throughout
the organization over the next 2-3 years. Nonetheless, certain steps Management
is taking to enhance the Corporate planning process, such as the presentation
of a comprehensive environmental scan, which will identify risks to be
considered in developing the City Corporate Plan and Departmental Business
plans, will address this issue.
Regarding the development of an integrated risk management policy management,
Management believes that the Auditor General’s observations in this area
should take into account that the City has a risk management policy, which
was approved by Council in 2001, confirms the City’s commitment to sound risk
management processes. Some of the specific measures that Corporate Services
has taken to explicitly address risks in different areas are outlined in this
policy. For example, risk management principles are explicitly applied in
investment decisions, in decisions regarding insurance coverage and in
providing and maintaining safe conditions in the workplace. In addition, risk
management processes are also applied in other key areas.
The Emergency Measures Unit has identified catastrophic risks that could
impact the City and has developed a program/plan to address them. Moreover,
on an ongoing basis, Public Works staff perform construction/maintenance
project risk assessments and procedures have been adopted by the City to
ensure that risks are reasonably transferred through the tender, contract and
agreement process. Both Real Property Asset Management and Public Works and
Services have adopted Comprehensive Asset Management Strategies that have
been approved by City Council and that include inventories, gap analyses and
strategies for decommissioning and rehabilitating infrastructure reaching the
end of its lifecycle.
|
Q4 2008
|
December 31,
2009: In Progress.
An ERM policy was developed and will proceed to SMC, EC, CSEDC and Council in
Q1 2010. An ERM framework, tools and
templates, have been developed including a Glossary, Risk Impact Measurement
chart stating the City’s tolerance for risk, a “How to do a Risk Assessment”
module, etc. Training on risk management
will be developed in 2010 based on the framework.
June
2009: The ERM Committee has had several meetings and a risk assessment demo
was held on May 12, 2009 with participation from most City departments.
Neither the ERM policy nor TOR for the Steering Committee went to Council in
Q2 2009. Corporate Risk Management was transferred to Organizational
Development and Performance branch on July 2, 2009. It is anticipated the ERM
framework will be complete in Q4 2009.
December 2008: Further to the August 2008 update, the following actions have
taken place:
a) City Council approved the permanent funding of $120K for both the ERM
program and the Coordinator, Corporate Risk Management position as part of
the 2009 budget deliberations in December 2008.
b) A new Corporate Enhanced Risk Management policy has been drafted and will
be forwarded to Council for approval in Q2 2009. Once approval has been
granted, the new policy will replace the 2001 Risk Management policy.
c) The Coordinator, Corporate Risk Management continues to provide strategic
advice and assistance to the SBR project. Specific assistance is rendered
with the Risk Management Module to capture the three to five most significant
risks per Branch and identify how those risks will be addressed.
d) A "Risk Review" of the Parks and Recreation Program Delivery
function has been completed.
e) The first meeting of the ERM Steering Committee was held on November 13,
2008.
f) The first ERM report to Council is being drafted together with an
implementation plan. This is expected to go forward in Q2 2009.
g) Development of an ERM framework is underway and is expected to be complete
in Q2 2009.
August 2008: Further to City Council approval of Phase 1 of an Enhanced Risk
Management (ERM) program, the following actions have taken place:
a) A Corporate Risk Management Officer has been hired to implement Council's
directives;
b) The Corporate Risk Management Officer has been providing strategic advice
and assistance to the Strategic Branch Review (SBR) project;
c) One of the two risk reviews scheduled for 2008 has been completed as
directed by Council;
d) The composition of the Corporate Risk Management Committee as well as the
draft terms of reference have been finalized.
A report on the progress of this initiative, together with recommendations
for next steps, including the permanent funding of the Corporate Risk
Management Officer position is expected in the late fall of 2008.
May 2008: As part of the 2008 budget, City Council approved the
implementation of Phase 1 of an Enhanced Risk Management (ERM) program, which
would include:
a) developing an ERM framework aligned with the Strategic Branch Reviews;
b) training around the framework;
c) two risk reviews with key clients; and
d)
the establishment of a Risk Committee.
Council approved one-time funding of $150K and one FTE for a Corporate Risk
Manager to implement the above. It is
anticipated that a status report will be presented to Committee and Council
in Q4 2008.
January 2008: The required funding for 2008 has been provisionally approved
pending completion of the Operational Budget Reviews for Administrative
Services. On March 7, 2008 a
presentation will be made to Long-Range Financial Planning Sub-Committee outlining
the planned approach to the broader, systems-wide initiative of
"Enterprise Risk Management". Risk management approaches have been
included in the detailed design for the strategic branch review process that
will go to Council on March 13, 2008.
September 2007: The required funding for 2008 has been submitted as a budget
pressure. In the meantime, risk
management approaches are being built in to the conceptual design that has
begun for the branch service review process.
May 31, 2007: Agreed to action plan.
Subject to further discussion between the Auditor General and the
Council Audit Working Group. A business case for the potential implementation
of an integrated risk management framework was completed in January
2007. Staff recommendation remains
deferring implementation of such a framework to focus on other priorities.
March 6, 2007: Resolution. Briefing note provided to CAWG. AG and CAWG confirmed that proposed actions
met the intent of the audit.
January 29, 2007: CAWG considered the business case
CPPRO will undertake the following to address the AG recommendation:
i) modify the existing risk management policy or develop a new Corporate
integrated risk management policy by 2008;
ii) introduce into its guidance for the preparation of branch business plans,
a section that outlines the potential risks to the achievement of the branch
objectives;
iii) develop a template that can be used to capture the 3-5 most significant
risks for each branch & how those risks are addressed - this will be
integrated with the branch business plan templates & will be made
available in 2008 for the 2009 business planning cycle; &
iv) develop a course to be offered in the latter part of 2008 on risk
management relating to the application of these concepts & the use of the
template.
Since the budget requirement was identified after the tabling of the original
report, discussion and approval will be required of CAWG. This course will be offered to management
staff involved in the evaluation of risk as part of the business planning
process. We estimate the cost of
policy development, training material development & delivery is $150K,
which we will include as a budget pressure for 2008.
|