7. PROJECT IMPLEMENTATION - 25 Esquimault avenue Qualicum - Graham park community Building MISE
EN œuvre DU PROJET – 25, avenue esquimault - centre communautaire dE
QUALICUM-parc GRAHAM |
That Council:
1.
Approve using a City
initiated and managed project implementation process, as outlined in this
report, rather than a request for proposal process, for undertaking the following
work:
a)
The construction of a
new community building to serve the Qualicum-Graham Park area on the property
municipally known as 48 Nanaimo Drive
being Nanaimo Park and shown as Parcel “B”
in Document 1;
b)
The demolition of the
existing building at 25 Esquimault Avenue shown as Parcel “A” in
Document 1;
c)
The remediation of the
environmental contamination at 25 Esquimault Avenue shown as Parcel “A”
in Document 1; and
d)
The redevelopment of the
site at 25 Esquimault Avenue shown as Parcel “A” in Document 1.
2.
Approve funding in the amount of $1M, and
authorize debt financing in the same amount, to allow for the construction
of the new community building in Nanaimo Park prior to the proposed sale of
approximately 3.0 acres of the 25 Esquimault Avenue property as outlined in
this report.
3. Upon completion of the remediation of
the environmental contamination at the 25 Esquimault Avenue property, approve
the transfer of approximately 3.0 acres of this property to the Ottawa
Community Lands Development Corporation to initiate the redevelopment and sale
of this property as described in this report.
RecommandationS MODIFéES du
ComitÉ
Que le Conseil :
1.
approuve l’utilisation d’un processus de mise en œuvre de projet initié
et géré par la Ville, comme le souligne le présent rapport, au lieu d’utiliser
le processus de demande de propositions approuvé précédemment, pour les travaux
suivants :
a)
l’aménagement d’un nouveau bâtiment
communautaire qui servirait le secteur Qualicum/parc Graham sur la propriété
située au 48, promenade Nanaimo, qui constitue le parc Nanaimo et qui est
présenté comme la parcelle « B » dans le document 1;
b)
la démolition du bâtiment existant situé au 25,
avenue Esquimault, présenté comme la parcelle « A » dans le
document 1;
c)
la décontamination environnementale de la
propriété située au 25, avenue Esquimault, présentée comme la parcelle « A »
dans le document 1;
d)
le réaménagement de la propriété située au 25,
avenue Esquimault, présentée comme la parcelle « A » dans le
document 1.
2. approuve
l’octroi de crédits d’un montant de 1 M$ et d’autoriser le financement
par emprunt pour la même somme en vue de permettre l’aménagement d’un
nouveau bâtiment communautaire dans le parc Nanaimo avant que n’ait lieu la
vente proposée d’environ 3,0 acres de la propriété située au 25, avenue
Esquimault, comme l’explique le présent rapport.
3. approuve,
après la décontamination environnementale de la propriété située au 25, avenue
Esquimault, le transfert d’environ 3,0 acres de cette propriété à la Société d'aménagement des terrains communautaires d’Ottawa afin de procéder au réaménagement et à la vente de cette
propriété comme l’explique le présent rapport.
DOCUMENTATION
1.
City Manager’s report dated 10 August 2010 (ACS2010-CMR-REP-0036).
Report
to/Rapport au:
Corporate Services and Economic Development Committee
Comité des services organisationnels et du développement économique
and Council / et au Conseil
10 August 2010 / le 10 août 2010
Submitted by/Soumis par: Kent Kirkpatrick,
City Manager / Directeur municipal
Contact
Person/Personne ressource : Gordon MacNair, Director, Real Estate Partnerships and
Development Office/Directeur, Partenariats et Développement en immobilier
(613)
580-2424 x 21217, Gordon.MacNair@Ottawa.ca
Ref N°: ACS2010-CMR-REP-0036 |
SUBJECT:
|
PROJECT
IMPLEMENTATION - Qualicum - |
|
|
OBJET :
|
MISE EN œuvre DU PROJET – 25, avenue esquimault - centre communautaire dE QUALICUM-parc GRAHAM |
REPORT RECOMMENDATIONS
That the Corporate Services and Economic Development
Committee recommend that Council:
1. Approve using a City initiated and
managed project implementation process, as outlined in this report, rather than
a request for proposal process, for undertaking the following work:
a) The construction of a new
community building to serve the Qualicum-Graham Park area on the property
municipally known as 48 Nanaimo Drive
being Nanaimo Park and shown as Parcel
“A” in Document 1;
b) The demolition of the existing
building at 25 Esquimault Avenue shown as Parcel “B” in Document 1;
c) The remediation of the environmental
contamination at
d) The redevelopment of the site at
2. Approve funding in the
amount of $1M to allow for the construction of the new community building in
Nanaimo Park prior to the proposed sale of approximately 3.0 acres of the 25
Esquimault Avenue property as outlined in this report.
