Welcome to the public information session for the integrated road, sewer and watermain renewal project on Dynes Road and Prince of Wales Drive.

The purpose of this public information session is to present the design and to inform residents and business owners of the upcoming construction activities.

Please feel free to circulate, review the information presented, discuss issues with the City and the design team and to provide your comments.

Project overview

  • Replacement of an existing trunk storm sewer
  • Replacement of select sanitary sewers and watermains
  • Installation of a new local storm sewer along Prince of Wales Drive (Forest Hill Avenue to Sanford Avenue)
  • Extension of 80m of watermain on Baseline Road, west of Prince of Wales Drive
  • Replacement of the services to the property line where required including the installation of backwater valves
  • Rehabilitation of the road with new pavement structure and the replacement of existing sidewalks
  • Addition of a new sidewalk on the south side of Dynes Road between Fisher Avenue and Claymor Avenue
  • Road geometry modifications along Prince of Wales Drive including new curbs, sidewalks, and cycle tracks
  • Protected intersection designs at Dynes Road and Fisher Avenue and at Dynes Road and Prince of Wales Drive\
  • Utility relocations as required
  • Modifications to on-street parking
  • Asphalt overlay of the cul-de-sac on the west side of Prince of Wales Drive opposite Forest Hill Avenue
  • Implementation of the following additional traffic calming measures:
    • Installation of two speed tables (i.e. flat top speed humps) along Dynes Road between Fisher Avenue and Prince of Wales Drive
    • Installation of a raised pedestrian crossing on Dynes Road at the Claymor Avenue intersection (at the existing signalized crossing)

Proposed underground work along Dynes Road from Fisher Avenue to Claymor Avenue [ PDF - 2.96 MB ]

Proposed underground work along Dynes Road from Claymor Avenue to Prince of Wales Drive [ PDF - 3.10 MB ]

Proposed underground work along Prince of Wales Drive from Forest Hill Avenue to 120 Metres South of Villa Crescent [ PDF - 3.18 MB ]

Proposed underground work along Prince of Wales Drive from 120 Metres north of Maryland Avenue to Dynes Road [ PDF - 1.88 MB ]

Proposed road geometry along Dynes Road from Fisher Avenue to Claymor Avenue [ PDF - 2.84 MB ]

Proposed road geometry along Dynes Road from Claymor Avenue to Prince of Wales Drive [ PDF - 2.92 MB ]

Proposed road geometry along Prince of Wales Drive from Forest Hill Avenue to 120 Metres South of Villa Crescent [ PDF - 3.05 MB ]

Proposed road geometry along Prince of Wales Drive from 120 Metres north of Maryland Avenue to Dynes Road [ PDF - 1.74 MB ]

Schedule

The project will be tendered in April 2017.

Construction will begin in the early summer of 2017 with completion in the spring/summer of 2019.

Thank you

Thank you for your attendance. We encourage you to provide feedback on the upcoming construction by email or in writing using one of the comment sheets provided. Please deposit completed comment sheets in the box provided or mail/fax/email your comments to the address shown on the bottom of the comment sheet by April 7, 2017.

All information/comments received will be maintained on file for reference during the construction period. The information collected will only be used for the purposes for which it was collected and may be shared with the Ward Councillor for a consistent purpose. With the exception of personal information, all comments will become part of the public record.

Accessible formats and communication supports are available upon request.

Public information session (30 March 2017)

Thursday, March 30, 2017
6:30 to 8:30 pm
St. Pius X High School Cafetorium
1481 Fisher Avenue, Ottawa, ON

The City of Ottawa would like to invite you to a public information session to discuss an upcoming project planned in your neighbourhood.

At the public information session you will be able to review the plans and related objectives. Representatives from the City will be available to discuss the project and answer your questions.

Accessibility is an important consideration for the City of Ottawa. If you require special accommodation, please contact the City of Ottawa project manager listed below.

If you are not available to attend the public information session, or would like additional information, please contact:

Franco Bonanno, P.Eng.
Senior Engineer, Infrastructure Projects
Design and Construction – Branch 2
Planning, Infrastructure and Economic Development  Department
City of Ottawa
100 Constellation Drive
Ottawa, ON  K2G 6J8
Tel:  613-580-2424, ext. 21775

Project overview

Project description

The City of Ottawa is undertaking the preliminary and detail design for the reconstruction of Dynes Road (Fisher Avenue to Prince of Wales Drive) and Prince of Wales Drive (Dynes Road to Forest Hill Avenue).  The existing trunk storm sewer on Dynes Road and Prince of Wales Drive is to be replaced with a larger trunk storm sewer to improve the storm sewer system.  The sanitary sewer and watermain will also be reconstructed along sections of Dynes Road and Prince of Wales Drive due to the age of the existing infrastructure.  A new local storm sewer will be constructed on Prince of Wales Drive between Forest Hill Avenue and Villa Crescent.  House or building services will be reconstructed to the property line within the limits of watermain and sewer construction.

In addition to the sewer and watermain construction, the following works are proposed:

  • Full-road reconstruction on Dynes Road (Fisher Avenue to Prince of Wales Drive) including replacing curbs, replacing existing sidewalks with 1.8m wide sidewalks and construction of a new 1.8m wide monolithic curb and sidewalk on the south side of the road between Fisher Avenue and Claymor Avenue.
  • Provision of on-street bike lanes on both sides of Dynes Road between Fisher Avenue and Prince of Wales Drive.
  • Removal of on-street parking on the south side of Dynes Road between Fisher Avenue and 847 Dynes Road to accommodate the proposed bike lanes.  Parking bays will be provided on the south side of Dynes Road between 847 Dynes Road and Morley Blvd.
  • Full-road reconstruction on Prince of Wales Drive (Dynes to Forest Hill) including new curbs, sidewalks and cycle tracks on both sides of the roadway.
  • Reconstruction of the Dynes Road / Fisher Avenue and Dynes Road / Prince of Wales Drive intersections with protected cycle-track crossings.  Parking bays will be provided on the east and west side of Prince of Wales Drive between Maryland Avenue and Villa Crescent.
  • Relocation/reconstruction of utilities, as required.

Refer to schematics below for typical road cross-section elements.

Dynes Road schematic [ PDF – 2.94 MB ]

Prince of Wales Drive schematic [ PDF – 2.92 MB ]

Tentative project timing

Design: 2016/2017
Construction start: Early Summer 2017
Construction substantial completion: Late Fall 2018
Final paving and landscaping: Spring/Summer 2019

For further information or to provide comments, please contact the City’s project manager:

Franco Bonanno, P.Eng.
Senior Engineer, Infrastructure Projects
Planning, Infrastructure and Economic Development Department
Design & Construction - Branch 2
City of Ottawa, 100 Constellation Drive
Ottawa, ON  K2G 6J8
Tel: 613-580-2424, ext. 21775