Joint Transportation and Transit Committee
Réunion conjointe du Comité des Transports et du Comité du Transport en
Commun
15 April 2008 / le 15avril 2008
Submitted by/Soumis par : Nancy Schepers, Deputy City Manager/Directrice
municipale adjointe,
Planning, Transit and the
Environment/Urbanisme, Transport en commun et Environnement
Contact Person/Personne ressource : Vivi Chi, Manager/Gestionaire
Planning
Branch/Direction de l'urbanisme
(613)
580-2424 x21877, vivi.chi@Ottawa.ca
1.
That this report be
received and tabled for public consultation and future consideration by the Joint
Transportation and Transit Committee meeting on May 21, 2008; and
2.
That, subject to
public consultations, the following recommendation be tabled at the May 21,
2008 meeting of the Joint Transportation and Transit Committee:
That the Joint Transportation and Transit
recommends that City Council approve Option 4 as the preferred downtown transit
solution and future rapid transit network.
1.
Que
le présent rapport soit soumis et déposé aux fins des consultations publiques
et de son examen futur à la réunion du Comité conjoint du transport et du
transport en commun le 21 mai 2008;
2.
Que,
sous réserve des consultations publiques, la recommandation suivante soit
déposée à la réunion du Comité conjoint du transport et du transport en commun
le 21 mai 2008 :
Que le Comité conjoint du transport et du
transport en commun recommande au Conseil d’approuver l’option 4 comme solution
privilégiée en ce qui a trait au transport en commun au centre-ville et au
réseau de transport en commun futur.
This report presents the primary rapid transit network component of the Transportation Master Plan (TMP) update for Committee’s and Council’s consideration and approval. The phasing or implementation plan (including possible interim solutions, and development of secondary transit corridors) will be assessed over the coming months and will be subject of another round of public consultation and reporting to Committee and Council in Fall 2008.
The review of the rapid transit system began in the Fall 2007, starting with a series of high-profile public consultation events on the transportation vision with particular emphasis on transit. The proposed Transportation Vision and a summary of the consultation are attached as Documents 1 and 2. Key transit comments received include:
· Support for a public transit system that is convenient and reliable;
· Transfers are acceptable provided that service is frequent and waiting areas are pleasant;
· Strong support for a downtown transit tunnel;
· Continuing interest in caring for the environment;
· Need to develop a transit plan that is affordable.
Following the visioning exercise, surface, elevated and tunnel connections through the downtown were assessed and only the tunnel option was deemed to be feasible. Four network options, all with a tunnel facility, were developed with combinations of bus and/or rail based transit systems. Agencies, business groups, and the public were extensively consulted on the four network options.
A strong majority of those who participated in the consultation events prefer the rapid transit network Option 4 (Figure 7). This network has a light rail transit (LRT)-based tunnel with rail transit in an east-west direction between Baseline and Blair transitway Stations. The network also includes a north-south rail line from downtown to Bowesville, including a link to the Airport. Extensions to all suburban nodes from the rail terminus points will continue to be on the Transitway.
The recommended rapid transit network Option 4 represents the minimum light rail and bus-based system that is required to serve the City to the year 2031, with an anticipated population of 1.136 million by that time. Its most significant feature that sets this plan apart from previous plans is the LRT tunnel through the downtown and the conversion of the Transitway to LRT between Baseline and Blair Stations. This grade separation will ensure reliable transit service through the downtown, which will encourage transit ridership and result in the City meeting its transit modal split target of 30 per cent. The transit tunnel could also be a major catalyst for partnerships with the private sector to create a vibrant community with services connected to active transit stations below ground. The network is also flexible in that it does not preclude future extensions of the LRT to the suburbs should it be deemed financially prudent to do so. In the meantime, BRT corridors to the suburbs can continue to be built so that early rapid transit service can be brought to these communities. The consultant’s technical report on the network development is attached as Document 3.
Options have also been left open to integrate with the Société de transport de l'Outaouais (STO) bus-based transit services. STO integration will be addressed through the City’s upcoming Downtown Transit Tunnel Planning and Environmental Assessment Study and the Interprovincial Transit Integration Strategic Planning Study (the latter to be led by the National Capital Commission (NCC) with joint partnership of the City of Ottawa and STO/Gatineau).
Staff also engaged an international team of respected transit and urban planning professionals to conduct a technical review of the proposed primary rapid transit network. The Peer Review Panel’s report and a brief background description of the panel members is attached as Document 4. Key findings of the Panel include:
· 30 per cent modal split target is achievable;
· Option 4 is recommended, however LRT corridors should be limited to inside the Greenbelt area (with BRT connections to the designated outlying Town Centres);
· LRT connection to the Airport is recommended because Ottawa is the nation’s capital;
· Transit investment should be contained within the current urban boundary and that only basic mobility (e.g. Para Transpo) be provided beyond;
· Aggressive management of land use and growth is required to complement the massive transit investment program that is envisaged for Ottawa;
· STO should continue to operate on-street in downtown Ottawa if possible.
Next steps in the TMP update relating to transit planning include examining the secondary corridors (grey lines depicted in Figures 4,5,6, and 7) and developing an implementation/priority plan. In setting the priority plan, the following factors need to be considered for each of the projects/corridors in the transit network:
· Ridership;
· Status of planning work to date;
· Ease of implementation (minimize disruption, opportunities to integrate with development, etc.);
· Logical sequencing of projects to maximize transit benefits;
· Opportunities to implement interim solutions/staging;
· Affordability (funding, available cash flow).
The preliminary cost estimate for the primary transit corridors in Option 4 (in 2008 dollars) is approximately $4B and the annual operating cost in year 2031 would be approximately $434M. The costs are subject to detailed planning and environmental assessments and system configuration. Secondary transit corridors still need to be developed and costs estimated. Estimated cost does not include costs for STO solutions, inflation, property acquisition or additional costs for unforeseen circumstances.
The current Long Range Financial Plan includes a total funding envelop of approximately $2.1B for rapid transit over the 10 years of the plan. This forecasted budget includes the anticipated minimum 1/3 contribution each from the Federal and Provincial governments. Discussions are continuing with the funding agencies.
The consultation program to-date has consisted of two main phases:
Phase 1 took place throughout September to December 2007 and focussed on informing and seeking feedback from citizens about various transportation related challenges and opportunities facing Ottawa. Within this context, the TMP Vision and Guiding Principles were reviewed and key information was collected with respect to the development of a preferred rapid transit network. Document 2 further summarizes the consultation process and outcomes from Phase 1.
Phase II consultations began March 3 and concluded March 31, 2008 as an exercise to inform and seek feedback from the public about four Downtown Rapid Transit Network Options and their implications on the overall transportation systems. A number of activities were undertaken including open houses, discussion groups, stakeholder focus group sessions, online consultation and a Mayor’s streeter survey. Feedback received is summarized in Chapter 8 of Document 3.
During the 1970s, the former Region began a program to implement a
rapid transit system. This program led to the construction of the initial
31-kilometre Transitway network (the sections from Baseline Station in the
southwest to Blair Station in the east and South Keys Station in the
southeast). Since the completion of
these initial sections, several extensions and use of freeway shoulder lanes
have been planned, parts of which have been implemented. To complement the Transitway system, an
eight-kilometre diesel light rail service, commonly known as the O-Train, was
introduced in 2001 between Greenboro and Bayview Stations. Today, the City has 46 kilometres of
rapid transit system (in exclusive rights-of-way and shoulder lanes), which has
been a key factor in Ottawa attaining enviable transit ridership levels. Ridership has reached over more than 120
riders per capita – highest in North America of comparable-size cities.
This success, however, has led to the
system reaching its capacity in the downtown area and has contributed to
congestion problem and reliability issues especially in the winter months. The lack of transit capacity in the downtown
area has been a topic of discussion for many years. Previous studies have identified the eventual need for a grade
separated rapid transit facility through the downtown. Regional/City Council decided to continue
with further extensions of the bus Transitway outside of the Central Area
first, leaving the expensive grade separation of the downtown section until
later. This “outside-in” approach to Transitway development helped with the
early establishment of Ottawa’s high transit ridership.
The 2003 Rapid Transit Expansion Study
(RTES) identified the implementation of a light rail transit (LRT) service from
the downtown (Rideau Centre) to Riverside South (Limebank Station) as the top
priority project. RTES reviewed the concept of a downtown transit tunnel and
concluded that the proposed on-street LRT corridor, combined with operational
improvements along the Albert and Slater Street Transitway, would provide the
required transit capacity within the 2021 planning period.
The plan to proceed with the North-South
LRT was approved by Council in November 2005 with a condition of reducing the
number of buses operating on Albert and Slater Streets by 30 per
cent. This condition would have
resulted in consolidating and reducing the number of direct-to-downtown express
routes.
However, in December 2006, due to non-fulfillment of conditions, the Project Agreement for the N-S LRT Project was terminated in accordance with its terms. One of the principle reasons leading to the decision not to proceed with the contract award for the North-South Corridor LRT project was concern over the proposed mixed operation of the LRT with buses and general traffic on Albert and Slater Streets.
In January 2007, Mayor O’Brien formed a Task Force to study the City’s transportation priorities. In June 2007, the Mayor’s Task Force delivered a report entitled “Moving Ottawa”. The report covered a wide range of transportation issues, but focused on the development of a future rapid transit plan. The Task Force recommended an east-west rail tunnel bored through the downtown with diesel-electric trains operating on a city-wide network that would switch to electric mode while in the tunnel.
In
November 2007, Council approved the scope of work for the Downtown Ottawa
Transit Tunnel Planning and Environmental Assessment Study. Furthermore,
Council identified the completion of the Transitway, construction of the
downtown tunnel, implementation of rapid transit using the Cumberland
Transitway corridor and the implementation of the LRT to the south-eastern
growth area as the City’s priority projects for transit funding.
The update of the Transportation Master Plan (TMP), which is being undertaken in conjunction with the five-year review of the Official Plan, provides an opportunity to reassess the City’s growing transit need to 2031, also keeping in mind the City’s vision for a transit system beyond the planning horizon.
This report summarizes the technical
work leading to the proposed network and technology options, public feedback
received as well as the recommended option for the downtown and its
implications on the rest of the network.
The analysis and recommendation presented in this report are one component of a
larger study to update the TMP.
Throughout the Fall of 2007, the TMP Vision and Guiding Principles were reviewed through the following new and unique public consultation activities:
· Educational materials ‘White Papers’;
· Online Consultation (Beyond Ottawa 20/20, Ottawa Talks, etc.);
· Streeter Surveys;
· Stakeholder-based Focus Groups;
· The City Café event;
· A Transportation Master Plan Interactive Workshop.
· Overall, a significant majority of people felt that the existing TMP Vision and Guiding Principles continues to remain valid and that only modest changes should be considered with respect to: the natural environment; performance measurements; implementation timelines; affordability; and land use planning.
· People want a transit system that is efficient, convenient, reliable and comfortable.