3. Upon completion of the remediation of
the environmental contamination at the 25 Esquimault Avenue property, approve
the transfer of approximately 3.0 acres of this property to the Ottawa
Community Lands Development Corporation to initiate the redevelopment and sale
of this property as described in this report.
RECOMMANDATIONS DU RAPPORT
Que le Comité des
services organisationnels et du développement économique recommande au
Conseil :
1.
d’approuver l’utilisation d’un processus de mise en œuvre de projet
initié et géré par la Ville, comme le souligne le présent rapport, au lieu
d’utiliser le processus de demande de propositions approuvé précédemment, pour
les travaux suivants :
a) l’aménagement d’un nouveau bâtiment
communautaire qui servirait le secteur Qualicum/parc Graham sur la propriété
située au 48, promenade Nanaimo, qui constitue le parc Nanaimo et qui est
présenté comme la parcelle « A » dans le document 1;
b)
la démolition du bâtiment existant situé au 25,
avenue Esquimault, présenté comme la parcelle « B » dans le document
1;
c)
la décontamination environnementale de la
propriété située au 25, avenue Esquimault, présentée comme la parcelle
« B » dans le document 1;
d)
le réaménagement de la propriété située au 25,
avenue Esquimault, présentée comme la parcelle « B » dans le document
1.
2. d’approuver
l’octroi de crédits d’un montant de 1 M$ en vue de permettre l’aménagement
d’un nouveau bâtiment communautaire dans le parc Nanaimo avant que n’ait lieu
la vente proposée d’environ 3,0 acres de la propriété située au 25, avenue
Esquimault, comme l’explique le présent rapport.
3. d’approuver,
après la décontamination environnementale de la propriété située au 25, avenue
Esquimault, le transfert d’environ 3,0 acres de cette propriété à la Société d'aménagement des terrains communautaires d’Ottawa afin de procéder au réaménagement et à la vente de cette propriété
comme l’explique le présent rapport.
The subject property, municipally known as 25 Esquimault Avenue, is a 1.41 hectare (3.48 a) site with a one storey vacant school building that has an addition at the north end of the building currently being used as the Qualicum-Graham Park area Community Centre. The property is shown as Parcel “A” in Document 1. The property to the north, shown as Parcel “B” in Document 1, is Nanaimo Park, a City owned park known municipally as 48 Nanaimo Drive.
The City purchased the property
at 25 Esquimault Avenue, as per a City Council directive approved on 23 April
2008 (Report Number ACS 2008-BTS-RPM-0016) following a long history of
multiple issues involving a long-term lease and the contamination of the soil
underneath the existing building from a leaking underground oil storage tank.
At that time, Council approved the report recommendations to acquire the
property in order to avoid potential litigation; to relocate the community
building into Nanaimo Park in order to demolish the existing building at 25
Esquimault and remediate the contaminated land; and then to sell approximately
3.0 acres of the 25 Esquimault property for redevelopment purposes in order to
ultimately reduce the total net project cost to $2,356,000 as indicated in
Table 1 below.
Table 1 |
Acquisition & Redevelopment |
Acquisition Cost (3.5 acres) |
$
2,500,000.00
|
Demolition Cost (bldg is 30,900 sq.ft.) |
$ 650,000.00
|
Remediation Costs
|
$ 600,000.00
|
Temporary relocation of community building facilities |
$ 55,000.00 |
*Construction of New (3,000 sq.ft.) |
$
1,000,000.00
|
Restore property tax base |
($ 575,000.00) |
**Potential Resale Value (3.0 acres) |
($2,000,000.00) |
Outstanding payment of rent |
$ 126,000.00 |
TOTAL NET COST |
$2,356,000.00 |
* This assumes a basic design with details to be
finalized through the public consultation process as part of the redevelopment
proposal
**This assumes that 0.50 acres of the original 3.5
acres would be retained to offset the requirement for a new Community Building
while the balance of the land would be redeveloped for low / medium density
housing.
Funds in the total amount
of $3,805,000 for the acquisition of the 25 Esquimault property ($2.5M), demolition
of the building ($650K), remediation of the environmental contamination ($600K),
and temporary relocation of the community facilities ($55K), as indicated in
Table 1 above, were then made available from within the existing capital budget
for the Realty Services environmental remediation program and a new capital
project account was established accordingly.
Staff were also
directed by Council to prepare a redevelopment proposal for the
lands, which is to include a
A Qualicum-Graham Park Community Building Working Committee, comprised of local residents, was established in 2008 to provide input for the proposed use, design and basic criteria of the new community building. This Committee held four meetings between September 2008 and January 2009, and, facilitated by Parks, Recreation and Culture staff, prepared the room data sheets and blocking plan for the building, shown in Document 2 of this report, to accommodate the various programs to be offered in the new facility.
