Report to / Rapport au :

 

Transit Committee

Comité du transport en commun

 

30 September 2009 / 30 septembre 2008

 

Submitted by / Soumis par: Nancy Schepers, Deputy City Manager/Directrice municipale adjointe,

Infrastructure Services and Community Sustainability/Services d’infrastructure et Viabilité des collectivités

 

Contact Person / Personne ressource : Vivi Chi, Manager/Gestionnaire, Transportation Planning/Planification des transports, Planning and Growth Management/Urbanisme et Gestion de la croissance

(613) 580-2424 x21877, vivi.chi@ottawa.ca

 

Rideau-Rockcliffe (13); Alta Vista (18)

Ref N°: ACS2009-ICS-PGM-0187

 

 

SUBJECT:

Multi-Use Pathway Connection – Coventry Road To Train Station:  Environmental Assessment Study

 

 

OBJET :

Sentier polyvalent – du chemin coventry à la station d’O-Train : Étude d’évaluation environnementale

 

 

REPORT RECOMMENDATION

 

That Transit Committee approve the Statement of Work for the Multi-Use Pathway Connection - Coventry Road to Train Station:  Environmental Assessment Study as detailed in Document 1.

 

RECOMMANDATION DU RAPPORT

 

Que le Comité du transport en commun avalise l’énoncé de travail en vue de l’évaluation environnementale du sentier polyvalent du chemin Coventry à la station d’O-Train, tel qu’expliqué en détail dans le document 1.

 

 

BACKGROUND

 

In December 1995, the former City of Ottawa approved The Coventry Road Plan of Development, which included a multi-use pathway connection over the Queensway between Coventry Road, at the baseball stadium, and the transit Train Station.  This link was deemed necessary to improve future access to rapid transit and to encourage transit-oriented development along Coventry Road. 

 

Since then, this multi-use pathway connection has been incorporated into the City’s Official Plan (OP) and Transportation Master Plan (TMP).  The OP, TMP and the City’s Strategic Plan encourage new infrastructure to improve access to transit through a number of mechanisms, including integrating the pedestrian network with transit facilities such as the transit Train Station.  

 

The TMP identifies this proposed connection as a required Phase 1 (2009–2015) multi-use pathway infrastructure project. 

 

Prior to initiating the consultant selection process, staff seeks approval from Committee on the scope of the work for the Environmental Assessment Study.  The study’s scope identifies the level of effort and helps to determine the budget to undertake the study.

 

DISCUSSION

 

The Statement of Work (SoW) is described in Document 1.  It outlines the tasks to be undertaken for the Multi-Use Pathway Connection - Coventry Road to Train Station: Environmental Assessment Study, including consultation, and upon approval from Transit Committee will form the basis for a call for proposals to the consulting industry.

 

This project involves developing a multi-use pathway to more directly and safely connect the Overbrook community to a rapid transit station.  Not only will the pathway improve access to an intermodal transit facility, but it will also improve access to the existing trail and cycling routes on City lands adjacent to the VIA Rail Station and the Coventry Road baseball stadium.

 

This project will be carried out as a Schedule ‘C’ Class EA as set out in the Municipal Engineers Association: “Municipal Class Environmental Assessment” document. 

 

Since there may be a requirement for Federal land, permits and funding, the project must also comply with the requirements of the Canadian Environmental Assessment Act (CEAA).  This project must satisfy both Provincial and Federal act requirements through a co-ordinated process to avoid duplication of effort.

 

The EA study area will primarily encompass lands within an 800-metre radius of the transit Train Station.  However, some study tasks will require examination of a broader area, beyond these limits in order to address environmental impacts and operational issues; to co-ordinate with relevant completed or on-going studies and projects (Ottawa Cycling Plan, Ottawa Pedestrian Plan, Downtown Ottawa Transit Tunnel EA, etc.) and to study and identify tie-ins to future network connections including drainage and environmental influences.

 

Key considerations for the study include the following:

 

q  Potential pathway grade separations

q  Links to pathways, multi-use trail system, transit and rail facilities

q  Pedestrian, cyclist and vehicular safety and security issues, including lighting

q  Geotechnical, grading and drainage, and municipal infrastructure

q  Effects on adjacent land uses

q  Consultation with the community and agencies

 

Study Timing

 

It is expected that it will take approximately 12 months after contract award to complete this study.  This timeline is consistent with industry practice for projects of this scope and reflects the City’s experience.

