Rec # |
Recommendation |
Management Response |
Est
Comp Date |
Status Updates (In Progress; Pending; Complete; Requires Resolution) |
|
1 |
That the Building Code Services Branch
(BCSB) ensure the documentation received with the
Application For a Permit to Construct or Demolish is complete in all cases,
as we found in this case the documentation provided with the application for
demolition was not complete. |
Management does not agree with the recommendation. Management
does not agree that there were procedural omissions with regard to the
applications for demolition and construction at 215 Preston Street. Building Code Services (BCS) did receive
sufficiently detailed documentation to ensure that the proposed demolition
and construction was reasonable and could be carried out in accordance with
the Building Code. It is the role of the Chief Building Official (CBO) to
determine the sufficiency of information supporting an application based on
the unique set of circumstances and conditions of each project and the CBO’s
interpretation of the requirements and standards as they apply to the
application. In this instance, the
submissions were deemed sufficient for the purpose of issuing the permits. |
December 2009: Requires Resolution. |
||
2 2 |
That the BCSB advise property owners that
the Branch reserves the right to verify the actual construction cost and to
adjust the fees accordingly. If this
cannot be done, that the BCSB implements a database of cost per unit area to
permit it to verify the budget estimates provided with the application. |
Management does not agree with the recommendation. In
the absence of legislative authority, there is no basis for verifying the
actual construction costs and adjusting the fees after the permit has been
issued and the construction completed.
The process of verification of estimated value of construction and
adjusting undervalued fees prior to the issuance of the permit is already in
place. This is a standard practice of
municipalities that assess fees based on the value of construction. While
the branch maintains a database of cost per unit area for new construction,
it is too difficult to obtain a cost per unit area for renovations due to the
nature of this construction activity (too many variables and unknowns). The
building permit fee is based on “assessed valuation of the work”, which is
not the same as the “actual construction costs”. An “Architect’s estimate of costs” may
include many elements, which do not form part of the “assessed valuation of
the work”, and which may vary greatly from the “actual construction costs”,
due to many unquantifiable factors. Finally,
the Building Code Act and Building Code prevent the permit fees collected
from exceeding the cost of providing the service, along with reasonable reserves
to offset liability and construction fluctuations. The Chief Building Official is
legislatively required to provide an annual report on these matters, and any
request for increases are subject to consultation with the industry and
public. |
December 2009: Requires Resolution. |
||
3 |
That the BCSB ensure all files are properly
documented and complete, including a complete record of telephone
conversations, for future reference and possible litigation. |
Management does not agree with the recommendation. It is the current practice for staff to
document observations and key discussions, particularly where conflict and/or
litigation is anticipated. However, it
is not possible, from a time-management perspective, to document all
communications. Each Building Official
must make a subjective assessment of the relevance of the communication and
the degree of recording based on the circumstances at the time of the
communication. Further, a requirement
that all files include a record of all telephone conversations would require
significant additional resources and investment in technology, for the few
occasions where conflict arises. |
December 2009: Requires Resolution. |
||
4 4 |
That
Occupancy Permits be issued only when all the construction review reports by
all professionals have been received to the satisfaction of the City. |
Management does not agree with the recommendation. In 2002, the branch established an operational policy that requires all required construction review reports to be submitted prior to the issuance of the “partial occupancy permit”; although the OBC only requires this threshold to be met prior to the “final occupancy permit” being issued. As a best practice, BCS moved this threshold to an earlier stage because once a building is occupied it becomes more difficult to address outstanding deficiencies. In
this instance, based on the Architect’s assurance that the reports would be
submitted in short order and relying on the professional integrity accorded
an Architect and their legal responsibilities under the Architect Act, the
Inspector issued the partial occupancy permit. The
Architect subsequently notified the City that he and the Structural Engineer
of Record would not produce the reports due to a dispute with their client, which
has yet to be resolved. The Architect
alleged there were welding deficiencies, and on this basis, an occupancy
permit should not have been issued. As
they are lawfully entitled to, the owners engaged the services of two other
engineering firms, one specialized in welding, to carry out the reviews and
provide the required reports. These
reports confirmed the structural adequacy of the welds and the structure;
therefore, the partial occupancy permit was allowed to stand as the
requirements for partial occupancy had been met. Finally,
it is noted that there are no areas of the building being used that are
prohibited from use and occupancy, although the final occupancy permit has
not been issued (only the partial) and the permit file remains open. |
December 2009:
Requires Resolution. |
||
5 5 |
That Inspectors be instructed to
actively monitor sites for which an application for building permit has been
submitted, including access to the site if necessary. |
Management does not agree with the recommendation. Such
inspections would serve only to document the fact that illegal construction
or demolition is continuing. As well,
caution must be taken to ensure that any inspections, prior to the issuance
of a permit, not be for the purpose of reviewing the illegal construction for
Code compliance, nor appear to do so, as this would encourage illegal
construction to continue. The
implementation of this recommendation will require additional resources to
integrate these inspections in addition to the mandatory inspections, which
form the basis of the City’s existing program and service delivery
levels. This recommendation will be
explored when the branch’s Strategic Branch Review is undertaken in Q2 2009,
as this review will be an appropriate forum to consider higher service
delivery levels. In
this instance, the Inspector was well aware of the on-going illegal
construction activities, had issued the requisite Orders and a court action
had commenced. Any additional
inspections after the Stop Work Order was issued and prior to the completion
of the construction (a 7 week period) would have confirmed only that illegal
construction was continuing, which was already known to staff and
sufficiently documented for purposes of the court case. Additional resources would have been
required to monitor the site more frequently.
|
December 2009: Requires Resolution. |
||
7 |
That the City require that structural
review letters be reviewed by the City’s Structural Review Engineer in cases
similar to the subject project. |
Management
does not agree with the recommendation.
