Report to/Rapport au :

 

Transportation Committee

Comité des transports

 

and Council / et au Conseil

 

15 March 2012 / le 15 mars 2012

 

Submitted by/Soumis par : Nancy Schepers, Deputy City Manager/Directrice municipale adjointe, Planning and Infrastructure / Urbanisme et Infrastructure

 

Contact Person / Personne ressource : Vivi Chi, Manager/Gestionnaire, Transportation Planning/Planification des transports, Planning and Growth Management/Urbanisme et Gestion de la croissance

(613) 580-2424 x21877, vivi.chi@ottawa.ca

 

 

City Wide/ À l’échelle de la Ville

Ref N°: ACS2012-PAI-PGM-0082

 

 

SUBJECT:

AREA TRAFFIC MANAGEMENT PROJECT PRIORITY INFORMATION UPDATE

 

 

OBJET :

MISE À JOUR DE L'INFORMATION CONCERNANT LA PRIORITÉ DES PROJETS DE GESTION DE LA CIRCULATION LOCALE

 

 

REPORT RECOMMENDATION

 

That Transportation Committee recommend that Council:

 

1.                  Receive this Area Traffic Management Project Priority Information Update, and

 

2.                  Remove the hold that was placed on outstanding localized Area Traffic Management Study requests.

 

RECOMMANDATION DU RAPPORT

 

Que le Comité des transports recommande au Conseil de :

 

1.                  Recevoir cette mise à jour de l’information concernant la priorité des projets de gestion de la circulation locale;

 

2.                  Supprime la suspension dont faisaient l’objet les demandes ayant trait aux études localisées de gestion de la circulation locale en cours.

 

 

EXECUTIVE SUMMARY

 

In October 2011, Council approved a motion placing a hold on all outstanding area traffic management (ATM) study requests and requesting that staff report back to the Transportation Committee and Council with a priority list of backlogged existing ATM projects.  In addition, as part of the 2012 Budget approval process, Council approved $2.5 million in Capital funding for the ATM program.

 

This funding provides a unique opportunity to implement solutions to the most serious issues studied thus far, and at the same time, substantially enhances the potential of new solutions from new studies proceeding to implementation much more quickly than has been possible in the past.

 

This report recommends allocating $2 million of the $2.5 million directly to implementing priority projects from the current backlog of previously approved measures with the remaining $500,000 retained for future project implementation.  The list of measures proposed for implementation was developed utilizing the processes described in the City’s Area Traffic Management Guidelines, which is based around the principle of prioritizing problems and solutions according to the severity of the concern.

 

This report also recommends removal of the hold and allowing localized outstanding studies and new studies to be undertaken based on the priority ranking process as described in the ATM Guidelines and as staff resources permit.

 

RÉSUMÉ

 

En octobre 2011, le Conseil a approuvé une motion qui mettait en suspens toutes les demandes relatives aux études de gestion de la circulation locale (GCL) en cours et qui demandait au personnel de présenter ses conclusions au Comité des transports et au Conseil, au moyen d’une mise à jour relative à la priorité des projets de GCL. De plus, dans le cadre du processus d’approbation du budget de 2011, le Conseil a approuvé une mise de fonds de 2,5 M$ pour le programme de GCL.

 

Une mise de fonds de 2,5 M$ offre une occasion unique de mettre en œuvre des solutions aux problèmes les plus sérieux étudiés jusqu’à présent et, en même temps, elle permet d’améliorer considérablement la possibilité de nouvelles solutions, les nouvelles études étant mises en œuvre beaucoup plus rapidement que par le passé.

 

2 M$ des 2,5 M$ seront affectés directement à la mise en œuvre de mesures prioritaires provenant du lot actuel de mesures déjà approuvées, tandis que les 500 K$ restants seront retenus pour des considérations futures liées à la mise en œuvre. La liste des mesures proposées pour la mise en œuvre a été établie en ayant recours aux processus décrits dans les Lignes directrices sur la gestion de la circulation locale de la Ville, qui se fondent sur le principe de priorisation des problèmes et des solutions selon la sévérité de la difficulté.

 

La suppression de la suspension actuelle des études en cours n’est recommandée que pour les études localisées, les études étant amorcées lorsque les ressources en personnel le permettent, selon le processus de priorité de rang, tel qu’il est décrit dans les Lignes directrices sur la GCL.

