M E M O   /   N O T E   D E   S E R V I C E

 

 


 

To / Destinataire

Chair and Members of Transportation Committee/Président et members du Comité des transports

File/N° de fichier: 

ACS2006-PWS-TRN-0001-IPD

From / Expéditeur

Acting Deputy City Manager/Directeur municipal adjoint intérimaire,

Public Works and Services/Services et Travaux publics

Contact / personne-ressource :

H. Gault   842-3636 ext. 2435

Helen.Gault@ottawa.ca

 

Subject / Objet

Impact of December 16, 2005 Snow Fall Event on Transit Services / Impact de l'incident de la chute de neige du 16 décembre 2005 sur les services de transport en commun

Date:     2030 January 2006/

             le 230 janvier 2006

 


 

BACKGROUND

 

On Friday, December 16, 2005, a snowstorm struck Ottawa with an intense level of precipitation just at the start and through the morning rush hour.  Bus operationsservice, particularly on the Transitway, were was severely affected, resulting in and many transit customers experiencinged very long delays getting to their destination.

 

Staff from Surface Operations, Traffic Operations, Fleet Services, Transit Services and Real Property and Asset Management have reviewed what happened to determine how the negative impact of the storm could have been reduced.

 

The purpose of this memorandum is to describe the impact this storm had on City services and identify ways to improve the response to future storms to reduce the negative impact on transit.  Adocument the verbal presentation was made to Transportation Committee on January 18, 200618 January 2006.   and iInformation that was requested at that meeting has been incorporated into this memorandum.

 

 

DISCUSSION

 

The Weather on Friday, December 16, 2005

 

On Friday, December 16, 2005, the City of Ottawa experienced a very heavysignificant snowstorm that resulted in an accumulation of 24 centimetres of snow being deposited over a twelve-hour duration, approximately 11 p.m. through 11:00  a.m.  While a storm of this magnitude is in itself sufficient to cause some disruption, there were aspects of this particular occurrence which were highly unusual. 

 

Environment Canada has advised that at 5:00 a.m. on December 16, there were four centimetres of snow down which fell had fallen at a rate of less than one centimetre per hour.  However, between 5:00 a.m. and 7:00 a.m. another 10 centimetres fell at a rate of five 5 centimetres per hour.  The remaining 10 centimetres fell over the next four hours at a rate of approximately 2.5 centimetres per hour.

 

The weather forecast was for heavy snowfall rates in the 2.5 to 3 centimetres per hour range.  However, for a two hour period at the start of the morning rush hour the snowfall rate that was received was five centimetres per hour or extremely heavy: double what is considered a heavy snowfall rate and double that which was forecast even that very morning.

 

Past experience in managing winter storms and discussions with Environment Canada staff have defined a snowfall rate of 2 to 2.5 centimetres per hour as being considered a heavy snowfall rate so to have 10 centimetres fall within two hours is very unusual.  The last severe storm in Ottawa previous to the December 16 storm was in December 2004, when 20 centimetres of snow fell over a period of 24 hours.

 

Vehicular Traffic

 

Traffic volumes are typically lower on a Friday and due to the advance notice of the approachingforecasted snow storm, some motorists may have adjusted their travel times to miss the peak hour.  During the snow storm, traffic conditions were quite variable.  At many major intersections, traffic was waiting numerous traffic signal cycles to clear the intersection, while at some.  On major corridors running parallel to the Queensway, such as Baseline and Carling, traffic was particularly heavy and further traffic signal timing changes were made in response to this.  At some major intersections, for example, (Hunt Club westbound at Woodroffe/Merivale), the queues were often clearing on the cycle of arrival..

 

Traffic Signal Control Systems

 

The computerized traffic signal system controls and monitors 866 of 1004 signalized intersections in the City of Ottawa.  As well, 62 traffic cameras located throughout the City bring back live video to the Traffic Control Centre.  This allows traffic system operators to monitor live traffic conditions and make traffic signal timing adjustments as needed to improve traffic flow and minimize delays.

 

On days when snow conditions are expected, the signal timing schedule is changed for the majority of traffic signals on the traffic signal control system.  This may include longer greens or left-turn arrows for critical traffic movements, as well as expanding the duration that peak hour timing is in effect.  Peak hour timing is implemented earlier in the day and is maintained beyond a typical end of rush hour.  At over 300 locations with newer traffic control hardware/software and detectors, the “gap time” that is typically used to decide when to best terminate a green signal is increased in response to the slower speeds experienced by vehicles approaching the intersection.  This will causes the signal to stay green longer than normal.  For example, on major corridors running parallel to the Queensway, such as Baseline and Carling, traffic was particularly heavy and traffic signal timing changes were made in response to this.