The Committee also
studied various locations for the new building and determined that, if practical,
the preferred location was an area close to the southerly boundary of Nanaimo
Park with vehicular access and servicing being accommodated via an internal
roadway through the proposed new infill development on the 3.0 acres to the
south at 25 Esquimault Avenue. The Committee also indicated strong support for
low profile residential development on the remainder of the 25 Esquimault
property and, in particular, for “adult style bungalow” development.
A presentation of the Committee’s findings was
made to the Qualicum - Graham Park Community Association Annual General Meeting
held on 22 October 2009. The more than
100 persons attending the meeting indicated unanimous support for the
Committee’s recommendations.
In December
2009, Council approved a staff report (Report Number ACS2009-CMR-REP-0054) recommending
the initiation of a Request for Proposal (RFP) process. That report included provisions
for redevelopment of 25 Esquimault Avenue that would be respectful of the
development concepts approved by the community and subject to a development
agreement that would include conditions for the proponent constructing a new community centre on the Nanaimo Park
property first, then demolishing the existing building and remediating the
contamination before redeveloping the remainder of the 25 Esquimault property. The proposed RFP process would allow community
activities to remain in the existing building until the new facility was
constructed and for the existing funding provision to be used without having to
provide additional up-front funding by the City for the community building in
the amount of $1.0M.
Staff has since been preparing the RFP
package which was to be released in September 2010 for a proponent to construct
a new community centre, demolish the building, remediate the site and
subsequently construct a new development on the lands.
However, in preparing the RFP package staff
has been required to take into account, among a number of factors, the Ontario Ministry
of Environment’s (MOE) new Regulation 511/09, which amends the existing Record
of Site Condition (RSC) Regulation 153/04, that comes into effect on 1 July
2011. This new regulation could
seriously affect the remediation plan for 25 Esquimault Avenue if the City does
not advise the Ministry by 31 December 2010 of its intention to undertake the
remediation of the property based on the 2004 Regulation and associated
environmental criteria, and to have the remedial work and associated follow-up
monitoring completed, with the record of Site Condition submitted to the MOE by
31 December 2012, as provided for in the “grandfathering” provisions of the new
Regulation. If the City cannot meet the
31 December 2012 deadline, and is required to meet the criteria of the new
regulation, there will be significantly increased costs to undertake the
remedial work as well as substantial additional time required to submit and
have a RSC approved by the MOE.
Consequently, staff has revaluated the RFP
process approach previously recommended to implement this project.
Staff has now estimated that:
If the City uses an RFP process based on the
successful proponent designing and building the Community Building before the
existing building is demolished and the environmental contamination remediated,
it is estimated that the overall time frame to submit an RSC will be in the
range of 27 to 34 months from the start of the RFP process. This means that it is highly unlikely that an
RSC can be submitted before the 31 December 2012 deadline. This is likely to
cause uncertainty for the proponents with respect to both redevelopment timing
and costs and, therefore, potential significantly lower sales revenue to the
City.
In addition, staff has determined that
constructing a new Community Building in the
community’s preferred location, with vehicular access and servicing accommodated
via an internal roadway through the proposed new infill development on the 3.0
acres to the south, before the overall 25 Esquimault site is fully remediated
and serviced, will most likely create interim access problems for the new
facility and increased construction coordination problems and cost.
As a result, it is now proposed that the City
not proceed with an RFP process, but instead proceed immediately to have staff
initiate and manage the project components using the City’s normal procurement
processes for the building demolition, environmental remediation and new
building construction work. It is also
proposed that the community activities in the existing building be relocated to
a temporary location until the new Community Building is constructed and that
this new building be constructed concurrently with the demolition and
environmental remediation components of the project to minimize the impact of
temporary facilities on the community activities. Staff is currently investigating both public
and private sector opportunities for providing temporary accommodation for
community activities while the new building is being constructed. Staff will
ensure that the community representatives involved in the current program
activities are consulted before leasing a temporary facility.
In order for the City to proceed with the
construction of the new community building that meets the local community
requirements as set out in Document 2, within a budgetary framework of $1M, as
established by Council in April 2008, staff has reviewed recent community
projects. In this regard, it was determined that a facility similar to the
recently built 3,000 sq. ft. McKellar Park
facility (as shown in Document 3)
with some small interior and exterior modifications, would likely meet
the community’s requirements and fit well architecturally within the Nanaimo
park neighbourhood. Utilizing the same architects and basic building design and
specifications that were used for the
As a test fit, the building footprint for the
It is also proposed that staff initiate the
planning approvals process for the redevelopment of the 25 Esquimault site,
including a rezoning of the property to provide for “adult style bungalow
development” in November 2010 to ensure that the site can be sold as soon as
the RSC for the property is obtained in the summer/fall of 2012. Once the 25 Esquimault
site has been fully remediated, and the environmental monitoring completed, it
is proposed that the sales process for the 3.0 acre parcel be initiated. To
ensure that the development will be carried out strictly in accordance with the
City’s development requirements, it is proposed that the 3.0 acre parcel be
transferred to the Ottawa Community Lands Development Corporation once the
environmental remediation work is complete, subject to the specific provisions
of the transfer being approved by Council, and based on a further report.
