Joint Meeting – Transportation Committee and
Transit Committee
Comité conjointe des transports et des services de transport en commun
and Council / et au Conseil
12 November 2008/le 12 novembre 2008
Submitted by/Soumis par : Nancy Schepers, Deputy City Manager/Directrice
municipale adjointe,
Infrastructure Services and
Community Sustainability / Service d'infrastructure et Viabilité des
collectivités
Contact Person/Personne ressource : Michael Murr, Manager
Strategic
Initiative and Business Planning/Initiative stratégique et planification
opérationnelle
(613)
580-2424 x 25195, Michael.Murr@ottawa.ca
That the Joint Transportation and
Transit Committee recommend Council:
1.
Approve the Baseline Station/Transitway
Functional Design Plans, as described in this report and as filed with the City
Clerk, to guide Rapid Transit Network and Centrepointe Town Centre (CTC)
planning and implementation including that for the City’s Archives/Library
Technical Services Facility and the Algonquin College Project;
2.
Approve the updated
CTC Concept Plan, attached as Document 1, as being consistent with the Baseline
Station/Transitway Functional Design Plans as set out in Recommendation 1; and
the development plans for the City’s Archives/Library Technical Services
Facility and the Algonquin College Project;
3.
Approve the
initiation of the environmental assessment for the long-term rapid transit
network from Baseline to Norice, as well as the preliminary/detailed design and
construction work required to implement the first phase of the Baseline Station/Transitway
Functional Design Plans to support the CTC Concept Plan and implementation,
including the provision of City funding in the amount of $23.6 million to
cover the estimated cost of immediate infrastructure investments as set out in
Document 2 (Table 1);
4.
Authorize the transfer of funds in the amount of $0.6M from account
904822 Pedestrian Crossing (Baseline-Algonquin) to account 904683 South West
Transitway (Baseline-Norice);
5.
Authorize the transfer of funds in the amount of $10M from Investing
in Ontario revenues and $6.6M from the Transit Capital Reserve Fund, subject to
approval as part of Council’s consideration of the draft Operating and Capital
Budgets scheduled for the first week of December 2008;
6.
Identify, as a
priority within the Transportation Master Plan (TMP) Phase 1 Increment 1
Transit Implementation Priority the $44.9M necessary, as set out in Document 2
(Table 2), for the next phase of the Baseline Station/Transitway Functional
Design Plans to immediately follow the first phase in 2009;
7.
Waive City policy
pertaining to the policy for the disposal of real property including internal
and external circulation, notice and marketing of surplus properties, and
declare the parcel of vacant land, consisting of approximately 1.115 hectares
(2.85 acres), being part of Lot 34 Concession 2 Rideau Front and shown as
Parcel 1 on the Annex “A” plan set out in Document 3, as surplus to the City's
needs;
8.
Authorize the
transfer of the property outlined in Recommendation 6 to Algonquin College to
allow the College to proceed with the implementation of Phase I of the
Algonquin Project (the Centre for Construction Trades and Building Sciences)
subject to the execution of an agreement between the City and Algonquin College
based on the conditions set out in Document 4, and authorize the City Manager
to prepare and execute the agreement; and
9.
Direct staff to
continue to work with Algonquin College on the planning and implementation of
Phase II of the Algonquin Project as well as exploring joint development
opportunities for the City and the College in implementing the remainder of the
updated CTC Concept Plan as set out in Document 1, including securing
additional public and private sector funding to the benefit of both parties.
Que le Comité mixte des transports et des
services de transport en commun recommande au Conseil :
1.
d’approuver les plans de conception
fonctionnelle du Transitway – de la station Baseline, tels que décrits
dans le présent rapport et déposés au Bureau du greffe, pour orienter
l’aménagement et la mise en œuvre du Centre d’activité de Centrepointe (CAC) et
du réseau de transport en commun rapide, y compris les projets du Collège Algonquin et de l’installation
des services techniques de la Bibliothèque – des Archives de la Ville.
2.
D’approuver le plan de conception
mis à jour du CAC joint en Document 1 et conforme aux Plans de conception
fonctionnelle du Transitway – de la station Baseline décrits dans la
Recommandation 1, ainsi que les plans d’aménagement des Projets du Collège Algonquin et de l’installation
des services techniques de la Bibliothèque – des Archives de la Ville.
3.
D’approuver le lancement de
l’évaluation environnementale du réseau de transport en commun rapide à long
terme de Baseline à Norice, ainsi que la conception préliminaire –
détaillée et les travaux de construction requis pour entreprendre la première
étape des Plans de conception fonctionnelle du Transitway – de la station
Baseline, afin de soutenir le Plan de conception et la mise en œuvre du CAC, de
même que la prestation du financement de la Ville au montant de
23,6 millions de dollars pour couvrir le coût estimé des investissements
immédiats dans l’infrastructure déterminés au Document 2 (Tableau 1).
4.
D’autoriser le transfert de fonds
d’un montant de 0,6 M$ du compte 904822, Passage pour piétons
(Baseline–Algonquin) au compte 904683, Transitway Sud-Ouest (Baseline–Norice).