 

Surface Operations Storm Response

 

A snow storm of this magnitude and duration is bound to be a challenge for Surface Operations resource capacity to respond while maintaining the service windows contained within the Council-a Approved Winter Maintenance Quality Standards:, wherein   the Transitway and highway networks are being the highest priority, followed by the arterials and then the collector network.  In conjunction with adjustments to signal timing, our Winter Maintenance Standards have historically proven to be effective in keeping traffic moving safely on the city’s road network.  Although routinely aided by Traffic Operations in the form of adjusted green-light timing on a typical snow day, aside from the delays to the motoring public and transit users would expect, these Winter Maintenance Standards have historically proven effective in keeping traffic moving on the city’s arterial network in a safe manner. 

 

In the case of the December 16 storm, with the snow forecast to be heavy in and around the morning rush hour, at the first sign of snow, staff began salting the Transitway and the arterial roadways.  The Transitway and the arterial network had been completely salted once by 4:00 a.m.  Because of the heavy snowfall rate forecast, staff was instructed to utilize the heaviest salt rate available as the rush hour traffic would compromise their ability to completely treat arterials a second time in a timely manner.  At 4:00 a.m., a second salting operation was initiated immediately behind the roadway ploughs.  On the Transitway and arterial streets, roadway ploughs are deployed when a snowfall occurs at such a rate that the action of road salt does not allow vehicle tires to readily penetrate the slushy snow to obtain traction.  The Urban Core Roads Division directed maximum resources as per procedure for a storm of this magnitude, calling in 90 hired and city-owned graders to perform continuous ploughing in tandem with the city’s 42 salt trucks.  Arterials outside the Urban Core area were being serviced before the morning rush hour by another 81 combination salter/plough units.  However, tThe intensity of the storm caused traffic bottlenecks in the arterial road network during the morning rush hour, impairing our ability to continue to clear major corridors of fresh snow..  The major delays to transit services can be attributed to the roadway inclines located at eastbound Booth and the Transitway, Slater Street at Bronson, and westbound on the Transitway at the Bayview Station.  Buses first started to become stuck eastbound at the intersection of Slater at Bronson with the first bus operator calling at 6:15 a.m. requesting assistance on the Slater hill.  Given the lower bus and traffic volumes at this time of the morning, significant delays or back-ups were not experienced.  As the heavy snowfall continued, buses became stuck on the more moderate grades in the areas of LeBreton Station and Booth Street and on Slater approaching Bronson.  With 450 buses scheduled to operate approximately every 20 seconds through this key section of the Transitway during the peak period, beginning at approximately 7 a.m., the combination of stuck buses and very slow operations resulted in a queue of buses that extended from LeBreton Station to west of Tunney’s Station.  This created customer delays of more than 60 minutes.  Bus traffic gradually began moving as buses were freed from locations that blocked through traffic.  Westbound Transitway service in the same area was subjected to delays and stop-and-go operation due to stuck buses in Bayview Station blocking the roadway.

 

With the snow forecast to be heavy in and around the morning rush hour, at the first sign of snow staff began salting the Transitway and the arterial roadways.  The Transitway and the arterial network had been completely salted once by 4:00 a.m.  Because of the heavy snowfall rate forecast, staff was instructed to utilize the heaviest salt rate available as the rush hour traffic would compromise their ability to completely treat arterials a second time in a timely manner.  At 4:00 a.m., a second salting operation was initiated immediately behind the roadway ploughs.  On the Transitway and arterial streets, roadway ploughs are deployed when a snowfall occurs at such a rate that the action of road salt does not allow vehicle tires to readily penetrate the slushy snow to obtain traction.  The Urban Core Roads Division calls in 90 hired and city-owned graders to perform continuous ploughing in tandem with the city’s 42 salt trucks.  Arterials outside the Urban Core area were being serviced before the morning rush hour by another 81 combination salter/plough units. 

 

Despite these efforts, and as could be seen on several traffic cameras located in the areas of the localized congestion, there were problems experienced by jack-knifed articulated buses and other buses stuck in the snow that resulted in roadways and major intersections being blocked for various periods of time.

