Council Member Inquiry/Motion
Form Demande de renseignements
d’un membre du Conseil /Formulaire de motion |
||
From/Exp. : Councillor Doucet/ Conseiller Doucet |
Date : 8 September 2010/ le 8 septembre 2010 |
File/Dossier : 31-10 |
To/Dest. : Deputy
City Manager, Infrastructure Services and Community Sustainability/ Directrice
municipale adjointe, Services d'infrastructure et de la viabilité des
collectivités |
||
Subject/Objet : Environmental Assessment for the 3.4 kilometre tunnel Évaluation environnementale du projet
de tunnel de 3,4 kilomètres |
||
Inquiry/Demande de renseignements Motion Whereas the Provincial Environmental Assessment (EA) of the 3.4 kilometre tunnel is completed; Whereas this EA of the tunnel has not been made available to either city council or the public Whereas the tunnel EA contains important information that belongs in the public domain and is necessary for informed decisions regarding any future light rail plans for Ottawa; Inquiry: Why has the EA for the 3.4 kilometre tunnel not been made available to Councillors their consideration? **************************** Attendu que l’évaluation environnementale
provinciale du tunnel de 3,4 kilomètres est terminée; Attendu que cette évaluation environnementale
du tunnel n’a pas été rendue publique ni présentée au Conseil municipal; Attendu que cette évaluation environnementale
du tunnel contient de l'information essentielle relevant du domaine public et
nécessaire à la prise de décisions éclairées quant aux plans éventuels
relatifs au train léger sur rail à Ottawa; En conséquence, nous formulons la demande
suivante : Pour quelles raisons l’évaluation environnementale du tunnel
de 3,4 kilomètres n’a pas été présentée aux conseillers aux fins
d’examen? |
||
Response/Réponse
The DOTT Planning and
Environmental Assessment (EA) Study – Recommended Plan was presented to
Council on January 13, 2010. Council approved this report and directed staff
to initiate the formal expedited transit projects EA process and file the
Environmental Project Report (EPR) with the Ministry of the Environment. In accordance with this
direction staff submitted the EPR to the Ontario Ministry of the Environment
on June 11, 2010. On this date, the EPR was posted on the project website, www.ottawalightrail.ca for the
30-day public review period. Notice of the completion of the EPR was published
in the Ottawa Citizen and Le Droit, posted on ottawa.ca, and printed copies
were made available at 11 different locations, including four City Client
Service Centres, three branches of the Ottawa Public Library and the Central
Archives. Following this review period,
the EA was approved by the Ontario Minister of the Environment, without
conditions, and Council was informed of the Minister’s approval by e-mail sent
on August 17, 2010. The EPR remains available on Ottawa’s Light Rail
Transit (OLRT) project website: http://www.ottawalightrail.ca/en/project-plan/environmental-project-report. For any further clarification please contact John Jensen, Director, Rail Implementation at ext. 12764. |
****************************
L’Étude d’évaluation environnementale (ÉE) et
de planification du tunnel de transport en commun du centre-ville d’Ottawa –
Plan recommandé a été présentée au Conseil le 13 janvier 2010. Le Conseil a
approuvé ce rapport et a donné le mandat au personnel de la Ville de lancer le
processus accéléré officiel d’ÉE des projets de transport en commun et de
déposer un rapport de projet environnemental (RPE) au ministère de
l’Environnement.
Conformément à ces directives, nous avons remis
un RPE au ministère de l’Environnement de l’Ontario le 11 juin 2010. À cette
date, le RPE a été affiché dans le site Web du projet à www.ottawalightrail.ca
pour la période d’examen public de 30 jours.
L’avis d’achèvement du RPE a été publié dans l’Ottawa Citizen et Le
Droit, posté à ottawa.ca et on pouvait s’en procurer des exemplaires dans onze
endroits différents, y compris à quatre centres de services à la clientèle de
la Ville, à trois succursales de la bibliothèque publique d’Ottawa et aux
Archives centrales.
Suivant cette période d’examen, l’ÉE a été
approuvée sans condition par le ministère de l’Environnement de l’Ontario et le
Conseil a été informé de l’approbation du ministre par courriel le 17 août
2010.
On peut consulter le RPE sur le site
Web du projet de train léger sur rail d’Ottawa : http://www.ottawalightrail.ca/en/project-plan/environmental-project-report.
Pour tous renseignements additionnels, veuillez
vous adresser à John Jensen, directeur, mise en œuvre du TLR au poste 12764.