Report to / Rapport au:
Planning Committee
Comité de l’urbanisme
7 June 2011 / le 7
juin 2011
580-2424, Ext. / poste : 28136, Caitlin.Salter-MacDonald@ottawa.ca
Ref N°: ACS2011-CMR-PLC-0011 |
SUBJECT: |
QUARTERLY PERFORMANCE REPORT
TO COUNCIL, Q1: JANUARY 1 TO MARCH 31, 2011 |
OBJET : |
RAPPORT TRIMESTRIEL SUR LE RENDEMENT PRÉSENTÉ AU CONSEIL POUR LE 1ER
TRIMESTRE, DU 1ER JANVIER AU 31 MARS 2011 |
That the
Planning Committee receive this report for further review and discussion of the
service areas’ performance results, as outlined in Document 1.
Que le
Comité de l’urbanisme reçoive le présent rapport aux fins d’un examen plus
approfondi et d’une discussion des résultats sur le rendement des secteurs de
service, tel qu’il est énoncé au Document 1.
At its meeting of 7 June 2011, the Finance and Economic Development Committee received a report from the Deputy City Manager, City Operations (ACS2011-COS-ODP-0010) and the following recommendations, as amended:
1. That the Finance
and Economic Development Committee receive the attached report and refer it for
review and discussion at the following standing committee meetings:
·
Planning
Committee – June 28, 2011
·
Transit Commission – June
15, 2011
·
Environment
Committee – June 16, 2011
·
Community
and Protective Services Committee – June 23, 2011
·
Transportation
Committee – June 29, 2011
2. That Council receive
the report for information on July 13, 2011 once it has been reviewed by
standing committees.
Accordingly, this report is before the Planning Committee for review and discussion.
No specific public consultations were undertaken in the production of the report. Notice of this meeting was posted on the City’s website as per Section 77(1)(b) of the Procedure By-law.
There
are no specific rural implications associated with this report.
LEGAL IMPLICATIONS
There are no legal impediments in receiving
this report.
RISK MANAGEMENT
IMPLICATIONS
There are no risk management implications associated
with this report.
There are no financial implications associated
with this report.
SUPPORTING DOCUMENTATION
Document 1: Report dated 31 May 2011 from the Deputy City Manager, City Operations (ACS2011-COS-ODP-0010) - English and French versions
Document 2: Quarterly Performance Report to Council Q1: January - March 2011 (Issued separately and held on file. English and French versions)
Staff in the City Clerk’s Office will submit a report to Council within the timeframe prescribed in the recommendations of the original report from the Deputy City Manager, City Operations.
DOCUMENT 1
Report to/Rapport au:
Finance and Economic Development Committee
Comité des finances et du développement économique
and Council / et au Conseil
Submitted by/Soumis par:
Steve Kanellakos, Deputy City
Manager/Directeur municipal adjoint,
City Operations/Opérations municipales
Contact Person/Personne-ressource :
Donna Gray, Director/directrice
Organizational Development and Performance/Service
du développement et du rendement organisationnels
613‑580‑2424,
ext./poste 25684
Ref N°: ACS2011-COS-ODP-0010 |
SUBJECT: |
QUARTERLY
PERFORMANCE REPORT TO COUNCIL, q1: JANUARY 1 TO MARCH 31, 2011 |
OBJET : |
rapport TRIMESTRIEL SUR LE rendement présenté au conseil POUR LE 1Er TRIMESTRE,
du 1ER JANVIER AU 31 MARS 2011 |
1. That the Finance and Economic
Development Committee receive the attached report and refer it for review and discussion
at the following standing committee meetings:
·
Planning
Committee – June 14, 2011
·
Transit
Commission – June 15, 2011
·
Environment
Committee – June 16, 2011
·
Community
and Protective Services Committee – June 23, 2011
·
Transportation
Committee – June 29, 2011
2. That Council receive the report for information on July 13, 2011
once it has been reviewed by standing committees.
RecommandationS du rapport
1. Que le
Comité des finances et du développement
économique prenne connaissance du rapport ci-joint et le soumette pour examen et discussion aux prochaines
réunions des comités permanents :
·
Comité de l’urbanisme – le 14 juin 2011
·
Commission du transport en commun –
le 15 juin 2011
·
Comité de l’environnement – le 16
juin 2011
·
Comité des services communautaires
et de protection – le 23 juin 2011
·
Comité des transports – le 29 juin
2011
2. Que le Conseil prenne
connaissance du rapport le 13 juillet 2011, une fois qu’il aura été examiné par
les comités permanents.
DISCUSSION
The Quarterly Performance Report to Council is an important component of the City’s accountability framework. Accountability is fundamental to good governance.