5.
d’autoriser le transfert de fonds
d’un montant de 10 M$ des revenus d’Investir dans l’Ontario et de 6 M$ du fonds
de réserve pour immobilisations dans le transport en commun, sous réserve de
l’approbation des budgets d’immobilisations et de fonctionnement préliminaires
dans le cadre de leur examen par le Conseil prévu pour la première semaine de
décembre 2008.
6. d’inscrire
au Plan directeur des transports (PDT), Phase 1, Augmentation 1,
Priorité pour mise en œuvre du transport en commun, comme il est expliqué dans
le Document 2, que la somme de 44,90 millions de dollars est une priorité
nécessaire pour l’étape suivante des Plans de conception fonctionnelle du
Transitway – de la station Baseline qui suivra immédiatement la première
étape en 2009.
7 De passer outre à la politique
relative à la disposition des biens immobiliers, y compris la diffusion interne
et externe, l’avis et la mise en marché des propriétés excédentaires et de
déclarer que la parcelle de terrain vacant qui comprend environ
1,115 hectare (2,85 acres), qui fait partie du Lot 34,
Concession 2, Façade Rideau et qui est affichée en Parcelle 1 au plan
de l’Annexe « A » du Document 3 est excédentaire aux
besoins de la Ville.
8
D’autoriser
le transfert de la propriété décrite dans la Recommandation 6 au Collège
Algonquin pour lui permettre de procéder à la mise en œuvre de la Phase I
du Projet Algonquin (le Centre des métiers de la construction et des sciences
du bâtiment), compte tenu de l’application d’une entente entre la Ville et le
Collège Algonquin selon les conditions décrites au Document 4, et
d’autoriser le directeur municipal à préparer et conclure l’entente.
9. De
demander au personnel de continuer de collaborer avec le Collège Algonquin à la
planification et la mise en œuvre de la Phase II du Projet Algonquin, et
d’examiner des occasions d’aménagement mixtes pour la Ville et le Collège au
cours de la mise en œuvre des étapes suivantes du Plan conceptuel mis à jour du
CAC décrit au Document 1 et, notamment, d’obtenir un financement
supplémentaire des secteurs public et privé à l’avantage des deux parties.
The Centrepointe Town Centre (CTC) is one of the City’s Community Lands Development Projects. The City’s objectives for these projects are to: 1) implement City plans that leverage strategic parcels of City-owned lands; 2) provide opportunities for innovation; and 3) showcase Ottawa 20/20 growth management principles.
Given its importance for showcasing innovation and smart growth, the CTC Concept Plan, as shown in Document 5, was created in 2006-2007 through a series of five public workshops with the community and stakeholders. Based on input from the workshops, city staff initiated the “due diligence” process to assess the risks and opportunities associated with the development of the area.
On 14 November 2007, Council authorized staff to continue the due diligence investigations/development plan design work for the CTC Project as the basis for establishing Corporate priorities in the budget process for key transportation initiatives set out in the CTC Concept Plan (ACS2007-CMR-CSE-0012). Council also directed staff to:
§ Prepare a transportation master plan for the CTC;
§ Prepare a transportation demand management demonstration plan for the CTC including a parking management strategy/implementation plan; and
§ Work collaboratively with Algonquin College with respect to the potential development of College facilities adjacent to and integrated with the Baseline Transit Station consistent with the CTC Concept Plan.
Concurrent with this direction,
on 14 November 2007 Council also confirmed its support for a major new $104M
initiative by Algonquin College to
expand its training capacity to address the chronic shortage of skilled trades
and health care professionals in Ontario (ACS2007-PTE-DCM-0003). This two-phase project includes the $69M
Phase I Centre for Construction Trades and Building Sciences (CCTBS) and a $35M
Phase II Health Sciences Education Facility (“the Algonquin Project”) and is
planned to be built on City-owned lands on the west side of Woodroffe Avenue
opposite the existing Algonquin campus.
As part of this support, Council agreed to hold in reserve and ultimately make available for development, two parcels of land abutting Baseline Station with a total area of approximately 1.62 hectares (four acres) for potential college facilities, subject to further Council approval of an Agreement between the City and College prior to the land transfers that will address all relevant issues (e.g. senior level government funding, environmental and transit objectives). The reserved land is shown as Parcel A (0.813 hectares or 2.01acres) and a portion of Parcel B (0.810 hectares or 2.0 acres) on Document 6.
Council’s approval of the Algonquin Project also included $5M (gross) in the 2008 Budget for the design and construction of a Pedestrian Bridge between Baseline Station and Algonquin College subject to further approval by Council of a satisfactory cost sharing agreement between the City and the College.
In June 2008, Algonquin College received a $35M funding grant from the Province of Ontario for the CCTBS facility on condition that the facility be completed and opened by September 2011 as set out in Document 7. On the basis of the funding grant, reserve funds and borrowing capacity, Algonquin College is proceeding to implement the project.
A conceptual design for the Algonquin Project has been prepared for the College by Griffiths Rankin Cook Architects (GRC). The project is to be staged to have the CCTBS facility completed by September 2011, with the Phase II Health Sciences Education Facility (and other educational facilities) completed by 2015 based on integrating the Algonquin facilities with the City’s rapid transit facilities in the CTC.