 

A side effect of ploughing the roads clear of snow is the ploughed snow being deposited adjacent to the curb.  Although the travelled lane is now clear, the access to buses from the bus stops is now blocked.  While trying to get closer to the curb as a convenience to the transit users, buses would end up straddling the windrow, which, in the case of this particular storm, was significant.  As a result of this practice buses would become hung-up on the snow bank.

 

Unfortunately clearing bus stops during or even immediately after a storm cannot currently be accommodated as all available resources (city and hired/contract) are still clearing snow from the transportation network (roads and sidewalks) in order of their importance as per the Winter Maintenance Quality Standards.  Currently the service windows for salting and ploughing the Transitway is 2 hours followed by arterials which is 3 hours and major collectors which is 4 hours.  Similarly, the service window for ploughing snow from sidewalks is 4 hours for the downtown business district and 12 hours for all other sidewalks including bus routes and urban/residentials (although staff have prioritised sidewalks abutting bus routes and service them within the first 4 hours of this 12 hour service window).  . At the cessation of the storm staff have 10 and 12 hours respectively to plough the snow from all residential roads and sidewalks.  Then, as per the Winter Maintenance Quality Standards, staff clear snow from bus stops during the next 12 hours which translates into the fact that all bus stops are to be cleared 24 hours after the cessation of the storm. 

 

During this storm a routine survey from field staff indicate that these windows were met.

 

Bus Operations

 

The most significant delays to transit developed due to specific problems which, while major in themselves, also had the complication that they were interrelated.  Immediately west of the downtown area, buses became stuck on the Gatineau side of the Chaudière Bridge, causing northbound back up of traffic on Booth Street all the way to Scott Street and beyond.  This traffic caused frequent blockages of the Transitway/Booth intersection.  As well, eastbound buses became stuck at the incline at Slater/Bronson, which also caused a back-up on the Transitway through the Booth Street intersection and further west.  Finally, the problems at this intersection were further exacerbated by a single articulated bus which had problems at the Booth/Transitway intersection itself.  With 450 buses scheduled to utilize this section of the Transitway during the morning peak, serious congestion developed quickly. It is also acknowledged that there were many other specific locations, generally involving inclines, which transit vehicles were unable to navigate. Bus traffic gradually began moving as buses were freed from locations that blocked through traffic.  Westbound Transitway service in the same area was subjected to delays and stop-and-go operation due to stuck buses in Bayview Station blocking the roadway.

 

In terms of passenger loading/unloading, difficulties were also experienced as a result of the large  windrows left by the ploughing operations.  Although the travelled lanes were cleared, the access to buses from the bus stops and sidewalks was seriously restricted.  Unfortunately, clearing bus stops during or even immediately after a major storm cannot currently be accommodated as all available resources (city and hired/contract) are still clearing snow from the transportation network (roads and sidewalks) as per the Winter Maintenance Quality Standards.

 

On a typical weekday, Transit Operations provides service to 350,000 daily riders using a peak period demand of 765 buses.  Throughout the day, the transit fleet undertakesis assigned to approximately 1200 daily bus assignmentspull-outs.  A review of the transit operations for the weather event of December 16 indicates bus operators called the Transit Operations Control Centre 107 times to report that their bus was stuck and that they needed assistance.  Typically for a significant snow event, Transit Operations would experience 10-12 requests for assistance from operators with stuck buses

.

The most severe congestion experienced by transit occurred in the Booth St/Transitway corridors.  Here roadways or intersections were blocked for extended periods of time (Transitway at Booth St. and Booth St. at north end of Chaudière Bridge) either by articulated buses or northbound traffic.  The blockage at the north end of the Chaudière Bridge caused Booth St. northbound to backup through the Transitway intersection so when the traffic signal turned green for the Transitway it was blocked by northbound traffic.  This severely congested the bus operations along the eastbound Transitway.  Eastbound bus queues did not clear until approximately 10:30 a.m.

 

As previously noted, there were specific bottlenecks which severely affected transit operations.  As well, The Transitway snow clearing activities could not immediately address some  left several critical areas, resulting unploughed resulting in numerous stuck buses.  The main areas of concern were the bus loops and roadways leading to the local platform areas at Blair and Billings Bridge.  Similar problems were encountered at the bus loops and lay-up areas at LeBreton, Hurdman and Orléans stations.  These are important in that buses finishing their routes must be able to turn around and wait to start their next run or to enter from or exit to local service at these locations.  The bus-only off and on ramps east and west bound along the 174 at Montreal Road and Jeanne d’Arc interchanges were also not cleared of snow in a timely fashionimmediately.