This Quarterly Performance Report to Council Q1: January 1 to March 31, 2011 provides measures from a broad cross-section of service areas to the public. This report provides information on how the City is performing relative to its established standards, as well as information on changes in performance over time. The Quarterly Performance Report includes:
This Quarterly Performance Report to Council covers the reporting period between January 1 and March 31, 2011. It provides performance measures for services within the following service areas:
There
are no specific rural implications associated with this report.
No specific public consultations were undertaken in the production of the report.
LEGAL IMPLICATIONS
There are no legal impediments in receiving
this report.
RISK MANAGEMENT
IMPLICATIONS
There are no risk management implications
associated with this report.
There are no financial implications associated
with this report.
Document 1: Quarterly
Performance Report to Council Q1: January 1 – March 31, 2011 (issued separately
and held on file with the City Clerk)
The Quarterly Performance Report to Council will be made available to citizens electronically in PDF and HTML formats on our Web site (ottawa.ca), and in printed format upon request.
Rapport au / Report to:
Comité des finances et du développement économique
Finance and Economic Development Committee
et au Conseil / and Council
le 31 mai 2011
/ 31 May 2011
Soumis par / Submitted by:
Steve
Kanellakos, directeur municipal adjoint / Deputy City Manager,
Opérations municipales / City
Operations
Personne-ressource
/ Contact Person: Donna Gray, directrice / Director
Services du développement et du rendement organisationnels/
Organizational Development and Performance
613-580-2424, ext./poste 25684
OBJET : |
rapport TRIMESTRIEL SUR LE rendement présenté au conseil POUR LE 1E TRIMESTRE,
du 1ER JANVIER AU 31 MARS 2011 |
SUBJECT: |
QUARTERLY PERFORMANCE REPORT
TO COUNCIL, q1: january 1 TO march 31, 2011 |
RecommandationS du rapport
1. Que le Comité
des finances et du développement économique prenne connaissance du
rapport ci-joint et le soumette pour examen et discussion aux prochaines
réunions des comités permanents :
·
Comité de l’urbanisme – le 14 juin 2011
·
Commission du transport en commun –
le 15 juin 2011
·
Comité de l’environnement – le 16
juin 2011
·
Comité des services communautaires
et de protection – le 23 juin 2011
·
Comité des transports – le 29 juin
2011
2. Que le Conseil prenne
connaissance du rapport le 13 juillet 2011, une fois qu’il aura été examiné par
les comités permanents.
RePORT RECOMMENDATIONS
1. That the Finance and Economic
Development Committee receive the attached report and refer it for review and
discussion at the following standing committee meetings:
·
Planning
Committee – June 14, 2011
·
Transit
Commission – June 15, 2011
·
Environment
Committee – June 16, 2011
·
Community
and Protective Services Committee – June 23, 2011
·
Transportation
Committee – June 29, 2011
2. That Council receive the report for information on July 13, 2011
once it has been reviewed by standing committees.
DISCUSSION
Le Rapport trimestriel sur le rendement
présenté au Conseil est un élément important du cadre de responsabilisation de
la Ville. La responsabilisation est essentielle à une bonne gouvernance.
Ce rapport trimestriel sur le
rendement à l’intention du Conseil, qui porte sur le premier trimestre de
l’année, soit la période du 1er janvier au 31 mars 2011, renferme
des mesures concernant un large éventail de services au public. Le rapport
fournit des renseignements sur le rendement de la Ville par rapport à ses
normes établies de même que sur les changements que le rendement a connus au
fil des ans. Le rapport trimestriel sur le rendement comprend :
Le Rapport trimestriel sur le rendement
présenté au Conseil couvre la période visée du 1er janvier au
31 mars 2011. Il contient des
mesures du rendement pour les services offerts par les directions suivantes:
Aucune répercussion particulière sur les zones
rurales n’est associée à ce rapport.
Aucune consultation publique particulière n’a
été entreprise dans le cadre de ce rapport.
RÉPERCUSSONS SUR LE PLAN JURIDIQUE
Il n'y a pas d'entrave d'ordre juridique à
prendre connaissance de ce rapport.
RÉPERCUSSONS DE LA GESTION DES RISQUES
Aucune répercussion particulière de la gestion
des risques n’est associée à ce rapport.
Aucune répercussion financière n’est associée à
ce rapport.
Document 1 : Rapport trimestriel sur le rendement présenté
au Conseil pour le 1e trimestre : 1er janvier au 31
mars 2011 (distribué séparément et retenu en dossier)
Le public pourra consulter ce rapport
trimestriel sur le rendement présenté au Conseil en format PDF et HTML sur
notre site Web (ottawa.ca) ou en
format imprimé en en faisant la demande auprès de la Ville.