On 14 November 2007, Council approved the
design and construction of a 81,363-square foot facility to house the City’s
Central Archives and Library Technical Services functions (the “Archives
Project”) in the Centrepointe area at the southwest corner of Tallwood Drive
and Woodroffe Avenue, subject to funding as part of the 2008 budget. Funding has been secured and the Archives
Project must be completed by the fall of 2010 when the City’s lease for the
existing archives facility at 111 Sussex Drive terminates. Detailed design for this facility is
underway with the foundation work scheduled to commence in the summer of 2009.
The full text of the 14 November 2007 Council approved recommendations, with respect to the CTC/Algonquin/Archives Projects, is attached as Document 8.
The
completion of the rapid transit network facilities in the Centrepointe area and
their integration with the Algonquin and Archives facilities are fundamental to
the implementation of the Centrepointe Town Centre Concept Plan.
On 28 May
2008 Council approved a 2031 Rapid Transit Network that is focused on
converting the Transitway to Light Rail Transit (LRT) from Baseline to Blair
stations (as shown in Document 9). Bus
Rapid Transit (BRT) service was also approved from Baseline to Norice through
the completion of this portion of the grade-separated Southwest Transitway.
Baseline Station is identified as a major transfer point between bus and rail,
until population densities further south warrant the conversion of the
Southwest Transitway for LRT service.
As noted
in the staff report Transportation Master Plan (TMP) Update, 2008 tabled at the
joint meeting of Transit and Transportation Committees on 10 November 2008, the
construction of the Baseline to Norice portion of the Southwest Transitway and
the new Baseline Station (with a BRT/LRT transfer configuration) is a high
priority and has been recommended for construction as a Phase 1, Increment 1
project, meaning that it will be part of the City's first package of funding
from partner levels of government.
McCormick Rankin Corporation has commenced design work and a land
preservation study for both the station and the Transitway piece. Should funding be received, construction
could be complete by mid 2011.
The LRT
project from Tunney’s Pasture to Baseline Station has a high benefit to
customers and is needed to remove the majority of the remaining buses on Albert
and Slater and therefore taking full advantage of the tunnel investment. Accordingly it has been recommended as a
Phase 1, Increment 2 project, meaning that it will be constructed once
Increment 1 projects are complete and partner government funding is available.
DISCUSSION
The Functional Design Plans for the SW
Transitway - Baseline Station, provide a design basis upon which to integrate
mixed-use development with a LRT/BRT transfer station in an urban setting. When approved by Council, these plans will
be the foundation for all subsequent Rapid Transit Network and Development
planning/project implementation in the CTC and will serve as the guide for any
required environmental assessments and site plan processes.
The study examined specific technical issues related to the integration of Baseline Station and transit network with upcoming development plans for the CTC, including the Algonquin Project, and the City Archives. City and College staff/consultants have worked collaboratively since June 2008 to solve technical, design and phasing issues with respect to integrating the proposed building projects with the rapid transit facilities in the CTC.
The resulting Functional Design Plans for Baseline Station are now complete and filed with the Office of the City Clerk. The Plans reflect a coordinated design effort that ensures that the Algonquin Project and required City transit facilities are properly staged as set out in Document 10.
The Evolving CTC Concept Plan - November 2008 Update
The CTC Concept Plan, shown in Document 5, has now been updated to incorporate the “Southwest Transitway LRT/BRT - Long Term” Functional Design Plan and the Algonquin Project Concept Plan as shown in Document 1.
The grade separation of the Transitway and Baseline Station in the CTC, as shown in Document 1, provides for the additional direct vehicular access to the CTC, a more significant public focal point and better integration of adjacent buildings with the transit station that the workshop participants were seeking but which could not be accommodated with the at grade transit station constraint that existed for the November 2007 Concept Plan.
Council’s approval of the November 2008 update of the Concept Plan (Document 1) will provide a consistent framework for further community consultation as the transit and development projects proceed through any required environmental assessment and site plan processes.
The estimated cost for implementing the grade
separated LRT/BRT system from Baseline Road to Norice Street and a new transfer
station is $185M as set out in Document 2 (Table 4). This estimated cost is now included in the City’s current TMP
project requirements as identified within the TMP Phase 1 Increment 1 Transit
Implementation Priority.
As set out in the Background Section of this report, the approved
strategic initiatives call for the BRT system to be completed by Dec. 2015
and for the LRT service to come to Baseline Station sometime after 2016.
Based on the LRT requirements after 2016 and, in order to avoid major
disruption to the BRT system when constructing the LRT works, the BRT
system must be completed on the basis of the ultimate grade separation
requirements. This will cost $165M as per the "Interim" cost
estimate set out in Document 2 (Table 3).
Because of the grade separation requirements, no stage of the grade-separated portion of the works will be useable until all the grade separation work is fully completed. On that basis the project can be initiated in stages based on approximately $27.5M per year of work and in locations that will best fit with adjacent development projects.
In that respect, both the City's Archives and Algonquin's CCTBS project need to be completed on or before 2011. The Algonquin Project deadline based on the funding conditions set by the Province of Ontario is 1 September 2011. The Archives Project deadline is based on the termination of the City’s existing lease at 111 Sussex in the fall of 2010. As a result, it is proposed that the Phase I Transitway work in the CTC provide for the completion of the grade separated structures adjacent to both the Archives and CCTBS projects at a cost of $68.5M as per the Phase I cost estimate set out in Document 2 (Table 2).