Building
Officials (Plans Examiners and Building Inspectors) are qualified by the
Province of Ontario to review structural review letters. In addition, the branch provides Building
Officials valuable in-house training to sufficiently equip them to review the
reports and render a decision as to adequacy.
The Building Officials do consult with the branch’s Building Code
Engineers in cases where they do not feel that the review letters are
adequate or where the issues are of such complexity as to require additional
review. In
this case, the reports submitted by the engineering consultant were
considered sufficient for purposes of determining compliance. |
|
December 2009:
Requires resolution. |
|
9 |
That
in future similar situations where an architect, engineer, or other
professional regulated by a professional regulatory body, appears to have
engaged in conduct unbecoming the standards expected by such a professional
and/or where the public interest demands, the City pursue complaints to the
OAA, or other such professional body as the case may be. |
Management
agrees with the recommendation. However,
in order to effectively implement this recommendation, additional specialized
resources (1 FTE, vehicle, equipment, training and qualification and work
space – minimum $125K) would be required to investigate, document and refer
complaints to the governing bodies where the actions or omissions of the
professionals have undermined the Building Code Act and the OBC or the CBO’s
ability to enforce the legislations.
This will be explored when the branch’s Strategic Branch Review is
undertaken in Q2 2009, as this review will consider changes to program and
service delivery levels. |
|
December 2009: Pending. The
Strategic Branch Review program has been discontinued. When a new program is implemented in its
place, the branch will include this higher standard for consideration. |
|
10 |
That the City develop
a policy by which the BCSB can request an injunction or restraining order to
ensure that the Owner complies in cases of disregard for the rules, such as
this example. |
Management
does not agree with the recommendation. Each case must be evaluated on its own merits and the option to seek an injunction is already available in the Building Code Act and has been resorted to in the past, as circumstances have warranted. In addition, the seeking of injunctions requires considerable resource allocation, on the part of both BCS and Legal Services. Additional resources would be required to implement a more aggressive enforcement strategy. Whether injunctions are obtained is a determination of the Court and they are only granted in extraordinary circumstances. In
this instance, BCS did undertake the necessary inspections, did issue the
required Orders and did successfully prosecute the owners of 215 Preston
Street. Once the owners obtained the
requisite planning approvals, a permit was issued, construction was inspected
and it was determined to meet the minimum OBC standards. |
|
December 2009: Requires Resolution. |
|
11 11 11 |
That the BCSB ensure compliance with the
Building Code Act and not try to balance the BCSB enforcement obligations and
requirements with the business objectives of the Owner. |
Management
does not agree with the recommendation.
BCS
did escalate enforcement action when the owners failed to comply with the
Orders and successfully prosecuted the owners. Once the owners had obtained the requisite
planning approvals, a permit was issued, construction was inspected and it
was determined to meet the minimum OBC standards. The Act is written in terms of imperative “shall” and permissive “may” statements. While the CBO and Building Inspectors “shall” enforce the Code, they “may” issue Orders, and “may” prosecute. The reason for this disparity, in language, is that the legislators recognize that enforcement is achieved when there is compliance. This is usually arrived at without the necessity of either Orders or prosecutions and is usually in response to an incremental escalation of enforcement options. In
addition, the CBO is a persona designata deriving authority from the Building
Code Act, with responsibilities defined by, not only the Act and the OBC, but
also by the Building By-law, Ministry rulings, the Building Code Commission
and the Building Materials Evaluation Commission rulings or decisions, and
more importantly, by the judicial system (court decisions and common law
principles). How the Act and Code are
interpreted and implemented is very much couched or formulated from best
practices, legal principles and actual court case precedents. In fact, there are only three entities that
can determine Code compliance: the Chief Building Official, the Building Code
Commission (for sufficiency only) and the Courts. The
Courts have held that the Act is “a complex piece of legislation which is, in
general terms, aimed at setting and enforcing standards for all manner of
construction and building projects in Ontario.” In this regard, the complexity and
technical nature of the Act require flexibility and balancing of various
factors. There is an expected degree of reasonableness and flexibility to
account for other variables, including business and practical realities of
the property owner and the building industry.
Thus, the branch mandate refers to the regulation of construction of
buildings, first through leadership, education and collaboration. If these approaches fail in obtaining
compliance, then through enforcement, including prosecution, etc. This was the approach adopted for this
particular case and although orders, court prosecution, etc., were required,
the construction was made compliant and the occupancy permit was eventually
issued. If
the CBO does not have discretion or flexibility in the administration or
enforcement of the OBC, this could lead to unintended and undesirable results
of increased Code non-compliance and may force aspects of the building
industry “underground”. Diversion of
this nature would defeat the objectives of the Act which seeks to ensure
minimum standards for building construction in Ontario. Finally, there is misapprehension as to
what BCS is attempting to balance. It
is not the needs of an individual business owner. Rather, it is recognition of the realities
of a fast-paced development construction industry and the benefits to the
broader public. The objective is to
ensure that the construction will achieve Code compliance and that there is a
sufficient discipline within the industry to enable this to occur. |
|
December 2009: Requires Resolution. . |
|