 

 

ENVIRONMENTAL IMPLICATIONS

 

The study will examine and evaluate the project’s effects on social, physical and natural environments within the study area.  Appropriate mitigation measures will be developed and post mitigation environmental impacts will also be determined.

 

 

CITY STRATEGIC DIRECTIONS

 

The recommendations contained herein directly supports the following Strategic Plan adopted by Council on 11 July 2007:

 

B3       Attain transit goals (30 per cent modal split) by 2021.

E9        Require walking, transit and cycling oriented communities and employment centres.

F4        Ensure that City infrastructure required for new growth is built or improved as needed to serve the growth.

 

 

CONSULTATION

 

This study will involve stakeholders, including local community/interest groups, property owners, businesses, area schools and approval agencies.  Early in the study process, community stakeholders will be identified through liaison with the Ward Councillor.

 

Consultation with the general public will occur principally through public meetings, but also through the project web page, e-mail and additional meetings as required.

 

 

LEGAL/RISK MANAGEMENT IMPLICATIONS:

 

There are no legal/risk management impediments to implementing the recommendations in this report.

 

 

FINANCIAL IMPLICATIONS

 

Funds are available to undertake this EA Study in Order No. 902973 - Smart Growth EAs.

 

 


SUPPORTING DOCUMENTATION

 

Document 1    Multi-Use Pathway Connection from Coventry Road to Train Station: Environmental Assessment Study – Statement of Work

 

 

DISPOSITION

 

Following Committee approval of the attached Statement of Work, staff from the Planning and Growth Management Department will commence the consultant selection process with the assistance of the Supply Management. 

 


MULTI-USE PATHWAY CONNECTION FROM COVENTRY ROAD

TO TRAIN STATION: ENVIRONMENTAL ASSESSMENT STUDY –

STATEMENT OF WORK                                                                                    DOCUMENT 1

 

 

INTRODUCTION

 

The City of Ottawa is the proponent of an Environmental Assessment (EA) to study a proposed multi-use pathway connection from Coventry Road, at the baseball stadium, to the transit Train Station.

 

This Statement of Work (SoW) describes the City’s intentions with respect to the methodology, public consultation and deliverables for this study.  The SoW outlines the tasks to be undertaken to complete the EA study, and upon approval from the City’s Transit Committee, will form the basis for a Request for Proposal (RFP).

 

BACKGROUND

 

The Overbrook Community is an established residential neighbourhood located inside the Greenbelt, bounded by the Rideau River, the former City of Vanier boundary, St. Laurent Boulevard and the Queensway.  The neighbourhood is comprised of a mix of dwelling unit types; served by schools, parks, commercial and office uses.  Access to the area is limited from the south via the Vanier Parkway and Belfast Road, both of which include challenging pedestrian environments that do not directly connect with rapid transit.  A paved multi-use pathway exists along the eastern shore of the Rideau River; however, it also does not provide convenient access to transit and is not maintained in the winter months. 

 

The Coventry Road Plan of Development was approved by former City of Ottawa Council in December 1995 and includes a pathway connection over the Queensway between the baseball stadium and the transit Train Station.  This link was deemed necessary to achieve the then targeted transit modal split for the area in the range of 20 to 25 per cent.

 

This proposed multi-use pathway is considered an important link from the community to the transit station and is encouraged through policies outlined in the Coventry Road Plan of Development, Official Plan (OP) and Transportation Master Plan (TMP).  The City’s Strategic Plan also requires an emphasis on walking, transit and cycling in communities and employment centres in developing and redeveloped areas of the City.

 

The TMP focuses on increasing the modal split to support transit and encourage new infrastructure to improve access to transit through a number of mechanisms, including integrating the pedestrian network with transit facilities such as the transit Train Station.   The TMP also specifically identifies this multi-use pathway connection between the Coventry Road baseball stadium and the transit Train Station as a required Phase 1 (2009–2015) multi-use pathway infrastructure project.

 

PLANNING CONTEXT

 

As the City is the proponent for this undertaking, this project is subject to the Ontario Environmental Assessment Act (OEAA).

 

Federal EA requirements must also be addressed due to a potential requirement for Federal lands, permits and funding. All relevant environmental inventories and analysis undertaken for this assignment will be of sufficient scope to satisfy both Federal and Provincial EA requirements.