Since the funding of the TMP initiatives will not be in place to allow
the City to commit to constructing all the Phase I Implement 1 Transitway work
in the CTC starting in May 2009, the following minimum work was identified for
the first year in order to be able to coordinate with the Algonquin Project
work:
The result is a total construction cost, including engineering and
contingency, of $23.6M as set out in Document 2 (Table 1).
In order for Phase I of
the City's Transitway work to start in May 2009, the environmental
assessment and preliminary engineering design work must be initiated in early
December and completed by the 31 March 2009. While an RFP for the
engineering work is currently in progress, the award of this work is
dependent on Council’s approval of the required funding.
Therefore, as set out in Recommendation 3, it is recommended that Council approve the initiation of the environmental assessment, preliminary/detailed design, and construction work necessary to implement the first phase of the Baseline Station/Transitway Functional Design Plans to support the CTC Concept Plan and implementation including the provision of City funding in the amount of $23.6 million to cover the estimated cost of immediate infrastructure investments as set out in Document 2 (Table 1). The sources of this investment are outlined in
Recommendations 4 and 5 and the Financial
Implication section of this report.
It is
also recommended, as set out in Recommendation 6 that the $44.9M remainder of
the $68.5M cost for the Phase I Transitway works for the CTC be
identified, as a priority within the TMP Phase 1 Increment 1 Transit
Implementation Priority, to allow the rest of the Phase I works to immediately
follow the first phase in 2009.
The provision of $23.6M funding by the City for
the immediate infrastructure investments needed to coordinate the transit
network construction with the CCTBS project construction will allow the City to
transfer the parcel of land, designated as Parcel 1 on the Annex A plan shown
in Document 3, to Algonquin College for the CCTBS building site subject to an
agreement being executed between the City and the College based on the
conditions set out in Document 4.
Once the existing Transitway station is relocated away from Parcels 1 and 2, as shown on the Annex A plan, by constructing the temporary station, Parcel 1 will be surplus to the City’s transit plan requirements and can therefore be declared surplus as set out in Recommendation 7.
As Parcel 1 has been held by the City solely for transit purposes, it is no longer needed for those purposes. Since Council in November 2007 reserved the area between the transit station and Woodroffe for potential Algonquin Project facilities, it is recommended that for this transaction Council waive the City policy pertaining to the internal and external circulation, notice and the marketing of surplus properties, and transfer the parcel to the College as set out in Recommendation 8.
Joint Phase 2 Algonquin Project and CTC Development
Planning/Implementation
The updated CTC Concept Plan, set out in
Document 1 evolved through the collaborative planning efforts of the City and
College and reflects the ultimate development objectives of both parties for
lands within the CTC.
There are significant opportunities for the City and College to cooperate in the joint development of other parcels in the CTC. As set out in the land transfer conditions in Document 4, the City will continue to reserve the 0.956 hectares (2.36 acres) Parcel 3, shown on the Annex A plan, for Phase 2 of the Algonquin Project as well as surface rights and air rights as required for pedestrian bridge links over the 0.770 hectares (1.90 acre) Parcel 2 of the transit tunnel.
In addition, the 0.293-hectares (0.72-acre) Parcel 6, shown on the Annex A plan, will be reserved for the College to integrate a building with the proposed LRT/BRT transfer station as set out in the land transfer conditions in Document 4.
Joint developments by the City and College of the Phase 2 Algonquin Project facilities with other CTC developments on Parcels 4, 5 and 7, as shown on the Annex A plan (Document 3), will provide greater development potential and additional revenue opportunities for both parties. It is recommended that the City continue to work with Algonquin College on the planning and implementation of Phase 2 of the Algonquin Project as well as exploring joint development opportunities for the City and the College in implementing the remainder of the updated CTC Concept Plan, including securing additional public and private sector funding to the benefit of both parties.
City staff, College staff and consultants have worked collaboratively to advance the Concept Plans for the CTC and Algonquin Projects in conjunction with the development of the functional design for the Rapid Transit Network facilities.
As this work has been undertaken on the basis of existing Council directions and approvals, and given that the resulting plans will be the subject of further environmental and site plan approval processes, additional community consultation has not been carried out at this point.
Subject to Council approval of the recommendations
in this report, it is the intention to coordinate with the Ward Councillor to
hold a public meeting early in 2009 that will deal with all planned CTC
initiatives including the site plans for the Archives and Algonquin Projects
and the EA for the rapid transit system.
PROCEDURE
According
to the Terms of Reference for Standing Committees, Recommendations 7 and 8 fall
within the jurisdiction of Corporate Services and Economic Development
Committee to recommend to Council.
While it is appropriate that the Joint Meeting of Transportation and
Transit Committee consider these recommendations first in the overall policy
context of the Centrepointe Town Centre - Baseline Station - Algonquin - City
Archive Project, in the normal course these two recommendations would then
proceed to Corporate Services and Economic Development Committee prior to all
matters rising to Council.
