Report to / Rapport au :

 

Transportation Committee

Comité des transports

 

01 November 2007 / 01 novembre 2007

 

Submitted by / Soumis par : Nancy Schepers, Deputy City Manager / Directrice municipale adjointe,

Planning, Transit and the Environment/ Urbanisme, Transport en commun et Environnement

 

Contact Person / Personne ressource : Vivi Chi, Manager / Gestionnaire, Transportation and Infrastructure Planning / Transports et planification des infrastructures

Planning Branch / Direction de l’urbanisme

(613) 580-2424 x21877, vivi.chi@ottawa.ca

 

Barrhaven (3), College (8), Knoxdale–Merivale (9), Rideau-Goulbourn (21), Kanata South (23)

Ref N°: ACS2007-PTE-POL-0066

 

 

SUBJECT:

Hope Side Road Extension (Richmond Road to West Hunt Club Road) Environmental Assessment – statement of work

 

 

OBJET :

évaluation environnementALE du prolongement du chemin hope side (du chemin Richmond au chemin WEST hunt club) – Énoncé des travaux

 

 

REPORT RECOMMENDATIONS

 

That Transportation Committee approve the Statement of Work for the Hope Side Road Extension (Richmond Road To West Hunt Club Road) Environmental Assessment as detailed in Document 1.

 

RECOMMANDATION DU RAPPORT

 

Que le Comité des transports approuve l’Énoncé des travaux lié à l’Évaluation environnementale du prolongement du chemin Hope Side (du chemin Richmond au chemin West Hunt Club), comme il est expliqué dans le document 1.

 

BACKGROUND

 

The 2007 Capital Budget approved funds to undertake the environmental assessment (EA) study for the Hope Side Road Extension (Richmond Road to West Hunt Club Road) this year. 

 

The City’s Transportation Master Plan (TMP) identifies the Hope Side Road Extension as a new two-lane road from Richmond Road to Highway 416, which crosses the National Capital Commission (NCC) Greenbelt. It is identified as a Phase 3 project–implementation between 2013 and 2021.

 

Growth in South Kanata, Stittsville, and the rural southwest has resulted in increasing demand on the Richmond Road-West Hunt Club Road corridor.  Intersections such as Stonehaven Drive at Richmond Road at the edge of the Bridlewood community have exceeded their capacity, have undergone expansion and continue to have significant impacts on the quality of life in the adjacent community due to traffic congestion within the residential community.

 

The EA for this project is being brought forward to evaluate the issues in the context of a larger study area and determine the appropriateness of the earlier implementation of a component of the larger project as a means to address diminishing service levels.  On a conceptual basis an initial component of the project could include a new two-lane roadway from Richmond Road to Moodie Drive at the south edge of the Greenbelt.

 

Prior to initiating retaining a consultant for this EA, staff seeks approval from Committee on the Study Statement of Work (SoW), which identifies the level of effort to undertake the work, and thus sets the study budget.

 

DISCUSSION

 

The SoW is described in Document 1. It outlines the tasks to be undertaken for the Hope Side Road Extension EA study, including consultation, and identifies the study deliverables. Upon approval from Transportation Committee, the SoW will form the basis for a call for proposals to the consulting industry.

 

This project will be carried out as a Schedule ‘C’ Class EA (self assessment) as set out in the Municipal Engineers Association: “Municipal Class Environmental Assessment” document.

 

As a significant portion of the study area is situated within the National Capital Commission Greenbelt, there will be a requirement for Federal permits and property to construct the project. Accordingly, the project must also comply with the requirements of the Canadian Environmental Assessment Act (CEAA). Since this project must satisfy both Provincial and Federal act requirements, a co-ordinated process will be undertaken to avoid unnecessary duplication.

 

The Study Area will include a primary zone that generally follows the south limit of the Greenbelt from Richmond Road to Moodie Drive, and then follows along the west side of Highway 416 to West Hunt Club Road.  A secondary Study Area zone will extend to the Eagleson Road Corridor on the west, the West Hunt Club Road Corridor on the north and the Fallowfield Road-Cedarview Road Corridor on the south and east.

 

Some tasks will require examination of a broader area beyond these limits in order to address environmental impacts; operational issues; to coordinate with relevant on-going studies and projects; and, to study and identify tie-ins to future network connections.

 

Key considerations for the Hope Side Road Extension EA study include the following:

 

 

It is prudent to start this study now due to the complex issues presented by the introduction of a new corridor in or near the Greenbelt.  Transportation demand projections have shown a consistent requirement for system expansion crossing the Greenbelt from the south half of the West Urban Community, and it is important to establish the feasibility of this corridor before additional communities such as the area currently being planed by the Fernbank Community Design Plan are established with the Hope Side Road Extension anticipated as a future corridor. 

 

It is unlikely that the TMP update will remove this project from the identified future requirements based on growth projections, development applications to date and current traffic demand.