· Interest in the idea of a downtown transit tunnel is strong. Many people believe that a tunnel is needed immediately while others believe further study is required to examine potential alternatives.
· A strong majority of people believe the City should consolidate express routes and expand feeder-line-haul service to improve transit speed and reliability through the downtown provided that transfers are convenient, quick, reliable and comfortable.
This led to the development of the following revised TMP Vision Statement (in box below) and its accompanying Guiding Principles, as summarized in Document 1.
|
Transportation Vision In
2031, Ottawa’s transportation system will enhance our quality of life by
supporting social, environmental and economic sustainability in an
accountable and responsive manner. |
Feedback from this phase of consultation influenced the development of the downtown rapid transit options as presented later in this report. Document 2 provides a complete summary of public comments received.
Planning Assumptions (population,
employment)
Projections of Ottawa’s long-term growth are fundamental to the City’s assessment of future infrastructure needs. As part of the Official Plan review, the City’s current 2021growth projections were comprehensively re-examined for the new 2031-planning horizon. The development of these new growth projections considered the Greater Ottawa-Gatineau Area (including adjacent municipalities) to ensure that the magnitude and the extent of the commuter shed were included in the overall assessment of growth for Ottawa.
The City’s population is projected to grow by approximately 30 per cent to reach 1,135,700 by 2031 (an additional 265,000 persons). Employment is expected to grow by approximately 35 per cent to reach 703,000 (an additional 180,300 jobs). The 2031 population and employment levels for major growth areas, and the percentage increase over current population and employment levels are summarized in Figure 1. By 2031, approximately 52 per cent of the population and 72 per cent of employment will be located in areas inside the Greenbelt.

Future Travel Demand
The requirements for transportation systems is fundamentally linked to where people live and work, with the most significant demands occurring during peak commuter travel times. Therefore, the travel demand analysis efforts have been focused on the morning peak hour as it represents the time of the day when road networks experience increased levels of congestion and is the busiest hour for transit use.
The 2031 morning peak hour travel demand forecast was determined using a computer-based long-range transportation demand model (TRANS model). The model was recently redeveloped to incorporate the state-of-the art modeling practices and calibrated against the 2005 Origin-Destination Survey.
Main findings of the forecast modeling, as summarized in Table 1, include:
1. Total travel by all modes will increase by about 38 per cent during the morning peak hour.
2. Non-motorized trips (walking and cycling): City-wide, morning-peak hour trips is forecast to grow by about 50 per cent, from 23,700 to 35,400 trips.
3. City-wide growth in trips by automobile during the morning peak hour is forecasted to increase by approximately 24 per cent (from 146,600 to 182,300 trips) which is less than the rate of population growth. The growth in auto vehicle use is largely to destinations outside the Greenbelt. City-wide morning peak hour mode split will decrease from 77 per cent to 70 per cent.
4. City-wide growth in travel by public transit during the morning peak hour is forecasted to increase by approximately 76 per cent (from 44,500 to 78,300 trips). City-wide transit mode split is forecast to increase from 23 per cent to 30 per cent by 2031.
5. Transit mode split, for morning peak hour, is forecasted to increase from 46 per cent to 55 per cent for trips destined to the Inner Area, from 26 per cent to 36 per cent for trips destined to inside the Greenbelt and from 9 per cent to 19 per cent for trips destined to outside the Greenbelt
6. Transit mode split is forecasted to increase from 24 per cent to 29 per cent for trips originated from outside the Greenbelt.
|
Ottawa Travel2 AM Peak Hour |
2006 |
2031 |
Percentage Growth |
||||
|
Person Trips |
Mode Share3 |
Mode Split4 |
Person Trips |
Mode Share |
Mode Split |
||
|
Walking/Cycling
(Non-Motorized) |
23,700 |
11% |
- |
35,400 |
12% |
- |
49% |
|
Transit Riders |
44,500 |
21% |
23% |
78,300 |
26% |
30% |
76% |
|
Private Auto Trips |
146,600 |
68% |
77% |
182,300 |
62% |
70% |
24% |
|
Total - All Trips |
214,800 |
100% |
100% |
296,000 |
100% |
100% |
38% |
1.
Individual
area transit mode split values are summarized in Appendix D of Supporting
Document 3
2.
Includes
all travel originating or destine to Ottawa
3.
Mode
share is the percentage of trips made by one mode, relative to total trips made
by all modes
4.
Mode
split is the percentage of trips made by one mode, relative to total trips made
by motorized modes
Primary Travel Desire Lines:
Figure 2 shows the 2031 predicted primary travel flows (i.e. greater than 1,700 trips/hour) as well as the transit mode split between different planning areas. The width of the arrows indicates the magnitude of travel (number of morning peak hour person trips) and the colour of the arrow indicates the transit mode split (the darker the colour, the higher the transit mode split).

Figure 2. Primary
Desire Lines (2031 morning peak hour)
As demonstrated in Figure 2, during the morning peak hour, Ottawa’s Inner Area will continue to be the most significant destination for travel since more than one-quarter of Ottawa’s 2031 employment base will be located inside the Inner Area. However, as a result of the significant planned growth in the urban areas outside the Greenbelt, other strong travel demand between other areas of the city will emerge, such as: from Orleans to AltaVista area; from Kanata to Bayshore and Merivale areas; and from Barrhaven to Merivale, Bayshore and Kanata areas.
Urban areas located outside the Greenbelt will continue to be attracted to transit to reach Ottawa’s Inner Area with average mode splits reaching 70 per cent (i.e. during the morning peak hour, 70 per cent of trips from the suburban areas to the Inner Area will be by transit). Transit mode splits for the other primary travel demand between other urban areas are predicated to be in the mid 20 per cent to 30 per cent range.
The configuration of the rapid transit network will dictate the corridor that transit customers will take and the directions through which they enter downtown. Riverside South/Leitrim residents as well as some Barrhaven residents could be carried north on the current O-Train corridor through Carleton University and Bayview Stations and enter the downtown from the west. The other option would be for Riverside South/Leitrim residents to use the current Southeast Transitway corridor to enter the downtown from the east. Each of these options would have different ridership implications on the capacity requirements for the downtown. The downtown transit demand for these two options is shown in Figure 3. The peak passenger demand would range between 13,700 and 15,600 passengers per hour. Option to fully integrate transit customers from Gatineau could potentially add up to 8,500 passengers per hour.
To visualize the scale of the problem in the downtown core, up to 347 standard buses at 10 seconds apart or 223 articulated buses at 16 seconds apart would be required to carry the 15,600 potential transit riders per hour entering downtown using Ottawa transit system. In addition, 252 standard buses or 162 articulated buses would be required to carry future morning peak hour transit customers coming from the City of Gatineau.
It is clear that the downtown will continue to be the bottleneck of the system and addressing the downtown transit congestion will need to be a priority if the City were to achieve the 30 per cent transit mode split target. The following section describes the different options that were investigated to provide the required capacity to accommodate future transit demand in the downtown area.
|
2006 Transit Demand |
2031 Transit Demand |
Various options to provide the necessary
transit capacity to accommodate anticipated transit demand in the downtown were
assessed:
· Surface options
· Elevated option
· Tunnel options
Surface Options
The theoretical capacities of the bus-only lanes on Albert and Slater Streets are 195 buses per hour per direction. In the last five years, in responding to severe delays to service in the downtown, transit service has been modified to reduce the number of buses from over 200 to no more than 180 buses per hour to maintain service reliability. However, with the current operating strategy and with transit ridership continuing to grow, it will be impossible to accommodate the growth in ridership without exceeding the physical capacity of the two streets.
The following measures to increase the potential capacity of the downtown Transitway are examined:
· Consolidating express routes;
· Use of additional bus-only lanes on each of Albert and Slater Streets;
· Dedicating Mackenzie King Bridge for transit only;
· Use of other downtown streets such as Wellington Street, Queen Street and Laurier Avenue;
· Increasing the use of high-capacity buses such as double-deck or double-articulated vehicles.
Each of the above measures would have unfavourable traffic impacts and would create a negative on-street environment that would be unattractive to pedestrians and cyclists, and unacceptable to the adjacent business and property owners. Adding more buses on the streets would jeopardize the reliability of the transit operation especially during winter months. In addition, the analysis shows that even combining all of the above measures does not offer the required capacity to accommodate 2031 ridership demand.
Light-Rail Transit (LRT) surface option was also examined. It is estimated that a two-car LRT vehicle, operating every one minute, would be required to carry future transit demand. This frequency is much higher than the 2.0- to 2.5-minute minimum practical frequency for rail operation. Using longer trains will not be possible because the required platform length will necessitate the closure of adjacent property access points. Therefore, the LRT-only surface option is not an acceptable downtown transit solution for the long term.
Two concepts of a combined bus and LRT operation were examined during the North-South Corridor LRT project EA Study: one direction of LRT and BRT on each of Albert and Slater Streets; and two directions of LRT service on one street and two directions of BRT service on the other street. The two-direction concept was deemed to be unsafe. The one-direction concept of LRT and BRT on separate lanes was rejected as it would have significant impact on business due to the loss of the left-hand curb lane used for parking, loading, delivery and taxi zones. The one-direction concept of LRT and BRT on the same lane was deemed feasible and would be sufficient to carry the anticipated demand (20 two-car LRT and 180 buses on each street during peak hour). This was an appropriate solution at that time given that the funding envelop for the North-South LRT project was limited. The EA noted that a grade separation should not be precluded, as it would be required at some point in the future to ensure reliability of service. Due to concerns related to the reliability of the combined LRT/BRT operation, Council directed staff to reduce the number of buses by a minimum of 30 per cent by 2009 and evaluate the possibility of removing up to 100 per cent of buses. In order to remove large volumes of buses, more bus-to-bus transfers will need to be introduced. This reduced and modified service, however, would not accommodate the transit demand being forecasted for the 2031-planning horizon.
Based on the above, it is clear that there is no feasible surface-only transit solution in the downtown area without severely impacting adjacent businesses, having an undesirable urban environment and severely impacting the reliability of transit service.
Elevated Option
An elevated option for downtown was considered in the 1988 “Central Area Transitway Grade Separation Feasibility Study”. The Study found that an elevated solution would create a visual barrier through downtown, reduce direct sunlight to street level and would have very high capital costs to integrate stations into existing adjacent buildings. Also, the elevated solution would require significant utility relocation, and would have high operating and life-cycle costs due to exposure to the elements. For the above reasons, the elevated solution was not recommended.
Tunnel Options
A tunnel can resolve many of the current surface operating problems, as it would allow unconstrained flow through the downtown and hence improve the reliability of transit service. It will also provide weather-protected amenities for transit customers, improve pedestrian and cycling operations, reduce street noise and emissions, and present opportunities to enhance the street environment. A range of transit technologies that may be incorporated in the tunnel was considered. They include bus-only, LRT-only, and combination of bus and LRT. These different options are discussed in more details in the next section.