Based on the above approach, staff estimate
that the project components can be undertaken based on a milestone schedule as
follows:
In
order to initiate the construction of the new
The process outlined in this report for the construction of the new community centre, demolition of existing building followed by the remediation and redevelopment of the property at 25 Esquimault Avenue will facilitate the remediation of the site and filing of a Record of Site Condition in accordance with Ontario Ministry of the Environment Regulation 153/04.
There are no rural implications resulting from the sale of the subject property.
Extensive consultation with the community was
undertaken in 2009 with Parks, Recreation and Culture staff
facilitating the working committee meetings that were held to develop the
criteria for the new community building. A presentation was made to the Qualicum - Graham
Park Community Association Annual General Meeting held on 22 October 2009 and
the more than 100 persons attending the meeting indicated unanimous support for
the Committee’s recommendations.
A further public meeting, chaired by
Councillor Chiarelli, was held on 5 August 2010 to provide information on the
implementation process being recommended in this report. Approximately 100 persons attended this
meeting and indicated unanimous support for the proposed process.
Individuals did express concerns about the traffic and parking impact of a new community building on Nanaimo Drive and also about ensuring the temporary facility for accommodating community activities would be sufficiently suitable so as to not require existing programs to be cancelled. Staff indicated that both these concerns would be addressed if the project implementation process is approved by Council on 25 August 2010.
HOUSING FIRST POLICY
The Official Plan policy directs that the City make land available for affordable housing and give priority for the sale or lease of surplus City-owned property for this purpose.
The Housing First Policy, approved by Council on 13 July 2005, establishes priority consideration to the Affordable Housing Division in the identification of potentially surplus City-owned property, to be used in achieving the City’s affordable housing program targets. The policy also requires that the Official Plan target of 25% affordable housing, be met on any City-owned property sold for residential development. Where viable, residential properties are disposed of without a condition requiring an affordable housing component, 25% of the proceeds from the sale are to be credited to a housing fund, to be used for the development of affordable housing elsewhere in the City.
While the proposed redevelopment of the 25 Esquimault property will be for “adult style bungalow” residential development, the sale of the property is being undertaken to reduce the City’s total net cost for this environmental remediation project to approximately $2.35M and, therefore, there will be no net revenue available from the sale of the lands to contribute to the housing fund.
Councillor
Chiarelli is aware of the recommendations of this report and, in this respect, held
a public meeting on 5 August 2010 to inform, and receive feedback from, local
residents on the proposed changes in the implementation of the project. At the
end of the meeting, the Councillor indicated his support for the report
recommendations and requested a show of hands which resulted in the approximately 100
persons who attended indicating unanimous support for the proposed changes.
CITY
STRATEGIC PLAN
The City originally purchased this property to facilitate, and reduce the long term costs associated with remediating of the fuel oil contamination on the 25 Esquimault property. As a result of implementing the recommendations of this report, the local community will also continue to benefit from the use of a community building that meets its activity needs and be assured of a residential development compatible with the neighbourhood.
LEGAL/RISK
MANAGEMENT IMPLICATIONS
There are no legal/risk management impediments
to implementing any of the Recommendations arising from this report.
As outlined in this report and set out in Document 2, funds in the amount of $3,805,000 were approved by Council on 23 April 2008 for the acquisition of the 25 Esquimault property, the demolition of the existing building, remediation of the environmental contamination, and temporary relocation of the community facilities. Funding in the amount of $1.28M remains in the capital project account to undertake the demolition of the existing building and the environmental remediation work at 25 Esquimault.
The recommendations of this report, to proceed with the construction of a new community building on Nanaimo Park, at a net cost of $1M, concurrently with the demolition of the existing building and remediation of the on-site contamination before the 3.0 acres of land designated for redevelopment at 25 Esquimault is sold, will require the establishment of a new Capital project account for this purpose and for the $1M cost of this project to be debt financed.
Document 4: Proposed Community Building Location
Subject to Committee and Council approval, staff will
implement the recommendations as outlined in the report.
DOCUMENT 1
PROPERTY
SKETCH
DOCUMENT 2
PROPOSED QUALICUM -
BLOCKING
PLAN AND ROOM DATA
DOCUMENT 4
PROPOSED COMMUNITY BUILDING LOCATION