 

STUDY TIMING

 

In accordance with established City practice for the acquisition of services, a two-step process consisting of a Request for Qualifications (RFQ) followed by a detailed Request for Proposals (RFP) will be utilized. The RFP process will end with a contract award in early March 2008.

 

It is expected that it will take 18 months after contract award to complete this study, which is consistent with industry practice for projects of this scope and complexity.

 

ENVIRONMENTAL IMPLICATIONS

 

The study will identify potential effects on the social, physical and natural environments. Alternative solutions will be developed and their impacts will be evaluated. The study will pay particular attention to identifying and assessing potential impacts on the NCC Greenbelt – most notably the Stony Swamp. Appropriate mitigation measures will be developed and post-mitigation environmental impacts will be determined.

 

RURAL IMPLICATIONS

 

The secondary Study Area includes the rural area bounded by Richmond Road, Fallowfield Road and Cedarview Road.  This area has been included in the scope of the study to ensure that any potential impacts (i.e. noise, vibration, air quality, drainage) are fully considered in the development and evaluation of alternatives.

 

CITY STRATEGIC DIRECTIONS

 

The recommendations contained herein directly support the following 2007-1010 City Strategic Directions adopted by Council on 11 July 2007:

 

F4        Ensure that City infrastructure required for new growth is built or improved as needed to serve the growth.

 

CONSULTATION

 

Consultation will be an integral part of the EA process. This study will involve a large number of stakeholders, including community groups, property owners, businesses, institutions, approval agencies and special interest groups as described in the Consultation Section of the Statement of Work (Section 4.0). Early in the study process stakeholders will be identified through various forms of consultation, including liaison with City Councillors, community associations, approval agencies and public notification.

 

The consultation process will include meetings with key stakeholders through the Agency, Business and Public Consultation Groups. Consultation with the general public will occur principally through open house meetings, but also through the project web page, and by e-mail. Additional meetings with specific agencies, landowners, groups or individuals will also be held as required to address any specific issues that may arise.

 

City staff have met with the local ward Councillor and NCC staff to introduce the project, identify issues for consideration during the EA and discuss the public consultation program. 

 

FINANCIAL IMPLICATIONS

 

Funding for the Hope Side Road Extension EA study is currently available in Order No. 902559, Environmental Assessment Studies –  Arterial Roads.

 

SUPPORTING DOCUMENTATION

 

Document 1     Hope Side Road Extension (Richmond Road to West Hunt Club Road) Environmental Assessment Study – Statement of Work

 

DISPOSITION

 

Following Committee approval of the attached Statement of Work, the Planning, Transit and the Environment Department will initiate the consultant selection process with the assistance of the Supply Management Division.

 


HOPE SIDE ROAD EXTENSION (RICHMOND ROAD TO WEST

HUNT CLUB ROAD) ENVIRONMENTAL ASSESSMENT STUDY –

STATEMENT OF WORK                                                                                      DOCUMENT 1

 
 
Hope Side Road Extension Environmental Assessment
Statement of Work

 

 

1.0 Introduction

The City of Ottawa is the proponent of a Class Environmental Assessment (EA) to study the proposed Hope Side Road Extension.  This Statement of Work (SoW) describes the City’s intentions with respect to the methodology, public consultation and deliverables for the study.

 

2.0 Planning Context

The Hope Side Road Extension was identified as a future roadway requirement in the former Regional Official Plan (OP) in 1997 and was reconfirmed as a future need in the City’s 2003 OP and the Transportation Master Plan (TMP).  The fundamental purpose of the Hope Side Road Extension is to provide additional arterial capacity across the Greenbelt for the southern half (south of Highway 417) of the West Urban Community (WUC).  The additional arterial capacity will allow a redistribution of traffic to reduce bottlenecks on the existing road network and accommodate the urban development that has been planned and being implemented in the WUC of the City.

 

Guided by the Ontario Planning Act, the OP contains Council’s objectives and policies for managing growth in Ottawa to the year 2021.  The TMP establishes infrastructure and program needs, and supporting policies for the City’s transportation system to the year 2021.

 

The form and function of this transportation facility will be determined through the EA process, which will satisfy the requirements of both the Provincial and Federal EA legislation.  The values and interests of the public/community groups are key elements that will be considered in the evaluation and decision-making process.  Effective consultation on the nature and form of the facility is fundamental to arriving at the most appropriate solution.

 

The conceptual location of the Hope Side Road Extension is illustrated on the following excerpt from the OP Schedule E - Urban Road Network, followed by excerpts from the OP Schedule B – Urban Policy Plan, and OP Schedule A – Rural Policy Plan.