Combined surface/tunnel options were also
considered. There are two main
options: Bus-only tunnel with LRT on
the street; or LRT tunnel with buses operate on the surface. However, since both options will require
extensive financial investment in building the tunnel component and since the
tunnel can provide the necessary capacity to fully accommodate future demand,
there is no need to continue surface operation for anything more than local
routes for the ultimate network. This
would maximize the use of the tunnel and will improve the return on the
investment.
The approach that is taken is to build a network from the core out — addressing downtown congestion and determining the best way to serve communities in the west, south and east. Therefore, four alternative core rapid transit networks, each incorporating a tunnel option, have been developed to determine the most appropriate long-range rapid transit network and technology to serve Ottawa. These options are:
· Network Option 1: BRT Tunnel - Bus based
· Network Option 2: BRT/LRT Tunnel – Bus based with North-South LRT
· Network Option 3: LRT Tunnel - East and West downtown LRT
· Network Option 4: LRT Tunnel - East and West downtown LRT plus North-South LRT
The four options are illustrated in Figures 4, 5, 6 and 7 with existing corridors shown as solid lines and future extension as dashed lines. The broad grey arrows represent other possible complementary rapid transit corridors, which will be evaluated following Council’s decision on the primary transit network.
All options will require the move
to a feeder-line-haul operation with major transfer points to be at Baseline,
Lincoln Fields, Hurdman and Blair Stations.
The basic difference between each of the above options is the extent to
which LRT is incorporated. The
following sections describe briefly each of the four options.
Option 1: BRT Tunnel - Bus
based
This option is based on the existing bus Transitway with extensions to outlying suburban areas in the east, west and south. It incorporates an underground bus tunnel through the downtown and keeps the existing diesel-powered O-Train service from Bayview Station to Greenboro Station.
To address emission concerns in the tunnel, low emission buses such as hybrid-electric buses are assumed to be used on the main feeder-line haul. Also, to simplify passengers boarding in the downtown area, consolidating of some express buses will be required which will result in more transfers from bus to bus for some residents. An articulated bus running every 18 seconds through the downtown tunnel is required to accommodate the projected 2031 peak hour transit ridership demand.
Option 2: BRT/LRT Tunnel – Bus
based with North-South LRT
This option is based on the existing bus Transitway with extensions to outlying suburban areas in the east, west and south and the addition of a twin-track electric North-South LRT line from Bowesville Station to the downtown and the University of Ottawa with a connection to the airport. A joint-use LRT/bus tunnel through the downtown is incorporated to accommodate both the east-west buses and the North-South LRT trains. Similar to Option 1, consolidation of some express services and the introduction of low-emission buses on the main feeder-line haul will be required. A combination of two-car LRT trains running every 3 minutes and 45 seconds, and articulated buses running every 22 seconds through the downtown tunnel is required to accommodate the projected 2031 ridership demand.
The LRT is extended beyond the Greenbelt
to Bowesville to reach the preferred location for a rail maintenance yard,
which was approved as part of the North-South Corridor LRT EA Study. The existing Walkley yard has several
operational issues dealing with its size and access, additional cost and
environmental liability that prohibit its use for the North-South LRT
corridor. An advantage of the extension
is to serve the Riverside/Leitrim communities as they are currently not served
by any form of rapid transit service.
Option 3: LRT Tunnel - East
and West downtown LRT
This option is based on an LRT-only tunnel through the downtown, which requires a conversion of the Transitway between Baseline Station and Blair Station to twin-track electric LRT. It also includes Transitway extensions to outlying suburban areas in the east, west and south. The existing diesel O-Train would continue in operation as it does today from Bayview Station to Greenboro Station. Train sets of four-cars each need to run every 2 minutes and 18 seconds through the downtown tunnel to accommodate the projected 2031 transit ridership demand.
Bus to LRT transfers will mainly occur at Baseline, Lincoln Fields, Hurdman and Blair Stations. Baseline Station directly serves Algonquin College and is the focal point for the development of the Nepean Centrepointe lands as well as provides a direct connection to the Southwest Transitway. Lincoln Fields Station provides a direct connection to the West Transitway, as well as to transit routes operating on Carling Avenue. Hurdman Station is already a major transfer facility, located at the connection of the East and Southeast Transitways. Blair Station is at the convergence point of the East and Cumberland Transitways, and is surrounded by employment and retail developments.
It should be noted that for Option 3, the Southeast Transitway is extended to provide direct service to Riverside South residents destined to downtown. For this reason, Option 3 is not a staging option for Option 4.
Option 4: LRT Tunnel - East and
West downtown LRT plus North-South LRT
This option is essentially the same as Option 3 except that the O-Train is converted to twin-track electric LRT and extended to Bowesville Station with an LRT connection to the airport. Riverside South residents would travel to the downtown on the North-South LRT line. This option will require four-car LRT trains running every two minutes and four seconds through the downtown tunnel to accommodate the projected 2031 transit ridership demand.
Bus to rail transfers will occur at Baseline, Lincoln Fields, Bowesville,
Hurdman and Blair Stations. Further LRT extensions east, west and southwest are
possible and can be considered, but the segments from Baseline to Blair
Stations and from Bayview Station to Bowseville Station have been selected as
the minimal segments required for a successful operation. .




Figure 7. Network Option 4: LRT Tunnel - East and West downtown LRT plus North- South LRT
Preliminary capital cost estimates
for each of the four options are provided in Table 2, in 2008 dollars.
These estimates include engineering and contingency costs, but make no
allowance for property costs. Details
are included in Appendix G of Supporting Document
3. They are subject to refinement through further detailed planning work
and environmental assessments, as appropriate.
Table 2. Capital and Operating
Costs for Different Network Options (millions $)
|
Section |
Description |
Alternative 1 |
Alternative 2 |
Alternative 3 |
Alternative 4 |
|
|
Central Downtown |
Bayview to Hurdman (excluding Tunnel) |
$49 |
$68 |
$112 |
$112 |
|
|
Downtown Tunnel |
$780 |
$1032 |
$555 |
$555 |
||
|
West Downtown |
Baseline to Bayview |
$22 |
$22 |
$237 |
$237 |
|
|
East Downtown |
Blair to Hurdman |
0 |
0 |
$97 |
$97 |
|
|
South Downtown |
Bayview to Bowesville Includes Airport Link |
$100 |
$435 |
$100 |
$435 |
|
|
South Transitway |
Barrhaven Town Centre
to Bowesville |
$100 |
$100 |
$100 |
$100 |
|
|
West Transitway |
From Southwest
Transitway to Kanata |
$338 |
$338 |
$338 |
$338 |
|
|
Southwest Transitway |
Cambrian to Baseline |
$180 |
$180 |
$180 |
$180 |
|
|
Southeast Transitway |
Greenboro to Hurdman Includes Hospital
Link |
$44 |
$44 |
$44 |
$44 |
|
|
East Transitways |
Blair to Trim and Blair to Millennium |
$239 |
$239 |
$239 |
$239 |
|
|
LRT Maintenance Facility |
|
|
$100 |
$100 |
$200 |
|
|
Bus Maintenance Facility |
|
$300 |
$240 |
$120 |
$120 |
|
|
Infrastructure
Sub-Total |
$ 2,152 |
$ 2,798 |
$ 2,222 |
$ 2,657 |
||
|
LRT Vehicles |
0 |
$140 |
$750 |
$890 |
||
|
BRT Vehicles* |
Initial Fleet |
$800 |
$720 |
$400 |
$320 |
|
|
Replacement Vehicles |
$600 |
$540 |
$200 |
$160 |
||
|
Vehicles
Sub-Total |
$1,400 |
$1,400 |
$1,350 |
$1,370 |
||
|
|
$3,552 |
$4,198 |
$3,572 |
$4,027 |
||
|
|
$ 485 |
$ 472 |
$ 453 |
$ 434 |
||
Note 1: Cost estimates are
subject to verification through EA studies and system design
Note 2: Estimates do not include costs for STO solutions, inflation, property acquisition and additional cost for unforeseen circumstances
Note 3: Vehicle costs are
estimated over 30 years
Note 4: Operating costs are to accommodate the demand at the end of the planning horizon (2031)
La Société de transport de l’Outaouais (STO) currently operates
approximately 120 buses serving 4,400 peak hour transit passengers through
Ottawa’s central core
on the Rideau/Wellington Street
corridor. The combined operation of STO
interprovincial and OC Transpo transit on the Rideau/Wellington corridor is
currently nearing capacity with little room for growth.
This interprovincial ridership demand is expected to increase to 8,500
peak hour passengers by 2031, which translates to approximately 250 standard
buses in the peak hour. STO currently
uses mostly standard buses to service their interprovincial passengers. STO has plans for a future BRT operation in
a freight rail corridor in Gatineau and does not anticipate any need to convert
to rail transit service within the planning horizon.
Four very preliminary options were developed to show how interprovincial
STO service might be integrated in downtown Ottawa with the primary rapid
transit network options described above.
Option A: Surface Transit - STO would continue to operate on the surface
in downtown Ottawa. However, with a projected 250 buses per hour in the peak
direction, a single corridor will not provide enough capacity. Therefore, STO
buses would require more streets in Ottawa’s downtown on which to operate. This is not an acceptable option and
solutions have to be developed.
Option B: Shared Transit Tunnel – STO buses cannot be accommodated in the
bus tunnels proposed for rapid transit network Options 1 and 2 because of the
limited bus tunnel capacity. For network Options 3 and 4, a wider LRT/BRT
tunnel would be required to accommodate STO buses with an estimated additional
construction cost of $475M.
Option C: Separate Transit Tunnel - a separate bus tunnel for STO services could
be built with an estimated additional construction costs of $610M.
Option D: Transfer to Ottawa LRT – for rapid transit network Options 2, 3 and 4, there is capacity in the tunnel to accommodate additional STO passengers if they transferred to the Ottawa LRT system. Additional trains would be needed to accommodate the extra STO passengers. Transfer point could be located either in Ottawa or in Gatineau. Estimated additional construction cost could range between $35M for a transfer point in Ottawa to $190M for a transfer point in Gatineau.
A more detailed analysis will be undertaken to select the preferred
option for interprovincial rapid transit service through the upcoming joint
NCC/Ottawa/Gatineau-STO Interprovincial Rapid Transit Strategic Integration
Study, and the Downtown Transit Tunnel Planning and EA Study.
The four rapid transit network options are assessed using a common set of evaluation criteria. These criteria are grouped under four general categories: Transportation; Natural Environment; Social/Cultural Environment; and Costs.