 

PROJECT DESCRIPTION

 

The multi-use pathway connection involves the extension of the pedestrian and cycling network over provincial lands (Highway 417) to connect the Overbrook community with the transit Train Station and other developments to the south, as shown in Figure 1.  

 

FIGURE 1- General Study Area

 

MAJOR ISSUES TO BE ADDRESSED

 

This study will determine how best to design and integrate the preferred alignment and profile for the multi-use pathway, including:

 

q       Compliance with Transitway Design Guidelines and future LRT Requirements

q       Compliance with VIA design goals and strategies

q       Aesthetic considerations

q       Pathway location, access points and configurations

q       Effects on the adjacent residential community and commercial development

q      Integration with the existing pedestrian and cycling environment, including safety and access considerations

q       Effect on cycling

q       Access to adjacent land uses

q       Impact on underground and overhead utilities and services, both existing and proposed

 

In addition, safety, aesthetic value, functional and security issues and emergency response will be investigated and addressed throughout the course of the study.

 

PROJECT SCOPE, TASKS AND DELIVERABLES

 

1.0       General

 

This project will be consistent with the approach and requirements set out in the Environmental Assessment Act.  Since there may be a requirement for Federal land, permits and funding, the project must also comply with the requirements of the Canadian Environmental Assessment Act (CEAA).   This project must satisfy both Provincial and Federal act requirements through a coordinated process to avoid duplication of effort. 

 

1.1       Study Area

 

The EA study area shown in Figure 1 will encompass those lands that are within approximately 800 metres of the transit Train Station.   However, some study tasks will require examination of a broader area, beyond these limits in order to address environmental impacts and operational issues; to coordinate with relevant on-going studies and projects; and, to study and identify tie-ins to future network connections such as drainage and environmental influences. 

 

The study area could be modified accordingly to respond to new information and conditions as they emerge during the course of the study.

 

The study will establish the requirements of the connecting links for pedestrian and cycling access and identify any right-of-way requirements and easements for the crossing. 

 

1.2       Timing

 

The study is expected to be completed within approximately 12 months of consultant selection.

 

1.3       Coordination with Other Studies

 

The EA Study process will take into consideration any information including analysis and findings of previous and concurrent transportation, development and infrastructure projects (i.e. Downtown Ottawa Transit Tunnel EA) that could influence the direction and/or conclusions of the Study.  Relevant background material will also be collected and reviewed.  

 

2.0       Environmental Assessment Study Tasks

 

 The major study tasks are summarized as follows:

 

2.1       Project Need

 

This study will assess and evaluate the need to provide a pathway connection across the Queensway to the transit Train Station.  The key components of this stage include:

 

q      Identifying and assessing future travel demand including the benefits to transit ridership and access to the transit Train Station

q  Identifying current and projected transportation problems and opportunities within the study area

q       Consideration of the implications of any corridor specific needs and/or constraints on crossing roadways.

 

This analysis will be used to identify all reasonable alternatives to the undertaking.

 

2.2       Environmental Inventory/Existing Conditions

 

An inventory of the social, economic, physical and natural environments within the study area will be compiled.   The inventory will consider all available background material and where necessary, supplement this information through on-site surveys and/or detailed studies.  

 

In general, the inventory will identify and describe those aspects of the environment that could potentially affect, or be affected by, the undertaking.  Some of the specific aspects of the environment associated with this project include:

 

q       Effects on green spaces and natural areas

q       Adjacent communities including the Overbrook Community

q       Current and future cycling and recreational pathway corridors/routes

q       Potential influence of the project from/on development patterns in the area

q       Current storm water drainage patterns

q       Subsurface (geotechnical) conditions

q       Utilities including water, sanitary, hydro, gas, cable, phone, fibre optic

q       Heritage and archaeological conditions

 

The inventory must be completed for the entire study area so that as alternatives are developed and analyzed, the cumulative effects can be examined.   The complete inventory will be clearly described and documented within the final report.

 

2.3       Evaluation Criteria and Evaluation Process

 

A comprehensive list of evaluation criteria and methodology will be developed and used to evaluate the various alternative solutions and designs.   Refinements may be made to the evaluation process in order to accommodate changing conditions or circumstances as they arise.