3.0   Work Plan

The major tasks for this Class EA are proposed as follows:

 

3.1 Study Initiation

The Study Initiation will include liaison with Provincial and Federal authorities responsible for EA reviews to obtain their input on various EA requirements that must be met (specific to this project).   The Study Initiation will also include consultation on; the description of the major tasks of the EA, including a plan for development of alternatives as well as a process for evaluation of these alternatives; include a detailed public consultation program identifying the roles and responsibilities of the Agency Consultation Group (ACG), and the Public Consultation Group (PCG), as well as timelines and communication plan for the public Open Houses; high-light major milestones and decision-making steps, and; consultation with the Advisory Committees.

 

3.2 Confirm the Need and Justification for the Hope Side Road Extension

Following the Study Initiation, the Class EA work begins with the review of the need and justification for the Hope Side Road Extension.  Although the TMP investigated demand and identified the need for additional arterial capacity, a re-examination of need and assumptions is required under the Provincial EA Act.  This exercise will be carried out by forecasting travel demand for the west end of the City and determining both existing and future needs for a facility with respect to the impact on east-west travel demand/distribution, economic benefits and links to major employment destinations. 

 

An examination of future traffic levels across screenlines and study area intersection level of service will also supplement the review.  The travel demand analysis must consider various Transportation Demand Management (TDM) trip strategies including enhanced transit service in the corridor in accordance with TMP and OP policies.

 

3.3 Examine and Document Existing Conditions

As with every EA, an inventory and assessment of the various existing conditions must be undertaken at the outset. These include, but are not limited to:

·        transportation

·        land use

·        utilities

·        social/human environment

·        physical environment

·        natural environment

 

In addition, the Study will include investigations of any special aspects of the Study
Area that should also be considered.  For example: the effects on green space and natural areas, natural / recreational / agricultural uses in the NCC’s Greenbelt, the effects of noise and air quality on the adjacent communities, any archaeological potential, and the environmental/economic implications of construction in the vicinity of a limestone resource area (Quarry).  The inventory must be completed for the entire study area so that as alternative solutions and designs are developed and analyzed, the cumulative effects can be examined.  The inventory must also be broad enough to fulfill both Provincial and Federal EA requirements.

 

3.4 Develop Evaluation Criteria and Evaluation Process

To expand on the general evaluation process developed at the Study Initiation, a list and description of the evaluation criteria to be used to assess the various alternative solutions and alternative designs, will be developed with input form both consultation groups. 

 

3.5 Develop Alternatives Solutions and Alternative Designs

The TMP recommends the Hope Side Road Extension be a new two-lane arterial roadway.  This Study will also investigate many other alternate infrastructure and transportation solutions such as:

·        do nothing

·        implement transit/HOV lanes

·        mixed-use facilities

·        transportation demand management (trip reduction initiatives)

·        alternate routes (other corridors, such as Richmond – West Hunt Club)

·        park and rides

·        bicycle lanes, sidewalks and recreational paths

 

The different alternative solutions and designs will be developed with input from City Advisory Committees and will be presented to the public for comments at three Public Open Houses throughout the Study (see section on Public Consultation Plan).  Developing and examining a full range of options complies with the EA Act requirement that all reasonable alternative solutions for the undertaking be assessed.

 

3.6 Develop a Recommended Plan

The alternative designs developed in Task 3.5 will be assessed and evaluated as to their affects on the natural, social, urban, economic and transportation environments.  To ensure that all of the impacts are identified, it would be necessary to carry out investigations such as: noise, air quality, vibration, natural areas and wildlife habitats, stormwater management, geotechnical surveys, traffic impacts, accessibility and safety, landscape design, property impacts and any other research that would be required to properly define the cumulative effects of the facility. 

 

Alternatives will be compared to each other with the ultimate goal of formulating a recommended plan.  This design would have to meet the transportation needs while at the same time minimizing adverse affects to the other environments (natural, social, urban, economic).  The recommended plan could be one or a combination of alternatives.  Staging of the recommended plan will also be considered.  The recommended plan will include a coordinated centre-line, cross-section and configuration, property envelope, mitigation plan, identification of next steps and approval, potential construction phasing, and preliminary cost estimates for budgetary purposes.

 

3.7 Environmental Study Report (ESR) & Environmental Screening Report

The Study deliverables will include an ESR, which documents the entire class EA including the recommended design and any appropriate mitigation plans.  A draft ESR will be circulated to the study consultation groups and any other approval agencies, such as the NCC and MNR, for comment.  The final ESR, incorporating all pertinent comments, will be prepared and made available to the public for the formal 30-day Review Period as outlined in the Class EA requirements. 

 

In addition to the ESR required under the Provincial EA process, a Federal Project Description as well as an Environmental Screening Report will also be produced as is required under the Federal EA process.  The EA will include a cumulative impacts assessment of existing and planned transportation infrastructure on the Stony Swamp and Bruce Pit Sector of the Greenbelt.