Transportation:
· Transit ridership attraction
· Accommodating forecast transit ridership by 2031
· Accommodating transit growth beyond the planning horizon
· Operating issues that may impact service reliability
· Air quality and greenhouse gas emissions
· Biophysical environment (amount of salt use during winter operation)
Social / Cultural Environment
· Urban form (intensification and redevelopment opportunities)
· Access to key destinations
· Tourism and national capital image
· Noise and vibration
Costs
· Capital construction costs
· Vehicle costs (including replacement)
· Operating Costs
The results of
the relative evaluation of the four network options are presented in Table 3
|
|
Alternative 1 Bus Based |
Alternative 2 Bus with NS LRT |
Alternative 3 EW LRT |
Alternative 4 EW and NS LRT |
|
|
Transit and
Transportation |
|||||
|
Transit Ridership Attraction |
Base ridership of 76,400
trips (Growth of 31,900) Limited potential |
Ridership of 76,900 trips (Growth of 32,400) (2% more than Alternative
1) Some potential |
Ridership of 78,700 trips (Growth of 34,200) (7% more than Alternative
1) Greater potential |
Ridership of 79,200 trips (Growth of 34,700) (9% more than Alterative 1) Greatest potential |
|
|
Accommodating Forecast Transit Ridership |
Theoretically could operate at capacity Requires stations with; ·
4 bus bays ·
Fare pre-payment ·
Bus platoons |
Buses may be accommodated but will operate close to
theoretical capacity NS LRT vehicles can easily be accommodated Mix of
bus and LRT traffic is unbalanced |
LRT
vehicles can be accommodated |
LRT
vehicles can be accommodated |
|
|
Accommodating Transit Growth Beyond the Planning Horizon |
No flexibility to accommodate growth beyond the
planning period |
Minimal room for additional buses LRT component has additional capacity but it is not
required for this option |
Has room for
growth. Longer trains and more
frequent service could be provided |
Has room for growth. Longer trains and more frequent service could be provided |
|
|
Operating Issues |
Operating at capacity will mean that the service reliability
is substantially reduced Small delays will cascade
through the system causing larger delays well after the first delay is
cleared |
Buses will be operating close to capacity, which may
alleviate some of the reliability issues however the loss of the passing lane
will affect service Allowing buses to use the LRT lane will require reduced operating speed, affecting capacity |
Signalized system will operate well |
Signalized system will operate well |
|
Natural Environment
|
|||||
|
Air Quality and GHG emissions |
682,900 kg CO 63,900 kg HC 515,500 kg NOx 33,300 kg SOx 11,800 kg PM 88,875 t CO2 |
646,900 kg CO 60,400 kg HC 489,400 kg NOx 31,600 kg SOx 11,100 kg PM 84,227 t CO2 |
557,300 kg CO 52,200 kg HC 421,700 kg NOx 27,200 kg SOx 9,600 kg PM 72,559 t
CO2 |
512,000 kg CO 47,800 kg HC 387,300 kg NOx 25,000 SOx 8,800 kg PM 88,875 t CO2 |
|
|
Excavated Material |
Tunnels: 390,000 cu. m. Stations: 3 standard
stations |
Tunnels: 390,000 cu. m. Stations: 3 larger stations
(to accommodate extra platforms) |
Tunnels: 140,000 cu. m. Stations: 3 standard
stations |
Tunnels: 140,000 cu. m. Stations: 3 standard
stations |
|
|
Salt Use |
Highest use |
Second highest use |
Second lowest use |
Lowest use |
|
|
Social / Cultural Environment |
|
|
|
|
|
|
Property and Development Criteria |
Continuation with the current technology will
encourage similar property and development patterns |
Introduction of some LRT will encourage more
development in those areas |
Substantial LRT network will encourage a substantial
amount of property and development interest |
Largest LRT network with the greatest potential to
encourage property and development interest |
|
|
Capital Image |
No improvement to Capital
Image |
Improves Capital Image
somewhat |
Fosters very good Capital
Image |
Fosters best Capital Image |
|
|
Public Support |
No support |
No support |
Some support |
Substantial support |
|
|
Direct Airport Service |
Provides bus access to the
Airport |
Provides rail access to the
Airport |
Provides bus access to the
Airport |
Provides rail access to the
Airport |
|
|
Noise and Vibration |
Largest proportion of the
network is bus-based Highest impact |
Less bus-based activity
than Alternative 1, however busiest routes remain bus-based Second highest impact |
Similar to Alternative 4,
but with more bus-based service in the south Second lowest impact |
Smallest proportion of the
network is bus-based Lowest impact |
|
|
Costs |
|
|
|
|
|
|
Capital Construction Costs |
$ 2,152 M |
$ 2,798 M |
$ 2,222 M |
$ 2,657 M |
|
|
Vehicle Costs (including replacement) |
$1,400 M |
$1,400 M |
$1,350 M |
$1,370 M |
|
|
Total Capital Costs |
$3,552 M |
$4,198 M |
$3,572 M |
$4,027 M |
|
|
Operating Costs |
$485 M |
$472 M |
$453 M |
$434 M |
|
Consultations began March 3 and concluded March 31, 2008 as an exercise to inform and seek comments from the public on the four Downtown Rapid Transit Network Options and their implications on the overall transportation system. A number of activities were undertaken to provide flexible and convenient opportunities for the public and agencies to provide comments to the City, as listed below:
· Open Houses held at various locations throughout the City, including a public presentation at City Hall followed by a questions and answers period;
· Registered Discussion Groups as part of each Open House;
· Stakeholder Focus Group Sessions;
· City Advisory Committee Briefings
· Online Consultations;
· Internal and External Agency Group Meetings;
· Mayor’s Streeter Survey.
In
total, approximately 1200 written submissions were received during the month of
March, which shows the great interest in this planning exercise.
What
We Heard
A
summary of the consultation effort and feedback is attached in Chapter 8 of Document
3.
In general, a strong majority of the public and stakeholders indicated Option 4 as the preferred long-term transit solution for Ottawa (approximately 70 per cent of all comments received supported Option 4). The respondents believe that Option 4 provides the highest quality of transit service; is the best approach for urban intensification; has the lowest operating costs; has optimum long-term transit growth capacity; has the most positive environmental, social and economic impacts; and projects the most favourable perception of Ottawa as the Nation’s Capital City.
While there was also support for Option 3 (approximately 22 per cent of all comments received) many suggested that this alternative could serve as a ‘staged’ implementation for ultimately developing Option 4. It should be noted, however, that Option 3 would only be a staging of Option 4 if the existing O-Train were to be extended further south to connect Riverside South to downtown, otherwise the direct route to downtown for these residents would be the extension of the Southeast Transitway as depicted in Option 3.
There was little to no support for Option 1 and Option 2 (approximately three per cent of all comments received). People found these options to be the least sustainable and economically viable networks for the future.
Few people were either undecided or did not prefer any of the four options (approximately 5 per cent of all comments received). Additional key issues included:
Many people suggested that the LRT corridors shown in Option 4 should extend further to serve urban communities beyond the Greenbelt such as Kanata, Barrhaven and Orleans. Several people also suggested a northern LRT extension to the City of Gatineau.
Response:
The options presented illustrate the recommended minimum LRT service
requirements and do not preclude future additional LRT service extensions. Adding more LRT service will increase
capital costs. For the projected
transit demand volumes to 2031, it is not necessary to extend the LRT lines
beyond what is depicted in Option 4.
Some people mentioned that existing rail lines should be utilized. Others suggested that providing LRT corridors inside the Greenbelt would result in less suburban sprawl and greater urban intensification. Some people questioned the feasibility of the corridors identified in Option 4 such as using the Ottawa River Parkway.
Response: In general, most of Ottawa’s existing rail lines are not located close to where many people live or work and would be more appropriate for a regional commuter system than for urban transit. The options do not preclude the development of a commuter system using existing rail lines in the future. All corridors identified in the options, including the use of the Ottawa River Parkway, are subject to Environmental Assessments and functional designs.
Several people suggested a need for greater transit integration between the City of Ottawa and the City of Gatineau. Ideas ranged from developing a single interprovincial system to more integration between the two transit networks. Both the Ontario Ministry of Transportation (MTO) and the Ontario Ministry of Public Infrastructure Renewal (PIR) recommended greater coordination between the Interprovincial River Crossing Environmental Assessment, STO’s Rapibus System Plan, and the National Capital Commission Transit Study.
Response: City of Ottawa, City of Gatineau,
STO, MTO, MTQ and the NCC are frequently involved in joint transportation
planning studies. This coordination is
on going. Staff appreciates the
importance of a coordinated effort while also respecting the autonomy between
our different cities.
Many people commented that they want an attractive and well-designed transit system with comfortable and accessible transit stations that are well integrated with development. Personal security and safety are also concerns. The idea of consolidating express routes and expanding feeder-line-haul service is acceptable if transfers are convenient, quick, reliable and comfortable (enclosed heated shelters).
Response: Station features and integration will be addressed during the design stage of each approved project. The City of Ottawa Urban Design Guideline and the Transit-Oriented Development Guidelines provide very good direction for urban design. The City’s Transit Service Policies identify standards for quick and reliable service.
Many people stated that Option 4 would have the most positive environmental and human health impacts. Greenhouse gas emissions were a major concern for many people from both a natural environment and human health perspective. People suggested that a transit tunnel that is well integrated with adjacent developments would improve the downtown environment, particularly during the winter months.
Response: Opportunities to integrate with development will continue to be
investigated through out all planning phases of each project.
Several people noted mobility and accessibility concerns associated with new transit stations and a downtown transit tunnel. Other people commented that improvements to our transit system are a priority as a way to improve mobility for people that do not drive (i.e. aging population, students, etc) and that transit improvements, particularly an LRT system, would help to improve Ottawa’s perception as a great world-class national capital city.
Response:
Mobility and accessibility will continue to be major considerations in the
planning and design phases of each project.
All transit stations will be wheelchair accessible and will include
elevators, as provincially mandated.
Economic
and Financial Implications
Many people mentioned that they support Option 4 because it has
the lowest operational costs and the greatest potential for land value uplift
and attracting new development. Several
people suggested that additional funding is required from senior levels of
government. Some people, including the
Ontario Ministry of Transportation (MTO) and the Ontario Ministry of Public
Infrastructure Renewal (PIR), recommend a more detailed analysis of the costs
and benefits. Both MTO and PIR also
recommend additional short-term transit investments to address immediate
transit challenges. People stated that operational costs are an important
consideration as operational costs are mainly funded locally through fares and
taxes. Increasing future fuel costs
associated with a bus-based system was also a noted concern.
Response:
Costs (capital and operating) will be refined as each project advances
forward from strategic planning to detailed planning (and environmental
assessments), design, and implementation phases. Cost-benefit analyses for each project will be undertaken as this
is typically a condition of funding from senior levels of government.
Technology Choice
Most people said they prefer electric LRT technology rather than hybrid electric-diesel or hydrogen, as it is perceived as a more sustainable, non-fossil fuel approach. A few people suggested that a subway or an elevated monorail system should be considered.