 

2.4       Alternatives to the Undertaking

 

Developing and examining a full range of options complies with the EA Act requirement that all reasonable alternatives to the undertaking be assessed.   The alternatives will be analyzed and evaluated based upon various criteria and indicators to assess the impacts (with consideration to possible mitigation measures) on the environment and to recommend a preferred alternative solution. 

 

The key components of this stage include:

 

q      Identify alternative solutions to address transportation problems.  Examples include:

o        Do nothing

o        Restrict pedestrian and cycling access between the two land uses/areas

o       Provide a pathway link between the two land uses

o       Provide an alternative using existing/proposed pathway connections within the public   right-of-way

q      Develop evaluation criteria and indicators to assess the impacts (with consideration to possible mitigation measures) on the environment by the various alternatives

q     Analyse and evaluate the alternative options and select the preferred solution(s) that best meet the needs

 

Alternative options will be developed with input from the Consultation Groups and will be presented to the public for comments (see section on Public Consultation Plan).  

 

2.5       Selection of Design Alternatives

 

Provided the preferred solution involves provisions of new pathway infrastructure, the Consultant will identify and evaluate various design alternatives.  

 

The pathway alignment and cross-section design alternatives will be identified based on consideration of constraints within the study area, input from the public and approval agencies, landowners, as well as City guidelines/standards/practices.  All proposed designs will include any required modifications on crossing/connecting roadways, either public or private.

 

The alternative designs will be assessed and evaluated as to their affects on the natural, social, urban, economic and transportation environments.   To ensure that all of the impacts are identified, the necessary investigations such as: noise, air quality, vibration, heritage and archaeological, natural areas and wildlife habitats, storm water management, geotechnical, traffic impacts, accessibility and safety, urban and landscape design, property impacts and any other research that would be required to properly define the effects of the facility will be carried out.

 

The alternatives will be compared to each other with the ultimate goal of determining a recommended design.   This exercise will be carried out with input from the study Consultation Groups.   Following the evaluation of alternatives and determining all necessary mitigation measures to minimize any adverse impacts, a technically preferred design will be prepared and the results will be presented at a final Public Meeting.

 

2.6       Recommended Plan

 

Upon receipt and incorporation of public feedback, the recommended design will then be developed to a sufficient level of detail as required to produce a functional design plan that is adequate for submissions for project approvals in principle and to establish a complete scope of work, baseline budget and implementation schedules for the entire project.   The recommended plan will incorporate the functional design plan and will include but may not necessarily be limited to:

 

q       A written description of the undertaking including the design parameters.

q      Functional design drawings (plan and profile) for the preferred alignment with a coordinated centerline and property envelope, structural general arrangement drawings

q      Cross-section drawings for typical sections as well as critical areas (e.g. Airport Parkway connections, etc.);

q       Implementation (phasing) plan

q       Recommended mitigation measures to reduce the environmental impacts of the project

q       Storm water management requirements

q      Cost estimate of the proposed works (prepared in the WBS format with scope statements for each element) for budgeting/funding purposes

 

The Recommended Plan will clearly identify and set out the requirements and timing for all subsequent approvals required to proceed with the construction phase of the project.

 

2.7       Environmental Assessment Report

 

The study findings and recommended design with mitigation plans will be presented to the Transit Committee for approval. A Draft and Final Environmental Study Report (ESR) will be prepared to document the entire study process including the recommended design and any appropriate mitigation plans, amending procedure, costing, and implementation and Staging Plan, and commitments to future action, including external approvals known to be required.

 

The final ESR, incorporating all pertinent comments, will be prepared and placed on public record for a minimum 30-day review period.  The Consultant will be available to address any issues as they arise during this review period.  Reference copies of the report will be made available at local libraries, City Hall, City Client Service Centres and the MOE Regional and/or District office.

 

2.8       Federal EA Project Description Report

 

Federal permits, property and funding may be sought before project implementation can proceed.  In order to expedite the future federal approval processes, early discussions will take place with the relevant federal Responsible Authorities (RAs) to identify all federal EA requirements and initiate the federal EA screening process. This will ensure that all relevant existing environmental inventory data collected and impact assessments carried out during this assignment are scoped sufficiently to address federal EA screening requirements.

 

A federal Project Description Report will be prepared, containing a written description and general arrangement drawings for the project in accordance with the requirements of the federal RAs. The report will include enough information on potential impacts, mitigation measures and conceptual compensation strategies to allow the federal agencies to conclude on the significance of environmental effects at this early planning stage.