 

 

4.0 Consultation Plan

There will be a comprehensive communications and consultation effort to ensure that all stakeholders are aware of the project and have an opportunity to provide input and feedback in a timely manner.  The communications plan consists of Study notifications and the consultation program.

 

4.1 Notifications

The public will be informed of the study commencement, Public Open Houses (POH), and study completion.  Notifications will be sent out at appropriate stages in the Study, and each announcement will take the following forms:

 

·        advertisements in daily newspapers (The Ottawa Citizen, Le Droit);

·        advertisements in community papers;

·        road signs along the study corridor (on Richmond Road at Hope Side Road, and West Hunt Club Road at Highway 416, and Moodie Drive and Richmond Road at the edge of the Greenbelt); and

·        City’s website – link dedicated specifically to this project.

 

The ward Councillor, and any other Councillors that identify an interest in the study, will be informed in advance of any public notification regarding this project.  The ward Councillor, and any other Councillors that identify an interest in the study, will also have the opportunity to attend status update meetings as required, which will typically be scheduled in advance of POHs.

 

In addition to study notifications the Public Open House meeting will be documented in a Public Open House Summary Report – one for each of three Public Open Houses, and the City website will include a Project Update Newsletter – minimum of three to coincide with the there key open house meetings. 

 

4.2 Consultation

The consultation program will consist of meetings with stakeholders through Consultation Groups, meetings with the general public through POHs and a website dedicated to this project.

 

Stakeholders will be organized into various groups, which will meet with the Study Team at key stages to review and comment on the Study findings.  The Study Team’s Project Manager will chair each consultation group meeting.  The 2 consultation groups are:

·        Agency Consultation Group (ACG)

·        Public Consultation Group (PCG)

 

4.2.1 Agency Consultation Group (ACG)

The ACG’s role will be to address the full range of technical issues and to comment on all of the special studies required to fully assess the various alternatives and to ensure compliance with policies, master plans and legislation.  The ACG will include experts in their related fields from government agencies and approval bodies with representation from the:

 

·        National Capital Commission (NCC)

·        Ministry of the Environment (MOE)

·        Ministry of Natural Resources (MNR)

·        Ministry of Transportation (MTO)

·        City’s Public Works & Services Department

à        Traffic and Parking Operations

à        Infrastructure Services

à        Surface Operations

·        City’s Planning, Transit & the Environment Department

à        Planning

à        Transit Services

à        Economic and Environmental Sustainability

·        Community & Protective Services

à        Fire Services

à        Parks & Recreation

·        Conservation Authorities

·        Ottawa Police Service

·        Other agencies identified through the consultation process

 

There will be a number of meetings between the Project Team and ACG.  They will include but not be limited to the following areas for which the ACG will review and provide comments:

 

·        Information gathering, and issue identification

·        Preliminary development of alternatives to the undertaking and initial screening of alternatives (modes and routes)

·        Refinement of selected alternatives and their detailed evaluation

·        Review of technically preferred alternative

·        Development of a recommended plan, including mitigation measures

 

4.2.2 Public Consultation Group (PCG)

The study area for the Hope Side Road Extension spans several different communities with their own characteristics, needs, and values.  In order to fully address both local and regional issues, a PCG will be established.  Generally, the PCG membership consists of leaders of community associations, City Advisory Committees and special interest groups that are directly affected by the Project.  Lists of groups and individuals potentially affected by this project will be compiled with the assistance of the adjacent ward Councillors.  These groups/individuals will be contacted upon commencement of the project to be invited to join the PCG.

 

Similar to the ACG schedule, the PCG will meet to review and comment on the findings at key stages in the Study.  The series of meetings will mirror those identified in Section 4.2.1.

 

4.2.3 Project Website

A website will be established, hosted on the City’s home page, ottawa.ca, that will contain all pertinent information about this project.  Notice of public meetings and events, information bulletins and POH material will be posted in English and French for review by the public. 

 

4.2.4 Public Open Houses

In addition to the Consultation Groups and the website, the Study Team will consult with the general public at three-planned Public Open Houses (POH).  Information for review and comment at these formal POHs will generally include the following:

 

POH #1

POH #2

POH #3

·    Introduction

·    Study Purpose

·    Need and Justification

·    Study Process & Schedule

·    Existing Conditions

·    Alternatives to the Undertaking

·    Evaluation Criteria

·         Preliminary Screening of Alternatives

·         Next Steps

 

·    Development of Options

·    Evaluation Criteria

·    Assessment of Options

·    Environmental Effects

·    Next Steps

·    Recommended Option

·    Mitigation Plan

·    Next Steps

 

At all Open Houses, there will be bilingual representatives from the Study Team and all presentation material will be in both English and French.

 

4.2.5 Transportation Committee Meetings

At the conclusion of the project, the study findings will be presented to the Transportation Committee for approval, followed by Council approval.