Brantwood Park integrated road, sewer and watermain renewal

Public information session display boards (26 June 2017)

Welcome

Welcome to the public information session for the Brantwood Park integrated road, sewer and watermain renewal project.

The purpose of this public information session is to present the preliminary design for the roadways and sidewalks and to inform residents of the upcoming construction activities.

Information regarding the sanitary sewer, storm sewer, and watermain design will be available at public information session no. 2.

Please feel free to circulate, review the information presented, discuss issues with the City and the design team and to provide your comments.

Project overview

  • Replacement of sanitary sewers and watermains
  • Replacement of sections of storm sewers
  • Replacement of the services to the property line
  • Rehabilitation of the road with new pavement structure and the replacement of existing sidewalks
  • Extension of the sidewalk on the north side of Burnham Road to Onslow Crescent

Road and sidewalk project limits [ PDF - 1.67 MB ]

Schedule

  • Review comments from this public information session
  • Finalize the preliminary design (summer 2017)
  • Finalize the detailed design (fall 2017)
  • Hold a second public Information session to review the final design in late 2017/early 2018
  • Construction is tentatively scheduled for the spring/summer of 2018 at the earliest.

Existing conditions / proposed conditions

 

Road width (existing)

Road width (proposed)

Sidewalk width (existing)

Sidewalk width (proposed)

Parking restrictions (existing)

Parking restrictions (proposed)
Letchworth Road 8.3m 8.0m 1.5m 1.8m none none
Burnham Road 9.0m 8.5m 1.5m 1.8m none none
Beckwith Road 7.25m 7.25m 1.5m 1.8m with localized narrowings none no parking on the north side
Glengarry Road 7.68m 7.5m 1.35m 1.8m with localized narrowings none no parking on the north side
Belgrave Road 9.0m 8.5m 1.35m 1.8m none none
Onslow Crescent 9.0m-9.5m 9.0m 1.35m 1.8m west side: 35m north of Elliot Avenue to Elliot Avenue
east side: 45m north of Elliot Avenue to Burnham Road
west side: 35m north of Elliot Avenue to Elliot Avenue
east side: 45m north of Elliot Avenue to Burnham Road

Letchworth Road and Burnham Road - road and sidewalk layout [ PDF - 3.05 MB ]
Beckwith Road and Glengarry Road - road and sidewalk layout [ PDF - 3.86 MB ]
Belgrave Road - road and sidewalk layout [ PDF - 3.59 MB ]
Onslow Crescent - road and sidewalk layout [ PDF - 3.76 MB ]

Letchworth Road, Burnham Road, Beckwith Road and Onslow Crescent - tree inventory [ PDF - 14.7 MB ]
Glengarry Road, Belgrave Road and Onslow Crescent - tree inventory [ PDF - 11.6 MB ]

Thank you

Thank you for your attendance. We encourage you to provide feedback on the upcoming construction by email or in writing using one of the comment sheets provided. Please deposit completed comment sheets in the box provided or mail/fax/email your comments to the address shown on the bottom of the comment sheet by July 6, 2017.

Julie Lyons, P.Eng.
Senior Engineer, Infrastructure Projects
City of Ottawa
100 Constellation Drive, 6th Floor 
Ottawa, ON  K2G 6J8
Tel: 613-580-2424 ext. 13343
Fax: 613-560-6064

All information/comments received will be maintained on file for reference during the construction period. The information collected will only be used for the purposes for which it was collected and may be shared with the Ward Councillor for a consistent purpose. With the exception of personal information, all comments will become part of the public record.

Accessible formats and communication supports are available, upon request.

Public information session (26 June 2017)

You are invited:
Monday, June 26, 2017
6 to 8 pm
Saint Paul University, Normandin Room (Room 228)
Laframboise Hall, Second Floor
249 Main Street, Ottawa, ON  K1S 1C4

The City of Ottawa invites you to attend a drop in Public Information Session to discuss a construction project planned in your neighbourhood.

At the public information session, you will be able to drop in to review the preliminary design plans for the entire project. The exhibits will illustrate the proposed roadway geometry, roadway widths and sidewalk locations. Representatives from the City, the design consultant and the ward Councillor, David Chernushenko, will be available to discuss the project and to answer your questions.

Where: The streets included as part of this project are:

  • Onslow Crescent: Elliot Avenue to Burnham Road, and through the park to Clegg Street
  • Belgrave Road
  • Glengarry Road
  • Beckwith Road from Marlowe Crescent to Onslow Crescent
  • Burnham Road
  • Letchworth Road

Who: J.L. Richards & Associates Limited, a local consulting engineering firm, has been retained by the City of Ottawa to develop preliminary and detailed design drawings and specifications for a construction contract that is to follow the design assignment.

Why: The purpose of the project is to renew the aging infrastructure on the affected streets.

What: Specifically, the works proposed include the rehabilitation and/or replacement of:

  • Sidewalks, road structure and pavement
  • Watermains and sewers
  • Lateral services to the property line

When: The current project schedule is as follows:

  • Design – Fall 2016 to Winter 2017/2018
  • Construction start – 2018 at the earliest

Accessibility is an important consideration for the City of Ottawa. If you require special accommodation, please contact the undersigned. Please note, this venue has a pay and display parking policy.

For further information about this project and/or to submit comments, please contact:

City’s project manager:
Julie Lyons, P.Eng.
Senior Engineer, Infrastructure Projects
100 Constellation Drive, Ottawa, ON  K2G 6J8
Tel.: 613-580-2424, ext. 13343

City’s consultant representative:
Philip Reeve, P.Eng.
Executive Director, Chief Municipal Engineer
J. L. Richards & Associates Limited
Tel: 613-728-3571

Comments with respect to the preliminary design shall be accepted until Friday, July 14, 2017.

Project overview (June 2017)

Project description

The City of Ottawa is undertaking the preliminary and detailed design for the renewal of infrastructure in the Brantwood Park area.  Affected streets, all or portions thereof, include Onslow Crescent, Belgrave Road, Glengarry Road, Beckwith Road, Burnham Road, Letchworth Road and Elliot Avenue.  The proposed work consists of the renewal of sewers, watermains and roadways, including sidewalks as detailed below: 

  • The streets within this area of Brantwood Park were originally serviced by combined sewers, circa 1920’s. Storm sewers were later installed between 1976 and 1981. Much of the original combined sewers remain as the sanitary sewers and are in need of replacement.  Work includes all sanitary services from the main to the property line.
  • The watermains within this area of Brantwood Park were also installed in the 1920’s and are in need of replacement.  Work includes all water services from the main to the property line.
  • Hydrant spacing for this area will be upgraded as required to meet current fire protection standards.
  • Full road reinstatement, including the replacement of the existing sidewalks.

There are a variety of programs available to residents within the project area to facilitate improvement of their services from the property line to the house, specifically:

Project timing

Preliminary and detailed design: Fall 2016 – Winter 2017/2018
Design assignment completion: Spring 2018
Construction start: 2018 at the earliest

Budget

Design: $380,000 (estimate)
Construction: $10,500,000 (estimate)

Public involvement

A public information session is being held on June 26, 2017 to present the preliminary design drawings to the public. At this time, attendees will be able to review the design, ask questions and provide comment on the proposed works.

For further information or to provide comments, please contact the City’s project manager:

Julie Lyons, P.Eng.
Senior Engineer, Infrastructure Projects
Planning, Infrastructure and Economic Development Department
Design and Construction - Branch 1
100 Constellation Drive, Sixth Floor West
Ottawa ON K2G 6J8
City of Ottawa
Tel: 613-580-2424 Ext. 13343