Response:
Environmental impacts associated with various technologies are part of the
evaluation criteria for assessing the different network options. An elevated solution was not recommended due
to the major aesthetic and physical impacts as detailed in the Document 3 and
the RMOC Central Area Transitway Grade-Separation Feasibility Study
(1988). An LRT system provides
sufficient capacity for the projected transit demand volumes to year 2031 and
also provides more service flexibility than a subway.
Construction and Phasing Implementation
People commented about disruptions to transit service during the construction period and are concerned about reduced transit ridership while the transit infrastructure is being built. Some people questioned the need to twin the tunnel under Dows Lake and the impacts on ridership this would have during the construction period.
Response:
There will always be disruption to transit service and general traffic
whenever major transportation projects are constructed. A comprehensive plan will be developed to
mitigate as much of the negative effects as possible. This work will be undertaken closer to the timing of project
implementation.
Ridership
Several people suggested that ridership should be the primary criterion for evaluating the four transit options, including the implementation-phasing plan of the preferred option. People mentioned that Option 4 would lead to the highest ridership due to its reliability and attractiveness.
Response: Ridership is a key evaluation criterion in assessing the various network options.
The City of Ottawa engaged a Peer Review Panel of respected professionals with decades of transit and urban planning experience to carry out the technical review of the proposed primary rapid transit network.
The Panel examined the transit network in place today and that proposed by the TMP study team in terms of their effectiveness in serving Ottawa’s existing and future travel demand. The Panel assessed the reasonableness of the study’s assumptions, methodologies, findings and conclusions pertaining to corridor locations, technology and estimated cost including the proposed downtown transit options.
The Panel’s report is included as Document 4. Key comments/recommendations made by the Panel with respect to the primary rapid transit network include:
· The 30 per cent peak hour modal split target appears achievable in light of current 23 per cent transit mode split;
· Bus Rapid Transit (BRT) alone will not provide the all-day mobility and urban development that are needed for future success;
· Light Rail Transit (LRT) corridors should be limited to inside the Greenbelt area with Bus Rapid Transit connections to the designated outlying Town Centres;
· Significant concerns about reliability of transit surface operation as well as the visual and mobility barrier presented by transit vehicles and passenger volumes making downtown public environment less attractive;
· LRT should operate in a tunnel through downtown with a two-corridor LRT system that includes an east-west line from Blair Station to Baseline Station, and a north-south line from Bayview to the Ottawa International Airport;
· Rapid transit corridors should be fully segregated to the greatest extent possible (providing good travel time and reliability);
· The existing O-Train corridor should be converted to a double-track LRT, with the line extended south only to the airport;
· STO buses should operate on-street in downtown Ottawa if possible into the future;
· No Transitway development beyond the Kanata, Barrhaven, and Orleans Town Centres;
· Transit investment should be contained within the current urban boundary and that only basic mobility (e.g. Para Transpo) should be provided beyond;
· Commuter rail network in the Ottawa region and beyond is not justified through 2031;
· Ottawa’s Greenbelt is a major asset and it should always be a permanent defining feature of the City as Canada’s Capital;
· The projection of 80 per cent of population growth and 58 per cent of employment growth to 2031 to occur outside the Greenbelt is a major concern – should focus population growth inside the Greenbelt to achieve a more efficient transit system;
· Aggressive land use and growth pattern are required to complement the massive transit investment program that is envisaged for Ottawa.
Based on the technical evaluation of the different core network options and feedback from the public as well as advice from the Peer Review Panel, it is recommended that Option 4 be selected as the preferred long-term core rapid transit network option. While the long term capital cost of this option is the most expensive, it provides a number of major benefits to the City including:
· The lowest annual operating costs;
· The highest annual ridership;
· The lowest negative impact on the environment as a result of the lowest greenhouse gas emissions and the least amount of winter salt contamination;
· The best overall quality of rapid transit service over the entire city;
· The best overall image of the city as a world capital including a direct and attractive rail connection from the airport to downtown and the parliament precinct for visiting tourists and world delegations; and
· The highest quality of transit service to key city destinations.
This recommendation is consistent with the Peer Review Panel recommendations with respect to the primary rapid transit work. The only exception is that the Peer Review is recommending terminating the North-South LRT at the airport with no further extension to Riverside South. Staff recommendation is to extend the line to Bowesville to connect to the preferred location for a rail maintenance facility.
The TMP Update will continue with further transit planning matters upon Council’s approval of the primary rapid transit network. These next activities include developing:
These are shown as grey links on the various network options. They are intended to link the primary corridors, enhance transit service coverage, and provide flexibility and choice for transit users. Potential secondary corridors to be examined are Carling, Rideau/Montreal, Baseline, Hospital, OCR rail and VIA rail corridors. Results of the analysis will be subject to public review in early Fall 2008.
Following the approval of the primary rapid transit network in May 2008 and the identification of the secondary corridors, a priority implementation plan to year 2031 will be developed in order to move forward with the transit implementation program in a staged approach. Developing the implementation plan will consider the following:
· Ridership (corridor demand, easing downtown transit congestion, enhance level of service for existing riders and attracting new riders);
· Status of the planning work;
· Difficulty of construction, potential complexity of design, uncertainty of location;
· Logical sequencing – e.g. need to connect to a maintenance facility;
· Staging flexibility (possible interim solutions);
· Minimize service disruption during construction;
· Support smart growth objectives of intensification and redevelopment.
This study will be undertaken concurrently with the TMP. The consultant selection process is underway. It is expected that the study will start in late Spring. The Study will be undertaken in accordance with the new accelerated Environmental Assessment Process for Public Transit Projects (expected to be in place by June 2008). With the likelihood of requirements for federal permits and property, and with the City pursuing federal funding, the Study will also have to comply with the requirements of the Canadian Environmental Assessment Act (CEAA). The Study will be using the technical work completed to date for the TMP which confirmed an LRT tunnel as the preferred solution.
As the City develops its rapid transit network, a commitment to complementary land use and Transportation Demand Management (TDM) policies will be made, including:
· Identify density targets for areas adjacent to rapid transit stations, especially at mixed-use centers;
· Ensure that type of development at rapid transit stations is transit supportive;
· Increase the overall accessibility of the rapid transit station;
· Revisiting the Zoning By-law to ensure that intensification targets can be met and “up” zone if necessary to facilitate intensification;
· TDM measures to change behaviour and promote transit as a more sustainable mode of travel;
· Fare policy to help spread transit peak demand to minimize capital and operating costs.
· Assess road infrastructure needs
· Assess other modes (cycling, pedestrian) and their infrastructure requirements
· Identify budgetary needs for infrastructure and programs for all modes
· Identify project priorities for all modes
· Develop implementation plan
· Update TMP policies
· Consult with public and agencies in late September/early October
· Prepare draft TMP for tabling in November 2008 to coincide with the tabling of the draft Official Plan
The TMP consultation objectives have been to engage, in a meaningful way, a broad range of citizens and stakeholders in a dialogue around Ottawa’s long-term transportation planning.
Towards this effort, the consultation program has consisted of two main phases, as summarized in Document 2 and in Chapter 8 of Document 3.
Phase 1 took place throughout September to December 2007 and focussed on informing citizens in new and unique ways about various transportation related challenges and opportunities facing Ottawa. Within this context, the TMP Vision and Guiding Principles were reviewed and key information was collected with respect to the development of a preferred rapid transit network. Document 2 further summarizes the consultation process and outcomes from Phase 1.
Phase II consultations began March 3 and concluded March 31, 2008 as an exercise to inform the public about the four Downtown Rapid Transit Network Options and their implications on the overall transportation systems. A number of activities were undertaken to provide flexible and convenient opportunities for the public and agencies to provide comments to the City, as summarized below and further outlined in Chapter 8 of Document 3.
· Four Open Houses held at various locations throughout the City;
· Registered Discussion Groups as part of each Open House;
· Stakeholder Focus Group Sessions;
· City Advisory Committee Briefings;
· Online Materials and Consultations;
· Internal and External Agency Group Meetings;
· Mayor’s Streeter Survey.
Open
Houses
Four Public Open Houses were held during the first week of March in various locations across the city. In total, approximately 400 individuals attended the Open Houses and 156 comment sheets were completed and submitted at the events.
Registered
Discussion Groups
Registered Discussion Groups were conducted between 7:00 and 8:00 p.m. at each of the Public Open Houses. In total, 152 people participated in the discussion groups. The format involved up to eight participants seated at each table and supplied with information and maps of the four Downtown Rapid Transit Networks. Technical facilitators led the discussions at each table and all comments and input was collected on flips charts.
Stakeholder
Focus Group Sessions
Three Stakeholder Focus Group Sessions were held at City Hall during the first week of March 2008. Participants were organized into an Industry, Economic or Downtown group according to their various interests and areas of expertise. Each session included a presentation of the four transit options followed by an open discussion.
City
Advisory Committee Briefings
A number of the City of Ottawa Advisory Committees with an interest in transit and transportation were invited to participate in a briefing on the Downtown Rapid Transit Network Options. Several Advisory Committee members also participated in the Public Open Houses and Registered Discussion Groups.
Online
Materials and Consultations
The Beyond Ottawa 20/20 website (www.ottawa.ca/beyondottawa2020) has been extensively used to promote the TMP update process, including all Public Open House materials, online feedback forms and additional background information. All information has been provided in both official languages. In total, 631 written submissions were received in the month of March via the online comment form, fax, mail and email.
Internal
and External Agency Group Meetings
The City hosted two meetings with various agencies during the first week of March 2008 that included representatives from different levels of governments, crown corporations and private interest groups. The primary objective of the agency meetings was to provide information about the four Downtown Rapid Transit Network Options. Each meeting included a presentation and was followed by an open discussion.
Mayor’s
Streeter Survey
A Streeter Survey was conducted with the Mayor during the week of March 17, 2008 to provide a brief snapshot of the public's awareness and opinions of the City's long-term transit plans. The locations were selected to capture a diverse set of opinions, mostly from transit users. The survey team approached people at transit stops, bus stops, park and ride lots, and sidewalks and asked a series of brief questions. In total, 401 surveys were completed.
Following the tabling of the recommended rapid transit network on 16 April 2008, further consultation will be undertaken to seek public feedback on the recommendation. Events include:
· Six city-wide ward consultations between April 21 and May 6, inclusive
· Online interactive consultations through OttawaTalks
· Online Feedback Form
Inputs received though these consultation events will be presented to Joint Transportation and Transit Committee on May 21.
The capital cost estimates included in the report are preliminary and will be subject to detailed planning and EA work. The costs do not include the secondary transit corridors – still to be developed and costed. It does not include costs for STO solutions, inflation, property acquisition and additional cost for unforeseen circumstances.
For the purpose of estimating the capital and operating costs for transit vehicles, LRT vehicles and standard propulsion buses are assumed. These estimates will be subject to detailed analysis of system specifications, LRT and bus standards and operating strategies.
This proposal continues a significant investment in transit infrastructure, which will require major funding commitments by all levels of government for the program to be implemented. Recent discussions with the federal and provincial governments indicate serious interest in rapid transit projects in Ottawa. Staff will continue to negotiate for funding from both levels of governments.