 

 

BACKGROUND

 

On 26 October 2011, Council approved the following motion:

 

THEREFORE BE IT RESOLVED that Council refer the NTI Implementation Plan back to staff for review as follows:
-
That all outstanding Area Traffic Management (ATM) Study requests be placed  “on hold”  until such time as Council makes a decision on Area Traffic Management;

- That the Studies currently underway be completed and that the existing ATM projects be re-examined against any known changes in traffic patterns;
- That these projects be prioritized, in consultation with Ward Councillors, with value for money and safety improvement impact as the evaluation criteria; and
- That staff report back to the Transportation Committee and Council with an ATM Project Priority Information Update by Q1 of 2012.

In addition, as part of the 2012 Budget approval process, Council provided $2.5 million in Capital spending authority for the Neighbourhood Traffic Improvement (NTI) plan which, based on the motion as listed above, is intended primarily for the implementation of Area Traffic Management (ATM) measures recommended through completed ATM studies.

 

With Council’s 2004 approval of the ATM Guidelines, the City enacted a process for considering community traffic calming/traffic management concerns around the principle of prioritizing problems and solutions in a logical order corresponding to the severity of the concern.  This new process was intended to ensure that available resources within this program would be focused on solving the most significant issues city-wide.

 

The ATM program, however, inherited a substantial backlog of pre-amalgamation study recommendations that at the time required close to $8 million in implementation funding.  A number of these study recommendations remain outstanding today as the available funding for the ATM program has been substantially less than that required to address both this backlog as well as recommendations from new studies that have come forward.  Managing this backlog and community expectations has been a significant issue for the ATM program.  Lack of funding results in substantial delays (often years) before implementation occurs – which raises questions about solutions meeting evolving community needs or expectations.  Timely implementation of solutions is important for everyone involved.

 

As well, given that the majority of pre-amalgamation study recommendations were from community studies in and around the City’s central area, a perception persists that the ATM program remains unfairly focused on serving the needs of central area communities without providing balanced services across the entire city.

 

DISCUSSION

 

In preparing this project priority information report, and through recent consultations with a number of Ward Councillors, a significant effort has gone into ensuring resources are being allocated in the most efficient and effective manner possible.

 

The $2.5 million in ATM capital funding included in the 2012 budget provides a unique opportunity to implement solutions to the most serious issues studied thus far, and at the same time, substantially enhances the potential of solutions from new studies proceeding to implementation much more quickly than has been possible in the past.

 

Prioritization Process Focused on City’s Most Serious Problems

 

With approval of the 2004 ATM Guidelines, the City, for the first time, was able to consider both the backlog of previously approved ATM study recommendations inherited from before amalgamation and new study recommendations on an equal footing, irrespective of the rigour utilized when recommendations were initially approved.  The process for prioritizing the implementation of both new and backlogged recommendations ensures resources are focused on the most significant issues.  The process used is described further in Document 1.  It considers factors such as inappropriate driver behaviour, vehicle speeds and volumes, through traffic volumes, collisions, and implementation costs. 

 

Prioritization Ensures Priority Recommendations Move Forward

 

Even with limited funding for implementing ATM measures, many of the recommendations of recently initiated studies have already proceeded to implementation, and a number of those that have not are recommended for implementation with the funding made available in 2012.  Document 2 provides a summary of recent studies and the implementation status of their recommendations.  Of the 17 studies completed since 2001, 11 have had all ATM recommended measures implemented.

 

Value for Money and Safety Improvement

 

The ATM Guidelines process is the most effective means of determining implementation priorities, especially given Council’s recent direction to obtain value for money and deploy funding where the safety improvement impact is high.  Prioritizing requests based on problem severity ensures implementation efforts are focused around implementing high impact solutions.

 

Efficiency Considerations

 

Approved measures that can be coordinated with currently planned roadway reconstruction projects will be implemented through that opportunity. Therefore, these measures have been excluded from potential funding considerations in this priority update.

 

ATM studies, in some cases, have included recommendations of non-ATM types of measures such as new sidewalks, traffic control signal modifications, or even widening or narrowing of entire streets.  Such measures, although beneficial from a community liveability point of view, are often very expensive to implement and considered beyond the level of affordability of the ATM program.  Such measures are best dealt with through other programs such as the new sidewalk program, or the new traffic signal program, or at the time these roads come up for full reconstruction.  These types of recommended measures have also been excluded from potential funding considerations in this priority update.