However,
because of the integral link of this project to the Transportation Master Plan,
it is appropriate that all of the recommendations rise to Council at the same
time. Therefore, as there is not a
meeting of Corporate Services and Economic Development Committee between the
Joint Meeting and Council, Recommendations 7 and 8 will proceed directly to
Council. The procedural motion for the
introduction of Standing Committee reports will contain the necessary language
to permit their consideration.
FINANCIAL IMPLICATIONS
Funds are
available for transfer from 904822 ($0.6M), Pedestrian Crossing (Baseline -
Algonquin). As part of Council approval
of the Rate Supported Budget, on 12 November 2008 Council pre-approved
the Water ($2.2M) and Wastewater ($3.2M) contribution from Reserves
in support of the CTC Concept Plan and the South West Transitway.
Subject to
Council deliberations and approval of the 2009 Operating and Draft Capital
Budgets during the first week in December, the availability and transfer of
$10M, Investing in Ontario Revenues and $6.6M from the Transit Capital Reserve
Funds. The forecasted uncommitted balance to year-end for the Transit
Capital Reserve fund is $39M.
In total,
and with all the above adjustments, the revised budget of the
South West Transitway (Baseline - Norice) will be $23.6M.
Document 1 Centrepointe Town Centre Concept Plan, updated November 2008
Document 2 Cost Estimate S.W. Transitway/Baseline Station
Document 3 Annex “A” Algonquin College Property Requirements
Document 4 Land Transfer Agreement Conditions
Document 5 Centrepointe Town Centre Concept Plan, Workshop 5
Document 6 Centrepointe Town Centre Road Network Workshop 5 Concept Plan
Document 7 Provincial Government Funding Commitment
Document 8 Council Approvals
Document 9 Rapid Transit Network Option 4
Document 10 Baseline Station/Transitway and Algonquin Project Phasing/Timelines
Upon Council
approval of the recommendations in this report, the Real Estate Services
Division (RESD) will coordinate the negotiations between the City and College
staffs with respect to the Land Transfer Agreement and associated agreements as
outlined in Document 4 of this report.
Once the above referenced negotiations are concluded, RESD will assist Legal Services in preparing the Land Transfer Agreement and associated agreements; having the agreements executed by both parties; finalizing the arrangements for the transfer of the Property from the City to the College; and closing this property transaction.
Also, upon Council approval of the recommendations in this report, staff in the Infrastructure Services and Community Sustainability Department will initiate the environmental assessment for the long-term rapid transit network from Baseline to Norris, as well as the preliminary/detailed design and construction work required to implement the first phase of the Baseline Station/Transitway Functional Design Plans to support the CTC Concept Plan and implementation.
CENTREPOINTE TOWN CENTRE CONCEPT
PLAN,
UPDATED NOVEMBER 2008 DOCUMENT 1
COST ESTIMATES S.W.
TRANSITWAY/BASELINE STATION DOCUMENT 2
Phase 1 (Immediate) -
Minimum Work Required to Coordinate with CCTBS Construction
Item Description |
Estimate |
|
|
Temporary Baseline Station |
$6.35 m |
|
|
Piling/Tiebacks for Tunnel Construction – College Avenue to Navaho Drive |
$2.8 m |
|
|
Excavation for tunnel and College/Navaho underpasses |
$2.6 m |
|
|
College Avenue underpass structure |
$2.8 m |
|
|
S.W.M. sewers – College Avenue to Navaho Drive |
$2.6 m |
|
|
Navaho watermain relocation |
$1.75 m |
|
|
Sub-Total
- Construction |
$18.9m |
|
|
Contingency @10 % |
$1.9 m |
|
|
Engineering @ 15% |
$2.8 m |
|
|
Total |
$23.6
m |
Notes: These estimates are based on the
City of Ottawa’s 2008 unit price data. |
Phase I - Temporary Baseline Station & Grade Separated Transitway Structures - Navaho Dr. to College Ave. and Tallwood Station
Note: Includes $23.6M costs identified in Table 1.
Item
Description |
Estimate |
|
|
Temporary Baseline Station |
$6.35 m |
|
|
Tunnel (covered) – College Avenue to Navaho Drive |
$27.4 m |
|
|
Excavation for tunnel and underpasses |
$2.6 m |
|
|
College Avenue underpass |
$2.8 m |
|
|
Navaho Drive underpass |
$3.5 m |
|
|
S.W.M. sewers – College Avenue to Navaho Drive |
$2.6 m |
|
|
Watermain relocation |
$1.75 m |
|
|
Tallwood Drive underpass |
$2.2 m |
|
|
Tallwood Station |
$2.0 m |
|
|
Excavation/grading for Tallwood Station and Transitway |
$2.8 m |
|
|
Tallwood storm sewer bypass |
$0.5 m |
|
|
Tallwood watermain relocation |
$0.3 m |
|
|
|
|
Sub-Total - Construction |
$54.8m
|
|
|
Contingency @10 % |
$5.5 m |
|
|
Engineering @ 15% |
$8.2 m |
|
|
Total |
$68.5 m |
Table 3
Phase II Interim - Provide for BRT Completion in Centrepointe -
Cost Estimate Summary - Functional Design - Baseline Rd. to Norice St. Intersection
Item
Description |
Estimate |
|
|
Temporary Baseline Station |
$6.35 m |
|
|
BRT – Tallwood Drive to Baseline Road – including Navaho, Collage and Station underpasses, Tunnel, Baseline Transit Station |
$98.5 m |
|
|
S.W.M. – Navaho to Pinecrest Creek |
$2.0 m |
|
|
S.W.M – Tallwood to Navaho |
$7.2 m |
|
|
Tallwood watermain |
$0.3 m |
|
|
Navaho watermain |
$1.75 m |
|
|
BRT – Tallwood to Norice |
$16.0 m |
|
|
Sub- Total Construction |
$132.1
m |
|
|
Contingency @ 10% |
$13.21 m |
|
|
Engineering @ +/- 15% |
$19.69 m |
|
|
Total |
$165.0 m |
|
|
Notes:
-
Includes $68.5M costs identified in Table 2.