Currently the City’s Long Range Financial Plan identified transit capital growth needs of $2.1B within the next 10-year period (2007-2016). This amount assumed a minimum of 1/3 funding each from Ontario and Canada. Besides provincial and federal grants, potential funding sources could include: development charges, gas taxes, transit reserve fund, and debt.
Document 1. Transportation Master Plan Updated Vision and Planning Principles
Document 2. Summary of Phase 1 Consultation on Transportation Vision and Planning Principles (September – December 2007), January 2008 (PACE)
Document 4. Peer Review Panel Report, April 2008.
Special Attachment: Recommended Vision for the Downtown Rapid Transit Network
Vision recommandée pour le réseau de
transport en commun rapide au centre-ville
The Planning, Transit and the Environment Department will continue with the transit-planning component of the TMP Update – specifically to assess the complementing secondary transit corridors and to develop an implementation/priority plan. The public will be consulted in early Fall 2008 on these new findings. Concurrently, the TMP Update team will also look at the needs of other modes that make up the City’s transportation network – this too will be available for public review and comment in the Fall.
TRANSPORTATION MASTER
PLAN UPDATED VISION AND
PLANNING PRINCIPLES DOCUMENT
1
|
In 2031, Ottawa’s transportation
system will enhance our quality of life by supporting
social, environmental and economic sustainability in an accountable and
responsive manner. |
Part A: Support for social, environmental and economic sustainability
1.
Reduce auto dependence
a) Give priority to public
transit in meeting future growth in travel demand
b) Make walking and cycling more
attractive than driving for short trips
c) Motivate sustainable travel
choices through education, promotion, incentives and disincentives
d) Encourage shorter trips and
travel alternatives like telework
2.
Meet mobility needs
a) Provide a continuous,
integrated system of multimodal facilities and services
b) Aim to provide an acceptable
standard of service for each mode of travel
c) Give priority to public
transit, walking and cycling over cars when conflicts arise
d) Provide barrier‑free
transportation facilities and services
3.
Integrate transportation and
land use
a) Build walkable communities
b) Provide rapid transit and other
quality transit services to community cores and employment areas
c) Foster transit-oriented
development in transit nodes and corridors
d) Support intensification where
transit, walking and cycling can be made most attractive
e) Foster a vibrant downtown by
improving transit, walking and cycling access
f) Recognize the distinct
transportation needs of rural communities
4.
Protect public health and
safety
a) Give priority to safety and
security when planning, designing and operating transportation systems
b) Promote safe walking, cycling
and driving through education, engineering and enforcement
c) Support active living by
promoting walking, cycling and transit for daily travel
d) Minimize the impacts of truck
and automobile traffic on sensitive communities
e) Minimize air pollution from
transportation sources
5.
Protect the environment
a) Minimize the need for new
infrastructure
b) Minimize transportation
energy use, greenhouse gas emissions and other impacts on air, water and land
c) Maximize greening within
transportation rights‑of‑way
6. Enhance the economy
a)
Maximize
access to businesses and institutions by employees, clients and visitors
b)
Support
efficient freight movement to, from and within the city
Part
B: Accountability and responsiveness
7. Deliver cost-effective services
a) Before adding infrastructure
make the best possible use of existing facilities
b) Integrate the consideration
of life‑cycle capital and operating costs into decision-making processes
c) Support appropriate private
sector roles in infrastructure and service delivery
8.Measure performance
a)
Identify
transportation performance objectives and indicators
b)
Regularly
measure and evaluate performance
c)
Integrate
performance evaluation results by adapting transportation plans and strategies
9.
Protect the public interest
a) Encourage public input and
informed decision‑making by reporting on transportation activities and
results and providing opportunities for dialogue
b) Consult with the public when
planning budgets, programs and projects
10.
Provide adequate and
equitable funding
a)
Seek
and/or establish funding sources that are stable and predictable
b)
Strengthen
the "user pay" component of transportation system funding
11.
Cooperate with other
governments
a) Liaise with provincial and
federal governments to align plans and policies, and to attract financial,
legislative and regulatory assistance
b)
Work
with the National Capital Commission, Ontario Ministry of Transportation, City
of Gatineau and other adjacent municipalities to develop balanced solutions
12. Lead by example
a) Minimize energy use and
environmental impacts of City transportation facilities, fleets, operations and
services
b) Foster walking, cycling and
transit use by employees and visitors to City facilities
c) Forge constructive
partnerships with the private sector, institutions and community organizations
SUMMARY OF PHASE 1
CONSULTATION ON TRANSPORTATION
VISION AND PLANNING
PRINCIPLES DOCUMENT 2
The mandate of the Transportation Master Plan (TMP) Study Consultation Strategy is to engage, in a meaningful way, a broad range of citizens and stakeholders in Ottawa. The programs completed between September and December 2007 to assist in achieving this objective have included:
· Educational Background ‘White Papers’;
·
Online
Consultation Opportunities (Ottawa Talks);
· Streeter Surveys;
· Stakeholder-based Focus Groups;
· The City Café event;
· A Transportation Master Plan Interactive Workshop
Over the course of the first phase of consultations members of the public have contributed a significant amount of input. Some of the overall themes can be summarized as follows:
· Need a transit system that is efficient, convenient, reliable and comfortable.
· Residents of Ottawa continue to support placing emphasis on sustainable modes of transportation (walking, cycling, carpooling and transit) when creating our future transportation infrastructure, including the need to support access to multi-modal transportation systems (e.g. Park & Rides, cycling and pedestrian access to transit, etc.).
· The use of more sustainable modes of travel through incentives, education, and other positive means of stimulating behavioural change is encouraged. This carrot approach was preferred to ‘stick’ methods to discourage or change behaviour, such as through tolls and higher parking fees.
· Many people felt that the existing Transportation Master Plan, with its accompanying planning principles, remains valid although some aspects should be modified. New elements need to be added to reflect an increased emphasis on the environment, performance measurement, implementation timelines, affordability and the importance of links to land use planning.
· There was an expressed desire to see the Transportation Master Plan’s planning principles reference unique Ottawa-specific issues such as: heavy truck problems downtown; the City’s urban-rural balance; and, the need to better co-ordinate transportation planning with Gatineau.
· Interest in the idea of a tunnel downtown is strong; some members of the public believe that we need the tunnel immediately while others felt that due to costs the project should be deferred until other transportation concerns are resolved.
· Only a few citizens identified costs as an important factor in the decision-making process.
·
Feeder-line-haul service is acceptable if transfers are
convenient, quick, reliable and
comfortable (enclosed heated shelters)
·
The big message heard was that the general public want
action on resolving Ottawa transportation problems.
What has happened so far?
In the fall of 2007, during Phase I of consultation, the goal was to reach out to the many voices around Ottawa in new and unique ways:
White Papers and Beyond
Ottawa 20/20 (September 2007):
In September, the City launched its Beyond Ottawa 20/20 website, which included nine White Papers that highlighted a variety of different topics specific to growth management issues in Ottawa. Although two of the nine White Papers specifically outline transportation and transit issues, the nine papers together illustrate the synergies required to achieve a balanced growth management approach. The White Papers were also distributed to all City public libraries and the public was encouraged to review them and to provide comments, including any issues relevant to updating the Transportation Master Plan.
Ottawa Talks (October to
December 2007):
In October, the Ottawa Talks
portion of the Beyond Ottawa 20/20 website was launched to allow citizens to
participate in real-time online dialogue concerning the issues and content of
the nine White Papers. This portion of the website was available to citizens 24
hours a day for a total of two months.
The site was visited by over 51,000 people during the two-month period
and 769 dialogue submissions were made, of which, 306 pertained to the
Transportation and Transit White Papers.
Key Trends
Public transit issues overwhelmingly dominated
the discussions and topics raised within the Ottawa Talks forum. Rapid transit
clearly constitutes the primary interest with the issues that generated the
most discussion related to LRT or replacing BRT with LRT; downtown transit
alternatives including a transit tunnel; and implementing a line-haul feeder
route system. The interest outside of
rapid transit can largely be categorised around making sustainable transportation modes
more competitive;
environmental sustainability; and financing transportation infrastructure.
Streeter Surveys (October
2007):
In October, ‘Streeter Surveys’ were conducted throughout the city allowing citizens to provide opinions on transit and transportation in a short face-to-face survey. The surveys were conducted at: transit stations; pedestrian walkways; shopping malls; office buildings; Park & Ride lots; and universities. Over 900 people participated.
Overview
The
‘Streeter Surveys’ involved a series of brief “intercept” interviews with
residents randomly drawn from various areas within the City. Participants were interviewed face-to-face
in public areas such as sidewalks and parking lots. An emphasis was placed on proactively reaching out to a diverse
group of citizens that might not normally be involved in traditional
consultation activities. The interviews
were qualitative in nature, allowing for a conversational interaction between
interviewer and respondent.
The goal was to achieve 300 completed surveys
throughout the duration of the ‘Streeter Survey’ schedule, conducted between
Wednesday, October 24th and Saturday, October 27th. Distribution and collection
of the survey also occurred at the Rural Settlement Workshop on Saturday,
November 3rd. Interviews were conducted
in either English or French, so that residents had an equal chance of
participating.
A notice was issued via the City’s media list inviting
coverage at a specific location. This
media event was well attended and resulted in positive radio, television and
print coverage.
Participation in the survey far exceeded expectations, as 916 completed surveys were collected from fourteen locations throughout the city. The exercise provided a valuable snapshot of the general public’s mindset, and allowed for quick collection of data and collating of results. The data will be used to contribute to the City’s update of the TMP Vision and supporting planning principles.
Key Trends
Once the Streeter Surveys were completed, the surveys were reviewed, collated and analyzed to determine key trends. The following is a brief summary of what we heard.
·
Fifty-seven percent of all respondents indicated
that they felt their primary method of transportation was ‘good’. Of those that
use transit as their primary method, 86 per cent positively rated that method
as ‘good’ or ‘very good’, while 14 per cent rated it as ‘poor’ or ‘very poor’.
Of those respondents that use private vehicles as their primary method of
travel, 82 per cent rated their method positively as ‘good’ or ‘very good’,
while 16 per cent rated it as ‘poor’ or ‘very poor’. Walking and cycling received a ‘good’ and ‘very good’ rating 95
per cent and 89 per cent of the time (respectively), from those that cited it
as their primary mode of transportation.
·
When asked to rank where the City should
spend its money, the largest proportion of respondents (342) indicated that
‘Improving Transit’ should be the City’s highest spending priority. This was
followed closely by 262 respondents wanting to see the City’s top spending
priority to go towards ‘Decreasing Road Congestion’. ‘Road Maintenance’
received a top priority ranking from 171 respondents, ‘Cycling’ from 55, and
‘Walking Improvements’ from 40.