 

Considerable effort to free stuck buses was made by staff in many areas.  Staff in Transit Operations worked with Fleet, RPAM, Surface Operations and towing contractors to free stuck buses.  This involved tow trucks, service trucks, ploughs and sidewalk cleanersclearing equipment.  As well, Surface Operations were contacted to direct ploughing and salting operations to areas with specific problems.Transit Control did not call Ottawa Police Services during the morning. Although there are close communications with OPS for accident and incident response, the stuck buses did not fall into this category.

 

Surface Operations were contacted to direct ploughing and salting operations to areas with specific problems such as Slater at Bronson and various Transitway Stations - LeBreton, Bayview, Blair and Place d’Orléans.

 

In response to the roadway conditions and blockages, Transit Operations did re-route some cases, Transit service was detoured buses away from problematic areas, although this was of limited success as buses became stuck on the detour routes or were delayed in traffic congestion.  Services were detoured in several locations, including: to avoid poor road conditions and other stuck buses.  These include:

·        Bayshore Station eastbound service in station detoured to westbound lanes;

·        Data Centre Road to Billing Bridge Station service detoured to Riverside and Bank ;

·        Brittany Drive service detoured to Montreal Road and St. Laurent;

·        Blair Station lower level service detoured to Shopping Centre Road;

·        Place d’Orléans Station service detoured to Ring Road;

·        Queensway Station upper level eastbound service detoured to stay on Highway 417.

 

An example of the challenges encountered is provided.  In an attempt to ease congestion on the Transitway in the LeBreton Station area, eastbound buses were detoured through the lay-up area between Bayview and LeBreton Station.  This detour was abandoned as buses became stuck and blocked the lay-up area forcing buses to remain on the Transitway.

 

In addition to the amount and rate of snowfall, the following factors have been evaluated to determine their impact on the number of buses stuck on December 16.

 

Location

 

An analysis of the location of the stuck buses shows that Transitway roadways observed the largest percent of buses stuck at 45 percent. Rideau Street and Gatineau each had seven percent of the stuck buses.  Other roadways throughout the City of Ottawa accounted for the remainder.

 

 

Location

Number of Stuck Buses

Percent

Transitway

48

45

Rideau Street

7

6.5

Gatineau

7

6.5

Other

45

42

Total

107

100

 

 

 

A closer analysis shows that the areas most susceptible to stuck buses are as follows:

 

 

 

 

 

 

 

It is recognized that the statistics do not give an indication within themselves of the specific impacts to overall operations caused by individual blockages.  An example is the serious back ups caused by a few buses stuck immediately north of the Chaudiere Bridge.

 

 

 

 

 

 

 

 

 

 

 

Type of Bus Stuck

 

Over 80 percent of the stuck buses were sixty foot articulated buses.  This compares to an on-street fleet of articulated buses on December 16 of 22 percent.  It is clear that these buses were more susceptible to becoming stuck in the large amount of snow experienced on December 16 than other bus types.

 

Type                                                                                                                                                       

No. Buses Stuck

% Stuck

No. of  Pull-outs

% of  Pull-outs

40’ Low Floor  Orion VI

3

3

148

13

40’ Low Floor      New Flyer Invero

11

10

131

11

60’ Low Floor      New Flyer  D60LF

88

82

260

22

Other

5

5

628

54

Total

107

100

1167

100


 

Operator Driving Experience

 

An evaluation of the driving experience of the bus operators indicates that 37 percent of the bus operators stuck on December 16 had less than five years of bus-driving experience.  This is consistent with the percentage of operators driving buses on December 16.

 

Years Driving

No. of Opts  Stuck

% of Stuck

% of Opts on duty on Dec. 16

<5.00

40

37

37

5.00  to 9.9910

20

19

15

10.00 to 15 - 14.99

8

7

5

15.00 - 19.99 to 20

8

7

11

20.00 - 24.99 to 25

14

13

9

25.00 - 29.99 to 30

12

11

12

>30.00

5

5

11

Total

107

100

100

 

Further analysis of the operators that became stuck indicates that 13 were stuck twice during their shift and one operator became stuck three times.  A review of the driving experience for these operators shows that there is no pattern and that the most senior operator that was stuck more than once had thirty years experience and the most junior had less than one year experience.  Of the 14 operators stuck more than once, 12 were driving articulated buses.