 


 

Allocation of Current Funding

 

The full $2.5 million approved in the 2012 budget will be allocated to implementing approved measures and associated detailed design.  This means that no new studies will be undertaken except for those studies of a localized nature that can be undertaken by in-house staff.  New, comprehensive, community-wide studies requiring the retention of external expertise (and funding) will no longer be undertaken during the remainder of this term of Council (to end of 2014).

 

The initial $2 million will be directed towards measures from the current backlog.  The remaining $500,000 will be retained to permit implementation considerations from new localized studies that are expected to come forward throughout the remainder of this term of Council.

 

Document 3 contains the list of prioritized measures to be implemented.  These measures came from the approved recommendations of 17 studies as listed in Document 4.

 

Moving Forward Through Addressing the Backlog

 

The immediate allocating of $2 million toward the implementation of highest priority measures, in combination with the removal of some of the lower ranking measures or out-dated measures on the backlog list that come as a result of recent consultations with individual Ward Councillors, significantly reduces the longstanding implementation backlog.  This represents a major enhancement for the ATM program, and the City’s ability to respond much more quickly to community needs.  It also greatly enhances the potential for priority recommendations from new studies proceeding to implementation within a reasonable timeframe.  The measures intended for immediate implementation, cover those with priority ranking points ranging from a high of 102 points to a low of 62 points.  Almost all of the remaining measures on the implementation backlog will have 61 priority points or less (out of a maximum potential of 145 points).

 

Document 5 summarizes the residual list of remaining outstanding measures following the initial $2 million implementation undertaking.  Of note, while some of the higher ranking of these may become priorities during the later rounds of implementation, for many of these, especially those with relatively few priority ranking points, the only opportunity for these to be implemented may be when future roadway reconstruction occurs.

 

New ATM Study Considerations

 

Through recent consultations with Councillors, a number of the more dated and/or lower priority ATM study requests that were on the list previously have been removed.  In a number of such instances, staff and/or the Ward Councillor have agreed to consider other potential means of responding to the concerns that were raised.  For lower ranking study requests, where opportunities for initiating these is considered to be relatively low, there may be opportunities through ‘quick fix’ types of considerations (e.g.,  targeted enforcement, or use of speed display boards), operational or safety reviews (e.g., where significant safety issues may warrant further consideration or actions through other programs).  Staff will respond back to the request initiators, ensuring they are aware of the actions taken and of other potential opportunities for their concerns to being addressed.

 

A list of both studies that are currently underway and of study requests is included as Document 6. The list consists of four studies that are currently underway, 41 outstanding study requests that can potentially be undertaken as localized studies, five requests that are expected to warrant being undertaken as comprehensive (area wide) studies, and three new requests that have come forward since a hold was placed on study requests.

 

Council’s Motion from 26 October 2011 included direction that all outstanding ATM study requests be placed “on hold” until such time as Council makes a decision on Area Traffic Management.  In light of the actions described in this report being expected to greatly enhancing the potential for priority recommendations from new studies to proceed to implementation within a reasonable timeframe, it is recommended that the current hold be removed on localized study requests.  The hold on comprehensive studies should remain through to the end of the current term of Council or until such time that funding is available.  With removal of the hold on localized studies, staff will continue to consider initiating new studies as in-house resources permit, based on the priority ranking process as described in the ATM Guidelines.

 

The number of new studies that can be initiated in a given year can vary depending on the complexity of individual studies, the extent of staff resources required to coordinate implementation activities, and the volume of other city activities or studies that require area traffic management staff input.  For 2012, four studies are already underway and significant implementation coordination activities will take place to address the $2 million in spending.  In general, approximately five to eight new ATM localized studies can be initiated annually.

 

The Area Traffic Management Unit currently has a vacant Senior Project Engineer position and the City was unsuccessful in an earlier attempt to find a suitable candidate to fill it.  This past spring, staff placed a temporary hold on the hiring process when the proposed new Strategic Initiative on Neighbourhood Traffic Improvements was initially announced.  This Strategic Initiative since has been referred back to staff to re-prioritize existing ATM projects.  With ATM funding having been approved in the 2012 budget, with significant implementation activities planned over the coming years, and with public expectations for new studies to be initiated, the hiring process for this existing position will immediately be re-initiated.

 

 

RURAL IMPLICATIONS

 

Area Traffic Management requests/concerns from all areas of the city, including rural areas, are dealt with in the same manner.