-
This functional design cost estimate summary is based
on the preliminary functional design drawing Plate PR2, Scheme 7, dated 24
October 2008 & Plate P3,
Scheme 5, dated 28 October 2008 (Temporary Station).
- These estimates are based on the City of Ottawa’s 2008 unit price data base
Table 4
Long Term – Provide for BRT/LRT Transfer Station
Cost Estimate Summary - Functional Design - Baseline Rd. to Norice St. Intersection
Item
Description |
Estimate |
|
|
Temporary Baseline Station |
$6.35 m |
|
|
Phase II – Interim BRT |
$98.5 m |
|
|
LRT and station/tunnel finishes |
$17.5 m |
|
|
S.W.M. - Navaho to Pinecrest Creek |
$2.0 m |
|
|
S.W.M. – Tallwood to Navaho |
$7.2 m |
|
|
Tallwood watermain |
$0.3 m |
|
|
Navaho watermain |
$1.75 m |
|
|
BRT – Tallwood to Norice |
$16.0 m |
|
|
Sub-Total - Construction |
$149.60
m |
|
|
Contingency @ 10% |
$14.96 m |
|
|
Engineering @ +/-15% |
$20.44 m |
|
|
Total |
$185.00 m |
|
|
Notes:
-
Note: Includes $165M costs identified in Table 3.
-
This functional design cost estimate summary is based
on based on the preliminary functional design drawings Plate PR1, Scheme 2,
dated 24 October 2008 & Plate P3,
Scheme 5, dated 28 October 2008 (Temporary Station).
- These estimates are based on the City of Ottawa’s 2008 unit price database.
LAND TRANSFER AGREEMENT CONDITIONS DOCUMENT 4
1. The City of Ottawa (the ”City”) agrees to transfer to Algonquin College (the “College”), for the nominal consideration of $1, the approximately 1.152-hectare (2.85-acre) parcel of land, being part of Lot 34 Concession 2 Rideau Front and shown as Parcel 1 on the Annex “A” plan set out in Document 3 of this report (the “Property”) subject to the City and College entering into a Development Agreement prior to the transfer of the property based generally on, but necessarily limited to, conditions as follows:
1.1 The City acknowledges that is the intention of the College to expand its Woodroffe Campus into the Centrepointe Town Centre (CTC), by the end of 2015, as contemplated by the CTC Concept Plan, as updated to November 2008 and attached to this report as Document 1, and generally in the development form shown on the Stage 2B Plan dated October 28, 2008, prepared by Griffiths Rankin Cook Architects (GRC) and attached as Document 10 of this report (the Algonquin Project”), and the City agrees to make its best efforts to accommodate the Algonquin Project in the CTC by providing lands and coordinating City infrastructure requirements as set out further in this agreement.
1.2 The College acknowledges that the City as part of its proposed Rapid Transit Network Plan of the Transportation Master Plan (TMP) intends ultimately to provide a grade separated LRT/BRT transfer station at Baseline Station during the period 2016-2031, as shown on Functional Design Plan on file with the City Clerk being McCormick Rankin Corporation (MRC) drawing Plate PR1, Scheme 2, dated 24 October 2008 - titled “Southwest Transitway LRT/BRT - Long Term”, and to provide an interim grade separated BRT system at Baseline Station by December 2015, as shown on Functional Design Plan on file with the City Clerk being MRC drawing Plate PR2, Scheme 7, dated 24 October 2008 - titled “ Southwest Transitway BRT - Interim Stage” (the “Baseline Station Project”), and the College agrees to make its best efforts to assist the City in implementing the Baseline Station Project by coordinating it with the implementation activities for the Algonquin Project as set out further in this agreement.
1.3 The College agrees to construct an approximately 150,000-square foot building, at an estimated cost of $69M, to accommodate the College’s Centre for Construction Trades and Building Sciences (the “CCTBS Building”) on the Property with construction commencing by August 2009 and completed by September 2011 as indicated on the GRC Stage 1C plan dated October 28 set out in Document 10 of this report.
1.4 The College agrees that the transfer of the Property by the City to the College will not be made until the College has obtained site plan approval for the CCTBS building on the Property.