Focus Groups (October and
November 2007):
Nine working focus groups were held throughout October and November. In each focus group, teams of citizens collaborated to come up with ideas and input on the various opportunities and challenges that the City faces in creating the transportation plan for the future. A total of 70 participants representing members of the public, community representatives, and industry and business groups, attended the focus groups which were held across the city between October 29th and November 13th.
Overview
The primary objective of the focus groups was to gain insight from participants on the existing Transportation Master Plan Vision (2003) and to gather responses to the various discussion topics outlined in the Transportation and Transit White Papers.
Focus groups provide the opportunity for citizens and stakeholders to engage in in-depth discussions surrounding particular topics. They are an effective participatory form of public engagement that allows for individuals and organizations to discuss issues in an interactive, face-to-face setting.
Participants at the focus groups were selected from two categories. The first included residents from the five geographical regions of the city (Central, West, East, South, and Rural). The second category was comprised of the various ‘voices’ that impact transportation decision-making at the city (Industry, Economic, Downtown, and Community).
Attendance at each focus group was drawn from an invitation list that was representative of the Ottawa population and geography. Existing stakeholder lists were supplemented by additional research to create a broad-based pool of potential candidates, consisting of a mix of individuals and organizations that had previously been involved in transportation-related consultation and those that had not.
Additional attendees were drawn from the City’s Advisory Committees as well as candidates that were recommended by City Councillor offices.
Upon confirmed attendance, a ‘homework’ exercise and copies of the two transportation-related White Papers were distributed to each participant via email.
The focus group sessions were designed to last two hours and were facilitated by a member of the PACE Consulting Team. A scribe and a member of the City of Ottawa staff were also present as observers.
The focus groups included a brief introduction to the TMP project, an open discussion surrounding the 2003 TMP Vision, team working sessions on the Transportation and Transit White Papers, open feedback opportunities on emerging ideas, and an opportunity for creative discussion around the topic of financing for transportation infrastructure. The focus group topics were developed based on the two Transportation White Papers.
Key Trends
Once the nine focus groups were completed, discussion notes were reviewed, collated and analyzed to determine key trends, areas of consensus, and areas of diverging views. The following is a brief summary of what we heard.
· The City needs to improve transit service to make it more attractive to the car user.
· Many agreed that the City should set an example of environmental stewardship but few felt that official targets would be effective.
· Several participants commented that the City is constantly having to react to growing subdivisions and instead should only develop subdivisions that have an extensive transit plan incorporated into them.
·
There was varied support for the tunnel but generally
more participants believed there was an immediate need for a tunnel rather than
deferring it.
· Ideas emerged around the possibility of making transit transfer points areas of interest by including services, retail, grocery, libraries, etc.
City Café (November 2007):
A City Café was held at Lansdowne Park on November 24th to engage residents in the broader Official Plan review process, including the Transportation Master Plan update. Councillor Peter Hume provided the opening address followed by keynote speaker Rod Bryden. Approximately 200 people participated, by breaking into small groups of five or less to discuss the growth management challenges facing the City of Ottawa.
Interactive
Technology-Assisted Event (December 2007):
A unique technology assisted event was conducted on December 4th to outline to the public a synopsis of information gathered throughout the Phase I consultation period. There was also an opportunity for all attendees to utilize touch-pad technology to provide input on transportation and transit questions. In total, 101 individuals registered for the December 4th event and 80 of those registrants attended the Interactive Workshop.
Overview
The Interactive Workshop was the concluding event of the Phase I consultation program. It was structured to allow the City to provide an update to citizens on issues and ideas that emerged through the various Phase I activities and to ask questions on key issues that required additional input. A total of fifteen questions were asked, inspired by the Transportation and Transit White Papers.
The primary objective of the event was to provide participants with a summary of the main points heard through the previous consultation events and to formulate a consensus by using a ‘touch pad’ voting mechanism. By pairing an in-depth PowerPoint presentation with the ‘touch pad’ technology, participants voted on various transportation related priorities and issues.
The use of the touch pad voting system was a new and innovative consultation method for the City, allowing for a participatory form of public engagement that permitted individuals to automatically provide input to questions posed. It went an additional step to allow citizens to immediately view the collective opinions of the other participants that attended alongside them.
The Interactive Workshop was divided into three sections: 1) Staff and Councillor welcome; 2) Staff presentation on the TMP review process and TMP Vision; and 3) the Technology-Assisted Interactive Session.
The first section included a welcome by Nancy Schepers, Deputy City Manager, Planning, Transit and the Environment; Councillor Maria McRae, Chair of the Transportation Committee; and Councillor Alex Cullen, Chair of the Transit Committee. Their remarks provided insight into the direction of Council and staff to conduct a thorough review of the 2003 Transportation Master Plan as a component of the 2008 Official Plan review. They also delivered a brief introduction to the TMP project, the Beyond Ottawa 20/20 “Ottawa Talks” website, the Streeter Survey, Focus Group consultations, and the City Café.
The second section consisted of a thorough review of the TMP Update by Steven Boyle, Planner III, Transportation - Strategic Planning Unit, Planning Branch. Mr. Boyle provided insight into the key objectives of the TMP Review Consultation Strategy, results from the various consultation activities, and a summary of the input collected on the 2003 Vision.
The final component of the evening was an interactive presentation that used touch pad technology provided by Duocom Audio-Visual Systems. Monique Stone, Senior Consultant at PACE Public Affairs & Community Engagement, facilitated the interactive session and provided context for each of the questions posed to the audience.
The technology also offered the ability to add ‘impromptu’ questions at the end of the session and participants took this opportunity to suggest four additional questions. These questions included location, age and gender of participants as well as a transportation related question.
Overall, attendees provided positive comments on the structure and focus of the interactive workshop. Of the 80 people in the audience, 77 consistently responded to the questions.
Key Trends
· 87 per cent of respondents believed that the City should proactively encourage intensification in areas where walking, cycling and transit can be made most attractive.
· 85 per cent of respondents believed that the City should consolidate express routes and expand feeder-line-haul service to improve transit speed and reliability through the downtown.
· 74 per cent of respondents believed that the City should re-allocate significantly greater resources to transportation system management and transportation demand management.
· 71 per cent of respondents believed that the City should plan roads to meet the average demand in the busiest three-hour period.
· 43 per cent of respondents believed that we need to study the downtown transit tunnel option fully and examine potential alternatives, while 38 per cent believed we need a tunnel now.
· 51 per cent of respondents believed that the City should set a strict target for reducing GHG emissions from transportation, and plan to do whatever is necessary to achieve that goal.
PEER REVIEW PANEL REPORT, APRIL 2008 DOCUMENT 4
Peer Review Panel Report,
April 2008

Peer Review Report
Rapid Transit Plan Component
Ottawa Transportation Master
Plan Update
1
Introduction
and Scope of Services
Background
The City of Ottawa as part of its review of its
Official Plan (OP), is updating its Transportation Master Plan (TMP). A consulting team comprised of McCormick
Rankin/Delcan has been retained by the City to undertake the update including
the development of a rapid transit plan.
The work will provide the basis for the transit component of the 2008
TMP.
In conjunction with the TMP update, the City
requested a peer review of the rapid transit plan. This report summarizes the results of the peer review, conducted
in the City of Ottawa February 11-15, 2008.
The Peer
Review Panel
The Peer Review Panel comprised five transit and
land use planning experts with experience in Canada, the U.S. and the United
Kingdom. A brief description of the
panel is included below:
§
Paul Bedford (Principal,
Paul Bedford & Associates, Toronto, Ontario). Former Chief Planner for the
City of Toronto where he led the development and adoption of the new city-wide
Official Plan for the amalgamated City of Toronto. He is currently the only
non-elected municipal member of the Greater Toronto Transportation Authority
Board of Directors.
§
Russell Chisholm (President, Transportation
Management and Design, Inc., San Diego, California). Founder and President of TMD, a U.S. firm that specializes in
urban rail and bus transit design, implementation and operation. Formerly held senior management positions
with Dallas, St. Louis, and Riyadh transit systems.
§
Alan Danaher (Senior
Principal, Kittelson & Associates, Orlando, Florida). Senior Principal with Kittelson &
Associates, a U.S. transportation planning and traffic engineering firm, where
he has led numerous bus and rail planning and operations studies. A leading authority on bus rapid transit
(BRT) in the U.S.
§
Alan Jones (Associate, Steer Davies
Gleave, London, UK). Associate with
Steer Davies Gleave – an international firm, providing a range of services
including transit planning. He has extensive
experience in the development and delivery of a wide range of urban transit
technologies including rail, light rail transit, bus rapid transit, bus,
metros, and automated people-mover systems.
§
Glen Leicester (Principal,
Shirocca Consulting, Vancouver, BC).
Former Vice-President of Planning for TransLink (the Greater Vancouver
Transportation Authority) where he guided the planning of Metro Vancouver’s
transport system with its highly
integrated multi-modal network of rapid transit modes.
Scope of Services
The
Peer Review Panel examined the current rapid transit network in Ottawa and that
proposed by the consulting team in their report “Development of a Downtown
Transit Solution and Network Implications, First Draft February 6, 2008”. Specifically the Panel was asked to comment
on the work of the consultants including:
1.
The
proposed transit modal split target and the forecasted transit demand
2.
The
proposed transit corridor locations (including the appropriateness of using
existing/ abandoned rail corridors)
3.
The
proposed technology for the different components of the network
4.
The
various downtown transit options and the proposed recommended solution
5.
The
proposed operating strategy (e.g. feeder-line haul versus direct service with
no transfer, etc)
6.
The
recommendations regarding the conversion of the Transitway system to LRT
7.
The
capital and operating cost assumptions for different technologies
8.
The
appropriateness of proposed facility types (e.g. exclusive and grade separated
versus transit lanes on arterial roads)
9.
The
appropriateness of extending the transit system beyond the City’s urban
boundary
10. The response to the Mayor’s
Task Force recommendations
In addition, the panel was
asked after the completion of the draft report to comment on rail technology
for Ottawa. Specifically the panel was
asked if it could see Ottawa needing a subway in the next couple of decades or
even further out? Should Ottawa have different rail technologies for the
Baseline to Blair section than the one for the other corridors (north-south
line and Carling, Montreal). A response
to the rail technology question is included in Appendix 1.
2 Existing
Transit System – An Overview
Background
The City of Ottawa and its neighbour, the City of
Gatineau, combine to make up Canada’s fourth largest urban region with a
population of more than 1.15 million.
The City of Ottawa is the nation’s capital and has a population of
870,000 as well as 520,000 jobs. Public
transit service is provided by a City Transit Services Branch under the name OC
Transpo, while the Societe de Transport de l’Outaouais (STO) provides bus
service in Gatineau. Both operate cross
river routes between the cities.