 

 

CONSULTATION

 

Information packages were sent to all Ward Councillors in advance of this report being finalized. The package provided an overview of the approach utilized in determining priorities, along with ward specific details where councillor input was required.  All Councillors were offered an opportunity to meet with staff.

 

At the time of finalizing this report staff had meet with 10 individual Ward Councillors.  In most cases the Councillors involved were those with outstanding measures from previously approved studies already in the implementation backlog.

 

The main discussion points are summarized as follows:

 

·         Councillors, and the public, have been frustrated with delays in implementing approved measures, and in initiating new study requests;

·         Councillors appreciate the need for the prioritization process utilized for implementation and the consideration of new studies (some did have suggestions on how the prioritization process could be improved, or how the focus of the ATM program could be broadened);

·         For ensuring continued support for this program, it is important that the ATM program be perceived as serving the needs of all communities, as opposed to a select number;

·         It is often unclear to Councillors, and the public, when ATM studies are appropriate, as opposed to other types of reviews (e.g., operational or safety reviews, etc.);

·         Several Councillors concurred with the removal of dated, lower ranking recommendations from previous studies, as well as dated, lower ranking study requests from within their ward.

 

Public Works Department

 

The Public Works Department is supportive of the report recommendations and will work with the Planning and Growth Management Department to implement the recommendations subject to approval by Council.  Any non-ATM type of measures that are the responsibility of Public Works to review will be conducted using existing policies and guidelines through the various traffic programs the Department manages.

 

 

COMMENTS BY THE WARD COUNCILLORS

 

Not applicable - City-wide report.

 

 

LEGAL IMPLICATIONS:

 

There are no legal impediments to receiving the report and to implementing the recommendation in the report.

 

 

RISK MANAGEMENT IMPLICATIONS

 

There are no risk implications.

 

 

FINANCIAL IMPLICATIONS

 

$2.5 million is available within the 2012 Area Traffic Management program budget.

 

ACCESSIBILITY IMPACT

 

Staff will ensure that any applicable accessibility standards are adhered to during the execution of the projects and initiatives identified in this report.  One of the primary objectives of the ATM program is to ensure that the effect of motorized vehicles on neighbourhoods is minimized, to improve safety and the quality of life of other street users and those affected by the use of the street.

 

ENVIRONMENTAL IMPLICATIONS

 

Ensuring the effect of motorized vehicles on neighbourhoods is minimized encourages the use of alternative modes of transportation, including walking, cycling and public transit.

 

TECHNICAL IMPLICATIONS

 

There are no direct technical implications associated with this report.

 

 

CITY STRATEGIC PLAN

 

The 2011-2014 City Strategic Plan included Strategic Initiative TM3-13 – Neighbourhood Traffic Improvements, which was intended as a program that provides funding allocation equally by Ward to address community needs relating to improving traffic operations.  Council Motion 23/5, and the funding allocation approved as part of the 2012 Capital Budget, as noted in the BACKGROUND section of this report, superseded Strategic Initiative TM3-13. As a result, the 2011-2014 City Strategic Priorities will be amended to reflect this change.

 

 

SUPPORTING DOCUMENTATION

 

Document 1    Prioritization Process Utilized for Implementation of ATM Measures

Document 2    Status of Recent Area Traffic Management Studies

Document 3    ATM Measures Implementation List

Document 4    Approved ATM Studies with Outstanding Recommendations

Document 5    Outstanding Area Traffic Management Measures

Document 6    Area Traffic Management On-going Studies and Study Requests

 

 

DISPOSITION

 

Staff from the Area Traffic Management Unit will carry out the work items as identified in this report.

 

 


Prioritization Process Utilized

for Implementation of ATM Measures                                         DOCUMENT 1

 

Indicator

Point Score / Maximum Score

Local Roads

Collector Roads

Major Collector Roads

Inappropriate driver behaviour

/10

Up to 10 points if there is a history of complaints that can be verified through enforcement efforts

Generators of vulnerable street users

/10

5 points per generator of vulnerable street users (schools, parks and community centres) on or in close proximity to street

Pedestrian facilities

/10 (5 for local)

5 points if no sidewalk exists

10 points if no sidewalk exists; 5 points if one sidewalk exists

Abutting land use

/10

Up to 10 points based percentage of street frontage that is primarily residential or pedestrian-oriented retail (e.g. “main street”)

15% of vehicles traveling at or over 50 km/h or speed limit

/15

1 point for every km/h over 50 km/h (or over posted speed limit if it is greater than 50 km/h)