1.5
Prior to the transfer of the Property by the City to
the College and before March 31, 2009, the City and College will negotiate and
enter into a Design and Construction Agreement for the following transitway related works (the “Initial City Transit
Project”) shown in MRC Functional Design Plan “Plate PR2, Scheme 7, dated 24 October 2008 titled “
Southwest Transitway BRT - Interim Stage”
·
Temporary Baseline Station Relocation as shown on the MRC Functional Design Plan “Plate P,
Scheme 5, dated 28 October 2008 - titled “Temporary Baseline Station - Location
and Configuration”;
·
Excavation and
protection/shoring as required for the construction of the tunnel structure
between Navaho Drive and College Avenue and the underpasses at College and
Navaho;
·
Construction of
the covered tunnel structure between Navaho Drive and College Avenue;
· Construction of the College Avenue and Navaho underpass structures; and
· Installation of Storm sewers under the transitway tunnel floor from north of Navaho Drive to South of College including the necessary relocation of the watermain at Navaho Drive;
1.6 The Design and Construction Agreement shall be based generally on, but not necessarily limited to, conditions as follows:
1.6.3 The College agrees that the detailed design, construction drawings, and design/build contractual arrangements for the Initial City Transit Project will be subject to City review and approval.
1.6.4 The College agrees that the construction of the Initial City Transit Project will be subject to the site supervision requirements of the City.
1.6.5 The College acknowledges and agrees that the City will, initially, only provide funding in 2009 to cover the “Minimum Work Required to Coordinate with CCTBS Construction” for the Initial City Transit Project, as set out in Document 2 of this report, and currently estimated to cost $23.6 million and that the implementation of the other works identified as part the Initial City Transit Project, as shown in the cost estimate for the “Proposed Phase I Transitway Project” and set out in Document 2 of this report, will be subject to the City obtaining funding as part of its TMP/Rapid Transit Network Project.
1.7 Prior to the transfer of the Property by the City to the College and before March 31, 2009, the City and College will negotiate and enter into an agreement for design, construction, operation and maintenance of the pedestrian bridges links across Woodroffe and College Avenues included in the Baseline Station Project described in section 1.2 above based generally on, but not necessarily limited to, conditions as follows:
1.7.1 The City will
be responsible for the following:
· Securing the funding for the design and construction of the pedestrian link bridges and any modifications required to the transit platform. Any additional third party funding will be used to de-fray the City’s cost commitment.
· Providing traffic control on Woodroffe and College Avenues, if required, for the biannual cleaning of the exterior windows.
·
Providing long-term structural maintenance of the
pedestrian link bridges.
· Coordinating and providing project management for the design and construction of the pedestrian link bridge.
1.7.2 The College will be responsible for the following:
· Providing up to $400,000 in funding for the design and construction of alterations for College buildings on the east side of Woodroffe to accommodate the pedestrian link bridge across Woodroffe.
· Providing, at the College’s cost, structural provisions and public pedestrian connecting links within the CCTBS building to accommodate the pedestrian bridge links across Woodroffe and College Avenues.
· Providing funding for and carry out modifications to the College buildings as required for operation of the pedestrian link bridges once constructed.
· Providing cleaning services for the pedestrian link bridges (interior (daily/as required) and exterior (biannual)).
· Providing security services for the pedestrian link bridge.
· Providing public access, through College buildings at all times that the OC Transpo service is operating, to the pedestrian link bridges as required for Public Access to Baseline Station
· Providing property and easements as necessary for the construction and maintenance of the pedestrian link bridge
· Providing and maintaining landscaping features of the pedestrian link bridge
· Operating and maintaining heating, ventilation and lighting for the pedestrian link bridge
1.8 The City agrees to continue to reserve the
0.956-hectare (2.36-acre) Parcel 3 as well as surface rights and aerial rights
as required for pedestrian bridge links over the 0.770 hectare-
(1.90-acre) Parcel 2, shown on the Annex A plan set out in Document 3 of this
report, for potential use by the College for implementing Phase 2 of the
Algonquin Project.
1.9 The College agrees that the College will,
at it costs, be responsible for the design, construction/landscaping,
maintenance and management of the public open space improvements over the roof
on Parcel 2 shown on the Annex A plan set out in Document 3.
1.10 The City agrees to provide the College with the first right at nominal consideration to construct a College Facility on the 0.293-hectare (0.72-acre) Parcel 6, shown on the Annex A plan set out in Document 3 of this report, that is integrated with the proposed LRT/BRT transfer station on this parcel.
1.11 The College agrees to make its best efforts to develop a College Facility on the 0.293-hectare (0.72-acre) Parcel 6, shown on the Annex A plan set out in Document 3 of this report, that is integrated with the proposed LRT/BRT transfer station on this parcel.
1.12 The City and College agree to continue to work cooperatively on the planning and implementation of Phase 2 of the Algonquin Project as well as exploring joint development opportunities for the City and the College on CTC Parcels 4, 5 and 7, as shown on the Annex A plan set out in Document 3 of this report, with the objective of securing additional public and private sector funding to the benefit of both parties.
1.13 The City and College agree to make their best efforts to establish a route through the College for #118 buses to have direct access to Baseline Station from College Avenue and to provide for improved transit service to the College when the City’s Baseline Station Project, as described in Paragraph 1.2 above, is completed.
1.14 Prior to the transfer of the Property by the City to the College, the City and College agree to enter into a Memorandum of Understanding that will establish the principles for the increased use of transit by Algonquin students and staff with the goal to increase transit ridership and revenue, support the College’s and City’s environmental goals, and to reduce the need for driving and parking.