 

3.0       Consultation

 

This study will involve a number of stakeholders, including community groups, property owners, businesses, institutions, approval agencies and special interest groups.  Early in the study process stakeholders will be identified. This will be accomplished through various forms of consultation, including liaison with City Councillors, community associations, approval agencies and public notification. 

 

The consultation program will primarily consist of meetings with stakeholders, individually and through Consultation Groups, and Public Meetings with the general public.  Consultation Groups will meet with the Study Team at key stages to review and comment on specific issues, the study progress and findings.  Two consultation groups will be established, namely:

 

q       Public Consultation Group (PCG)

q       Agency Consultation Group (ACG)

 

The membership, roles and responsibilities of each Consultation Group will be outlined and communicated to each prior to meetings taking place. 

 

Specific aspects of the consultation program are detailed as follows.

 


3.1       Public Consultation Group

 

A Public Consultation Group (PCG) will be formed to enable stakeholder groups to provide direct input to the study, advising and commenting on local issues and concerns.   PCG members may include representatives from local community groups, area business representatives, special interest groups, and adjacent property owners including representation from each of the following groups:

 

q       Community Council of Overbrook

q       Area businesses and employers (Hampton Inn, VIA, Canadian Tire, RCMP, etc)

q       Pedestrian and Public Transit Advisory Committee

q       Roads and Cycling Advisory Committee

q       Accessibility Advisory Committee

q       Environmental Advisory Committee

q       Other interested groups or persons identified during the development of the study design, or that come forward during the course of the study

 

3.2       Agency Consultation Group

 

An Agency Consultation Group (ACG) will be formed to address the full range of technical and policy issues and to comment on all of the special studies required to fully assess the various alternatives and to ensure that the City is following the procedures, legislation and addressing appropriate policies.   ACG members will include experts in their related fields from government agencies and approval bodies including, but not limited to:

 

q       Canadian Environmental Assessment Agency

q       Parks Canada

q       National Capital Commission

q       Transport Canada

q       Department of Fisheries and Oceans

q       Ontario Ministry of Transportation

q       Ontario Ministry of the Environment

q       Ontario Ministry of Natural Resources

q       City of Ottawa

·          Public Works Department

·          Infrastructure Services Department

·          Planning and Growth Management Department

·          Real Estate Partnership and Development Office

·          Emergency Protective Services Department (Ambulance, Fire)

·          Police Services

q      Other interested agencies identified during the development of the study design, or that come forward during the course of the study

 

3.3       Notifications

 

The public will be notified of: the Study commencement, all Public Meetings and the submission of the EAR for Ministry approval.  Notifications will be sent out at appropriate stages in the Study, and each announcement will take the following forms:

 

q       Advertisements in daily newspapers (The Ottawa Citizen, Le Droit)

q       Advertisements in community papers where appropriate

q       The project web site on the City’s web portal

 

3.4       Public Meetings

 

Public Meetings will be held to present and obtain feedback on existing conditions and alternatives to the undertaking, the preferred solution and alternative design concepts, and the recommended plan.

 

Background and presentation material will include a “Project Update Newsletter” which summarizes the information presented at the public meetings and will be available for general distribution.   Bilingual staff will be present during all public meetings and all material presented at the meetings as well as the “Project Update Newsletter” will be bilingual.  

 

3.5       Project Web Page

 

A Project Information Web Page for the Study will be established on the City’s external web site. The purpose of the Web Page will be to inform the public of the progress of the study and upcoming meetings or activities, post the bilingual materials presented at each Public Meeting, and provide a point of contact for e-mail correspondence. It is imperative that bilingual information for the Public Meeting be ready and posted on the day of each event. 

 

3.6       Deliverables

 

The deliverables for the study include:

 

q      Public Meetings Summary Reports – one for each public meeting

q      Project Web Page data – as required

q      Project Update Newsletter – one for each public meeting

q      Draft and Final Environmental Assessment Reports (EAR)

q      Functional design drawings of the preferred design, including plans and profiles for recommended alignments, proposed station layouts and elevation drawings, structural general arrangement drawings, utility relocation details, storm water management plans, landscape design plans, and property requirement plans

q      Project Implementation/Staging Plan, which will identify all future approval requirements including those for property acquisitions and easements and other property related matters

q       Project capital and maintenance costs in WBS format

q       Approvals in principal as required by regulatory agencies