5% of vehicles traveling at or over 60 km/h (or if speed limit is more than 50 km/h, 15% travelling 10 km/h or more the speed limit)

/15

1 point for every km/h over 60 km/h (or 1 point for every km/h greater than 10 km/h over the posted speed limit if it is greater than 50 km/h)

Motorized traffic volumes

/15

1 point for every 100 vehicles per day over 1000

or

1 point for every 10 vehicles per hour over 120 (in the busiest hour)

1 point for every 250 vehicles per day over 2500

or

1 point for every 25 vehicles per hour over 300 (in the busiest hour)

1 point for every 350 vehicles per day over 5000

or

1 point for every 35 vehicles per hour over 600 (in the busiest hour)

Through traffic volumes

/15

1 point for every 2% in the proportion of through traffic over 20% (minimum 20 through vehicles per hour)

Collisions

/30

Ratio of collision rate to average collision rate (for streets or intersections, whichever is greatest).

                Less than 0.75                         0 points

                0.75 to 1.25                             5 points

                1.25 to 2.0                               15 points

                2.0 to 3.0                                 25 points

                Greater than 3.0                      30 points

If a vulnerable street user is involved in a collision within the most recent three-year period, the maximum of 30 points are given.

Cost

/25

Up to 25 points assigned to reflect relative costs (with lowest cost groups of measures receiving maximum points) using the following formula:

Total Score

 

 


Status of Recent Area Traffic Management Studies       DOCUMENT 2

Study

Study Completion Date

Ward

Implementation Status1

Johnwoods Street and Hartin Street

Traffic Calming Plan

2001

6

Completed

Albion Road

Corridor Study

2002

10

Completed

Beaver Ridge/Leaver/Trillium

Area Traffic Management Study

2002

9

Completed2

Billings Avenue

Traffic Study

2002

18

Completed

Booth Street

Corridor Study

2004

14

15 of 20 recommendations completed

Glebe

Traffic Management Implementation Study

2004

17

23 of 35 recommendations completed

Perth Street Revitalization

Village of Richmond: Traffic Assessment

2004

21

Completed

Delmar/Featherston/Ryder

Area Traffic Management Study

2008

18

Completed

Michele Heights

Area Traffic Management Study

2008

7

Completed

Quigley Hill Road

Area Traffic Management Study

2008

19

Completed

Abbott Street East

Area Traffic Management Study

2009

6

Completed

Carleton Heights

Area Traffic Management Study

2009

16

Completed2

Pleasant Park

Area Traffic Management Study

2009

18

Completed

Alta Vista Drive

Area Traffic Management Study

2010

18

All recommendations included on draft 2012 implementation list

Dalhousie South Community

Area Traffic Management Study

2011

14, 17

Signage changes pending, other measures did not prioritize for implementation

McKellar Park/Highland Park/Westboro

Area Traffic Management Study

2012

15

3 of 6 recommendations included on the draft 2012 implementation list.

Old Ottawa South

Area Traffic Management Study

2012

17

All recommendations included on draft 2012 implementation list

1. Of the 17 studies completed since 2001, 11 have had all recommended measures completed.

2.  All ATM measures have been implemented.  Sidewalks however, have not been completed.

Approved ATM Studies with

Outstanding Recommendations                                                       DOCUMENT 4

 

Study

Date

Ward

Sandy Hill Traffic Calming Plan

1995

12

Somerset Heights Transportation and Parking Study

1996

14

New Edinburgh Traffic Calming Study

1996

13

Centretown Traffic Calming Plan and Kent Street Traffic Calming Concept Plan

1997

14

Parkdale Area Transportation Study

1997

15

Island Park, Kirkwood, and Churchill Area Transportation Assessment and Traffic Calming Plan

1998

15

Barrhaven Traffic Study

2000

3

Main Street Transportation and Streetscaping Study

2000

17

Woodroffe Avenue Transportation Study

2000

7

Beaver Ridge/Leaver/Trillum Area Traffic Management Study

2002

9

Booth Street Corridor Study

2004

14

Glebe Traffic Management Implementation Study

2004

17

Dalhousie South Community Area Traffic Management Study

2007

14, 17

Carleton Heights Area Traffic Management Study

2009

16

Alta Vista Drive Area Traffic Management Study

2010

18

McKellar Park/Highland Park/Westboro Area Traffic Management Study

2012

15

Old Ottawa South Area Traffic Management Plan

2012

17