Planning
Framework
Ottawa 20/20 is an overarching growth management
strategy that is intended to prepare the City for growth over the next two decades. The 2003 Official Plan (OP) is prepared
within the context of Ottawa 20/20 and establishes overall city development
policies; sets out the types and location of permitted land uses and identifies
major transportation and other infrastructure investments to support the land
use plan. The Transportation Master
Plan (TMP) supports the growth management strategy by setting out a transport
vision that includes focusing on transit, influencing travel demand, making
efficient use of resources and forging a community partnership. The TMP, adopted by Council in 2003, is
being updated by the City.
Land Use
The City of Ottawa is characterized by a strong
central downtown and generally lower density residential development. A unique feature is the presence of a
greenbelt that rings the city and separates the inner part from three outlying
urban centres to the east, south and west.
It is projected that over the next 25 years, 80% of the future
population growth will occur beyond the greenbelt while only 20% will occur
within the contiguous part of the city inside the greenbelt. Employment today is highly centralized
within the greenbelt accounting for 82% of the city’s total. Over the next 25 years, 42% of the future
employment will take place within the greenbelt and 58% will occur
outside. The strong growth in
population in the outer part of the urban area coupled with continued growth in
employment within the greenbelt will increase overall travel demand, lengthening
trip times and distance, and putting pressure on transportation facilities
across the greenbelt.
Existing
Transit Provision
The City of Ottawa’s current transit system is
structured around the rapid transit network comprising 34 kms of segregated
busways and an eight km light rail line.
Supporting the rapid transit facilities is an extensive network of local
and express bus services providing service to within 400 metres of 95% of the
city’s urban population during peak periods.
Ridership in 2006 reached 92 million and with more than 120 rides per
capita, Ottawa is rated among the highest in North America. STO in neighbouring Gatineau provides an
extensive network of local buses as well as commuter services into downtown
Ottawa. The City of Gatineau is
developing a bus-based rapid transit system called Rapibus.
The bus-based rapid transit system has served the
City of Ottawa very well over the past two decades. Local buses circulate
within the low density outer urban neighbourhoods and then travel the busways
providing fast, one-seat rides for commuters into central Ottawa. Frequent and fast rapid bus routes provide a
high level of service on the busways and have resulted in development around
key stations, although the development appears in many cases to be less well
integrated without easy station assess.
Outside the Greenbelt, station development is much less intense with
predominantly suburban retail and residential development.
Key Issues
§
Within
downtown Ottawa, the rapid transit buses operate on a one-way couplet with bus lanes. The volume of buses during the weekday p.m.
peak period is nearing the maximum that can be accommodated.
§
The strong
focus on peak period downtown trips results in an under utilization of the
infrastructure at other time periods of day and in the reverse peak direction.
§
The bus rapid
transit system is labour intensive with high operating costs compared to light
rail systems. This is exacerbated by the high peaking of the system.
Review of
Past Studies and Summary of Proposals
The Panel reviewed a number of studies and
summarized the proposals.
|
Study |
Date |
Proposals |
|
Rapid Transit Expansion
Study (RTES) |
February 2003 |
§
Proposed
a major expansion of the rapid transit system including LRT §
Identified
expansion of LRT into downtown Ottawa and to Limebank (Riverside South) as
the highest priority project §
Proposed
at grade LRT operation in downtown
Ottawa |
|
Official Plan (OP) |
May 2003 |
§
Emphasis
on compact, integrated land uses to encourage shift from auto travel to
walking, cycling and transit §
90%
of growth to be accommodated in areas designated within urban boundary §
Large
undeveloped lands within urban boundary serve as locations for new communities,
providing for mix of housing types and better balance of jobs and housing §
Development
of mixed use centres outside central area §
Central
area will be enhanced by providing for a range of uses, quality community
design and strengthening residential uses |
|
Transportation Master
Plan (TMP) |
September 2003 |
§
Proposed
a transit modal split target of 30% in p.m. peak hour §
Major
expansion of the rapid transit network including 100 kms of new electric rail
and 42 kms of busway extensions §
Expansion
of bus and rail fleets §
Development
of a comprehensive transportation demand management strategy |
|
Moving Ottawa – Mayor’s
Task Force on Transportation |
June 2007 |
§
Expansion
of rapid transit by use of existing rail corridors to build an integrated, region-wide,
light rail system §
East-west
bored tunnel under downtown §
Converting
the Government Conference Centre into a downtown rail hub (Union Station) §
Building
rail rapid transit to connect Gatineau and Ottawa |
3 Response to the Scope of Services
Questions
Introduction
This section of the
report addresses the Peer Review Panel’s response to the ten questions posed in
the Scope of Services for Peer Review Services. This response is based on the results of the panel review of all
relevant documents and information provided by City staff the week of February
11, 2008, a field review of the existing transit system and development
conditions around the transit system, and discussion amongst panel members.
An over-arching concern
noted by the Panel was the basis on which the latest transit proposals had been
developed. These appear to rely on long-term (2031) ridership forecasts for a
peak hour only. This approach leads to high cost solutions designed only to
address peak hour conditions. The Panel was also concerned at the lack of any
cost: benefit analysis or wider option evaluation being applied to test,
compare and appraise alternatives against clearly defined Transit Plan (and
wider Official Plan) aims, objectives and targets.
The detail of the Panel’s
five day discussions and suggestions have also been developed in the absence of
any appraisal tools. However, this is addressed in the section covering
Conclusions and Recommendations.
Question 1: Proposed
Transit Modal Split Target and Forecast Transit Demand
Response: The Panel strongly feels that transit system
improvements should be designed for a wider set of travel conditions than just
for the a.m. peak hour. Addressing
off-peak and overall daily transit modal split target in addition to peak hour
would be appropriate. The 30% peak hour
modal split goal appears achievable in light of the current 23% peak hour
transit share in Ottawa. However, this target appears to be driven by transit
supply conditions as opposed to transit demand reflecting changes in land use
and potential further densification patterns. With respect to the regional
travel demand model, there appears to be no distinction between BRT and LRT
ridership within corridors where similar service levels are provided, given
similar speeds are assumed. There is
also nothing in the model addressing particular comfort and convenience factors
for BRT vs. LRT. Modifications to the
travel demand model should be made to create more sensitivity in the
characteristics of these different premium transit modes. For such an analysis,
daily/weekly/annual ridership and revenue forecasts should be available for
each option, together with capital and operating costs to allow basic cost:
benefit calculations to inform the option choice process. Wider criteria
informing a more comprehensive appraisal would also be appropriate.
Question 2: Proposed
Transit Corridor Locations (including the appropriateness of using
existing/abandoned rail corridors)
Response: The Panel strongly feels that the transit
corridors should be limited to within the Greenbelt area, with connections to
the designated outlying Town Centres.
These transit corridors should be fully segregated to the extent
possible (providing good travel time and reliability), with transit needing to
have priority over traffic in highway corridors. With this approach, transitway corridors would not be developed
beyond the outlying town centres, such as the proposed Transitway extensions to
north Kanata, Stittsville, south of Barrhaven Town Centre, and east to
Trim/Millennium. In these corridors,
bus operations on-street would be more appropriate, with bus lanes and
intersection signal priority to the extent possible. At such time as these extended corridors developed or were
developing a linear pattern of higher density urban centres, then segregated
transit options could be considered.
Until such time, it is suggested that the rights-of-way be preserved.
Segregated
Transitway investment should be focused within the Greenbelt. The Carling Avenue and Rideau
Street/Montreal Road corridor would be appropriate for streetcar development,
to attract further development in the central portion of Ottawa south and east
of downtown. A BRT line on Baseline
Street connecting Baseline with Hurdman would also be appropriate. Both the Carling, Rideau/Montreal and
Baseline corridors should have segregated transit running way with at-grade
operation and signal priority at intersections. With respect to existing/abandoned rail corridors, the existing
O-Train corridor should be converted to a double-track LRT, with the line
extended south to the airport. The
existing Ottawa Central Railway east-west corridor could also be a BRT or rail
corridor in the future, but not developed until after the Carling,
Rideau/Montreal and Baseline corridors closer to downtown are developed. Abandoned rail corridors only work
effectively if you can cluster urban density development around key stations,
where there is a need for an integrated approach where land must be available
for development.
Question 3: Proposed
Technology for Different Network Components
Response: The Panel makes the following
recommendations with associate rationale in Table 1 for a particular technology
in each segment of the transit network:
Table 1 – Proposed Technology for Different Rapid
Transit Network Segments
|
Network
Segment |
Segment
Limits |
Appropriate
Technology |
Comments |
|
Central
Downtown |
Bayview
to Hurdman |
LRT
– OC Transpo in Tunnel LRT
or BRT - STO |
Tunnel
configuration for OC Transpo and
provision for STO needs further assessment |
|
West
Downtown |
Bayview
to Baseline |
LRT |
Intermediate
and terminal station development desired |
|
East
Downtown |
Hurdman
to Blair |
LRT |
Intermediate
and terminal station development desired |
|
South
Downtown |
Bayview
to Bowesville |
LRT
to airport BRT
to Bowesville |
Direct
service from airport to downtown desired; protect r-o-w to Bowesville |
|
South
Transitway |
Bowesville
to Barrhaven |
Segregated
BRT |
Barrhaven
served by SW Transitway, but protect r-o-w for South BRT |
|
West
Transitway |
SW
Transitway to Kanata |
Segregated
BRT |
To
Kanata Town Centre (Terry Fox) only.
Preserve r-o-w to Stittsville and North Kanata |
|
SW
Transitway |
Cambrian
to Baseline |
Segregated
BRT |
To
Barrhaven Town Centre only. Preserve
r-o-w for Cambrian |
|
SE
Transitway |
Greenboro
to Hurdman |
Segregated
BRT or LRT |
BRT
could be tied to Baseline BRT, LRT could provide east rail feeder to downtown
- this helping to balance LRT loads in tunnel |
|
East
Transitway |
Blair
to Trim/Millennium |
Segregated
BRT to Orleans, On-street BRT to Millennium |
To
Orleans Town Centre. Preserve r-o-w for potential Transitway to Trim and
Millennium |
Question
4: Various Downtown Transit Options and
Proposed Recommended Solution
Response: The Panel makes a later finding and recommendation
that the City adopt LRT for the basic urban line-haul network inside of the
Greenbelt with BRT feeder services connecting with the urban area outside. We don’t believe that BRT will provide the
all-day mobility and urban development that are needed for future success.
Surface
(OC Transpo)
Each of the three surface options [all bus,
all LRT, or bus/LRT] present issues with daily delivery of capacity. While we believe that vehicle capacity
issues can be addressed in theory[1],
we have significant concerns about the daily reliability of such a surface
operation, especially during winter months.
We have further concerns regarding the visual and mobility barrier
presented by such surface transit vehicle and passenger volumes making the
downtown public environment significantly less attractive.
Surface operation is an
interim solution at best; not recommended as a permanent solution.
The current situation can be enhanced in the
short-term at low cost to allow time for an underground tunnel option to be
more fully evaluated.
Tunnel
(OC Transpo)
Consequently, the panel believes that LRT s