 

It can therefore be concluded that years of driving experience was not a significant factor in this event.

 

Bus Recovery - Towing Operations

 

The City owns two large tow trucks, one stationed at 1500 St. Laurent in the east and the other at the Merivale Garage on Colonnade Road in the west.  A towing contract is also in place with J & E Towing that provides recovery services for the City’s entire fleet of vehicles.  Three of their trucks have been specially set up to recover buses.  As part of this Standing Offer, two other towing companies are available to the City once our efforts have been exhausted with the prime contractor

 

The process for dispatching either City owned or contracted units is that Transit Services control room staff contact the Fleet Services supervisor who provided the service using either the internal resources or contracted resources. However there had been no pre-positioning or early alerting of resources in anticipation of the eventstorm.

 

During the eventOn December 16, towing operations started before 6:00 a.m. and during the day, contractors recovered 31 vehicles, city-towing vehicles recovered 49 and about 37 27 were able to recover themselves or received assistance from others.

 

There were three accidents involving buses reported on the day of the storm and 12 more units were identified after the fact as having received minor damage.  Six buses sustained such minor damage that they remained in service.  The total cost of accident repair incurred was about $20,500.  All buses were back in service by early January.

 
Articulated Bus Analysis

 

The OC Transpo articulated bus fleet consists of 227 sixty-foot New Flyer low-floor buses (D60LFs) that employ a “pusher” configuration, with a rear drive axle powered by a rear-mounted engine, with longitudinal stability of the vehicle maintained by an active hydraulic system located below floor level at the articulated joint.

 

This particular design was selected in 2000 for operation in Ottawa for a number of reasons.  The articulated bus provides increased passenger capacity while the flexible joint allows safe transit of City streets, in spite of their increased length.  Additionally, the pusher type of configuration generally allows longer length low-floor sections without steps, while also providing reduced risk of passenger discomfort due to trace exhaust fumes, high noise and vibration levels.  City transit maintenance facilities and equipment are also better suited to propulsion systems that feature rear mounted, upright vertical engines.

 

The articulated fleet has performed satisfactorily for five years, and although there have been isolated cases of unserviceable buses due to winter road conditions, there has been no widespread events comparable to the number of artics articulated buses immobilized by the December 16, 2005 snow conditions.  Pusher articulated buses also provide satisfactory service in other Canadian jurisdictions, including Mississauga and Edmonton.  As well, an evaluation undertaken in 2004 by the City of Montreal concluded that the model used in Ottawa (one of our buses participated in the evaluation) performed on a par with other articulated configurations in snow conditions. 

 

There are a number of features in the D60LF design to provide an operating envelope that is satisfactory for the range of environmental conditions that normally occur in the City:. 

 

1.      A shorter rear section with a pivot point behind the center axle to effectively limit the turning corridor and bend angle required.

2.      An articulated joint design consisting of a ring frame bearing assembly, which connects the front section to the rear and transmits the loading forces, with a hydraulically controlled geared section to provide dampening forces to stabilize the rear section both with the bus travelling on a straight roadway alignment and with the bus in a bend.

3.      A programmable electronic controller (on-board computer) to control the degree of damping that is required at the articulated joint, which is a function of the bend angle, direction of travel, speed and transmission selection, and is re-adjusted continuously.

4.      The actuation of operator warning indicators and control interlocks, if the bend angle exceeds specific limits; e.g. at 44° bend, before the physical stops are encountered at 54º, vehicle brakes and throttle interlocks apply and 100 percent dampening is actuated, if in reverse gear.

5.       A joint-override switch to release the damping and control interlocks for 20-second intervals, if at the maximum bend angle, which allows the bus to be straightened either by driving the bus if tire traction is sufficient, or by towing.

6.      Traction control, which reduced engine torque and uses the Anti-Lock Braking system to control a slipping tire, under accelerating or launch conditions.

7.      For deep mud or snow, an override traction control option to allow continuous rotation of the tires at high throttle.  This feature is intended for travelling short distances over soft surfaces like snow, mud or gravel, where wheel spin is required to provide enough drive traction to move the vehicle, and consequently was not effective in preventing immobilization of many of the articulated buses on December 16.

