Project description

This project consists of the design and construction for the replacement of the storm sewer on Churchill Avenue North (from Highway 417 to Carling Avenue).  The work involves: 

  • Churchill Avenue North (Highway 417 to Carling Avenue):
    • Trench excavation to replace 215 metres of existing storm sewer
    • Connect to existing upstream and downstream sewers
    • Restoration of disturbed area including paving

Timelines

Design completion:               Spring 2016

Construction Start:               Summer 2016

Construction Completion:      Fall 2016

Budget

 Design and Construction: $875,000