1.15 Prior to the transfer of the Property by the City to the College, the College agrees to undertake such investigations as it deems necessary to assure itself that the Property is suitable for the CCTBS Project and the College further agrees to accept the transfer of the Property by the City to the College on an “As Is” basis, subject to the other provisions set out above with respect to this proposed Development Agreement. The College reserves the right to not accept the transfer of the property if risks, environmental or otherwise are such that the College does not wish to assume them.
CENTREPOINTE TOWN CENTRE ROAD NETWORK
WORKSHOP 5 CONCEPT PLAN DOCUMENT 6
COUNCIL APPROVALS DOCUMENT
8
Ø November
14, 2007, Centrepointe Town Centre Project - Council authorizes:
“Staff to continue with due diligence investigations/development plan design work for the Centrepointe Town Centre (CTC) project and, in order to assist in establishing the Corporate priorities in the budget process for the key transportation initiatives set out in the Centrepointe Town Centre Concept Plan as described in this report, staff be directed to:
a) Prepare a transportation master
plan for the CTC based on the road network concept established from the
Community Workshop process and initial due diligence investigations,
b) Prepare a transportation demand
management demonstration plan for the CTC including a parking management
strategy/implementation plan, and
c)
Work
collaboratively with Algonquin College with respect to the potential
development of College facilities adjacent to and integrated with, the Baseline
Transit Station consistent with the Centrepointe Town Centre Concept Plan”;
Ø
November 14, 2007, Archives and Library Technical
Services Facility - Council
approves recommendation that Council:
“Refer the following Option 3 for consideration as part of the 2008 budget process: Design and construction of the 81,363 square foot RPG recommended synergy option E-2 (synergistic option), described in Document 1, that provides for selected archives public services, archives technical services and library technical services to be located at Centrepointe, which can be implemented using a phased approach.” Note: estimated cost $38.6M.
Ø
November 14, 2007, Algonquin Project - Council approves recommendations that Council:
“1. Support
Algonquin College’s development concept for a Centre for Construction Trades
and Building Sciences and Health Sciences Education Facility (“the Algonquin
Project”), as further described in this report, by instructing staff to prepare
a letter to be sent to the federal and provincial governments under the Mayor’s
signature indicating the City’s support for, and commitment to, the Algonquin
Project and requesting that they provide their respective funding contributions
set out in the report entitled: ”Algonquin College Strategic Academic
Expansion, A Centre for Construction Trades and Building Sciences and An
Expanded Facility for Health Sciences Training” dated August 8, 2007;
2. Direct
staff to include $5M (gross) in the 2008 Budget for the design and construction
of a Pedestrian Bridge between Baseline Station and Algonquin College as a
priority project, subject to further approval by Council of a satisfactory cost
sharing formula that will address the design, construction and maintenance of
the bridge in an Agreement between the City and the College;
3. Direct
staff to hold in reserve and to ultimately make available for development as
part of the Project for $1.00 each, two parcels of land abutting Baseline
Station with a total area of approximately 1.62 hectares (4 acres) in the
locations designated on the City’s Centrepointe Town Centre Concept Plan
(attached to this report as Document 1) for potential college facilities,
together with air rights over Baseline Station between these two parcels of land
subject to further Council approval of an Agreement between the City and
College prior to the land transfers that will address all relevant issues (e.g.
site plan requirements, senior level government funding, environmental and
transit objectives, etc.);
4. Direct staff to work with
Algonquin College to explore development opportunities for other
academic/institutional uses within the Centrepointe Town Centre area as part of
the Centrepointe Town Centre development planning process; and
5. That the City’s support
of the Algonquin project be conditional on the following:
a) That Algonquin College secure
its required funding;
b) That the City secure funding
for the pedestrian bridge transitway configuration and expansion to the south
through the Centrepointe area;
c) That the design of the facility
meet the City’s transit-oriented development needs and fit within the
Centrepointe Town vision;
d) That the City and Algonquin
College enter into an agreement, subject to a further City Council approval, to
reflect the terms and conditions required to implement the joint development
initiative in accordance with the objectives and requirements of both parties,
including maintenance of the pedestrian overpass; and
e) That if items a) to d) have not
been accomplished by 2012, then this approval will lapse.”
RAPID TRANSIT NETWORK OPTION 4 DOCUMENT 9
LRT Tunnel - East and West downtown LRT plus North- South LRT
BASELINE STATION/TRANSITWAY AND
ALGONQUIN
PROJECT PHASING/TIMELINES DOCUMENT 10
ALGONQUIN
COLLEGE EXPANSION - CENTREPOINTE October 28th, 2008
Overview of Phasing and
Timelines
Note: to be read in
conjunction with corresponding phasing diagrams
PHASE 1 (Temporary Transit plan) - Scheduled for Completion by August 2011
Stage
1A – October 2008-March 2009 (5 months)
Stage 1B – April 2009 - September 2009 (6 months)
Stage 1C – August 2009
-August 2011 (24 months)
PHASE 2
(Interim Transit plan) -
Scheduled for Completion between
2013-2015
Stage
2A – August 2011-2013
PHASE 3
(Longterm Transit plan) 2016
onwards
Stage
3 - 2016 onwards