8.      Relatively heavily weighted rear and center axles to provide adequate traction with the buses empty, which is achieved primarily by the rear mounted engine and the 1,100 kg articulation system located near the center axle.

 

The environmental conditions of December 16 generated extreme road conditions resulting in a significant accumulation of snow and ice on many City roadways.  A vehicle’s ability to brake, steer and accelerate is dependent on the tractive force generated at the tire, an ability which is seriously restricted by snow and ice accumulation., which is directly proportional to the friction f

actor (or the effective coefficient of friction) between the road surface and tire, and the normal tire loading (vertical weight).  Average friction factors of from 0.1 to 0.3 are reported for ice and snow conditions, as compared to 0.6 to 0.8 for dry pavement, which translates to a loss of traction under snow and ice conditions ranging from 50 percent to 90 percent.

 

From a transit perspective, the impact of the  December 16 event storm is best described as a widespread loss-of-traction event, as it significantly affected most buses in the fleet.  Non-articulated 40-foot buses became stuck in the snow, as well as a significant number of articulated buses, at various bend angles, including those that were longitudinally aligned and yet were still unable to generate sufficient traction at the rear tires to launch move the vehicle. 

 

Intuitively, a pusher articulated bus will have an operational traction limit in a turn that is less than a non-articulated vehicle, under heavy snow-load road conditions, as indicated by the high number of articulated buses adversely affected by the December 16 event.  Increased rolling resistance at the front and centre axles, as well as any resistive snow loading accumulation under the bus, will tend to decrease forward momentum of the bus, as tractive forces at the rear drive wheels generate an increasing pusher force – having a lateral component -- - at the centre axle tires, as the bend angle increases.  If this the lateral pusher forces and the normal centrifugal (or cornering) force exceed the resistive traction of the centre axle tires, the centre tires of the bus will skid laterally across the road surface.  Eventually, the added resistance of the bus being pushed sideways will overcome the tractive force generated by the drive axle and the bus will become immobilized.  As well, under all conditions, the additional tires resulting from the use of a centre axle on an articulated bus adds significantly to the rolling resistance, as compared to a 40-foot bus, which has to be overcome by the rear axle tractive forces.

 

Tires

 

All-season tires are currently used on the City transit fleet.  These tires range from new to retreads and incorporate both square and rounded treads.  A measurement survey of the remaining tire tread on the articulated buses that were immobilized during theon December 16 event showed that tread remaining in all cases was well within specified ranges.

from 5 mm to 8 mm remaining on the rear drive axle tires, from 5 to 12 mm on the centre axle tires, and from 8 to 19 mm on the steering front axle tires.  By comparison, the Fleet administrative minimum is 3 mm for all tires, whereas the legal limit is 1.6 mm, except for the steering axle tires, which has a 3 mm limit. 

 

A survey of transit tire suppliers (Bridgestone/Firestone, MichelonMichelin, and Good year) as well as a survey of other Canadian transit operators (Hamilton, Mississauga, Kingston, Gatineau, Montreal, and Quebec City) confirmed has revealed that snow tires are not available for and not used by the transit industry vehicles in Canada.  There are all- season tires with different traction characteristics from those used in Ottawa that may provide improved adherence grip under some winter conditions.  There is no commonly used pattern or brand used throughout the industry.

 

A marginal improvement in drive traction under heavy snow conditions may be attainable through use of tires from a different manufacturer, although there also may be trade-offs under other winter conditions such as icewould likely be attainable through the use of traction tires on the rear axle of the articulated fleet.  However, traction tires would not necessarily provide improved adhesion under other winter conditions, such as on ice.  For buses negotiating a turn, it may also be necessary to improve the lateral resistive traction generated by the centre axle tires This may necessitate the use of tires with a different tread design at the centre axle..  However, it is very unlikely that the marginalany  improvement in adherance adhesion provided by the use of traction tires would have made a significant difference given the extreme road conditions that existed on December 16, a conclusion that is consistent with results from winter snow tire testing completed by other transit organizations..

 

 

SUMMARY

 

Review of Major Problems – Lessons Learned and Actions Taken

 

Surface Operations

 

At one critical intersection (Booth and the Transitway) where the roadway incline created a significant problem for articulated buses, equipment was redeployed to spread winter grit in addition to the salt applications. the supervisor for the area redeployed a salt truck to spread winter grit.    This remedial action appeared to give the articulated bus enough traction to navigate the incline successfully without aid.  As a result, should conditions warrant it, all three,  inclines previously identified in the first paragraph as trouble spots for articulated transit buses have subsequently and will continue towill receive de-icing via the regular salt spreader attending that salt beat as well as an additional applications of winter grit to facilitate short-term traction.

 

 

As a second measure, a basic communications protocol has been formalized such that bus operators and transit supervisors can communicate immediate problems to Surface Operations staff through the Call Centre.  Furthermore, Transit Services and Surface Operations will meet in the fall to review winter operations procedures and salt beat maps will be shared.

 

Operations procedures have also been enhanced as follows:

 

i)        Bus loop area clearing procedures have been reviewed and modifications have been implemented to improve the operations;

ii)       Bus lanes on Montreal Road and Jeanne d’Arc will be prioritized and will be done at the same time as Highway 174;

iii)     Orléans Station will be completed at the same time as Highway 174.     


 

Bus Operations

 

On the day of the event, Transit Operations originally contacted Surface Operations through the City Call Centre.  Direct communications to the various yards responsible for the snow clearance operations took place after the mid-point of the event.  Since this time, direct lines of communications between Transit Operations Control and Surface Operations have been established. .  The Transit Control Centre did not call Ottawa Police Services during the morning.  Although there is close communications with OPS for accident and incident response, the stuck buses did not fall into this category.  This issue will be reviewed to consider how the involvement of the OPS could have assisted with the response to the problems experienced by the transit service during the storm.

 

For weekday rush-hour service about 180 articulated buses are scheduled and these are required for their passenger carrying capacity.  However, at off-peak times, when heavy snowstorms are predicted, it is possible to use standard, instead of articulated, buses on some runs. Off-peak trips tend to be more discretionary and the number of people using transit in a snowstorm on a Saturday or Sunday tends to be lower than would be the case in more clement conditions. Plans are being developed to alter the bus assignments to use more standard buses in these circumstances. Procedures are already in place to ensure that there are standard buses available as extras for heavy storm conditions.

 

The way in which the overall incident was managed from the point of view of any benefits that could have been provided by bringing in Ottawa Police Services will be reviewed an OPS representative will be included in the Task Force that has been set up.

 

Winter driving tips are communicated to bus operators prior to the start of each winter season. However, discussions with on-street supervisory staff assisting with stuck buses indicates that the traction control features of the articulated buses could be better understood by some operating staff.  These features as well as a reminder of procedures in winter storm conditions will be communicated to staff, particularly to those who were stuck more than once.

 

Fleet

 

There are preventative measures with respect to towing operations that can be taken to minimize the impact of future events of this nature through closer coordination of event anticipation with Surface Operations.

 

 

The feasibility of introducing program changes to further optimize the degree of hydraulic dampening generated at the articulated joint under heavy snow conditions is currently under investigation with the manufacturer of the articulation system. 

 

.Availability of higher traction tires is being pursued with a trial planned for the winter of 2006/2007 as directed by Transportation Committee.

 

Task Force

 

While the Department has implemented a number of measures to address issues experienced during the December 16 storm, it is acknowledged that the magnitude of disruption to the transit users on that day underscores that a careful review needs to be undertaken to ensure there is no reoccurrence.

 

Accordingly, aA Task Force has been formed to refine the improvements already implemented, to ensure optimal coordination and communications and to develop comprehensive plans/actions. for longer-term improvements that have been identified.  Membership will include:  Surface Operations, Fleet Services, Transit Services, Traffic and Parking Operations, Infrastructure Services, Real Property and Asset Management and Ottawa Police Services.

 

During its meeting of January 18, 2006, Transportation Committee directed that  theThe Task Force has been directed to report back to Transportation Committee inby June 2006.

 

 

Original signed by

 

 

R.G. Hewitt

 

 

Cc:  Mayor and Members of Council

       Executive Management Team

       Police Chief

       A/Director Surface Operations

       A/Director Transit Services

      A/Director Infrastructure Services

      Director Fleet Services

      Director Traffic and Parking Operations

      Director Real Property and Asset Management

      Coordinator Transportation Committee

       

 

 

S:\PDAdmin\Gault\Memo\Memo 2006-07\Transp Cttee - Impact of Dec 16 Snow Fall on Transit Services Jan 06.doc