Brantwood Park integrated road, sewer and watermain renewal

Project Status: 
Underway

Project overview (June 2017)

Project description

The City of Ottawa is undertaking the preliminary and detailed design for the renewal of infrastructure in the Brantwood Park area.  Affected streets, all or portions thereof, include Onslow Crescent, Belgrave Road, Glengarry Road, Beckwith Road, Burnham Road, Letchworth Road and Elliot Avenue.  The proposed work consists of the renewal of sewers, watermains and roadways, including sidewalks as detailed below: 

  • The streets within this area of Brantwood Park were originally serviced by combined sewers, circa 1920’s. Storm sewers were later installed between 1976 and 1981. Much of the original combined sewers remain as the sanitary sewers and are in need of replacement.  Work includes all sanitary services from the main to the property line.
  • The watermains within this area of Brantwood Park were also installed in the 1920’s and are in need of replacement.  Work includes all water services from the main to the property line.
  • Hydrant spacing for this area will be upgraded as required to meet current fire protection standards.
  • Full road reinstatement, including the replacement of the existing sidewalks.

There are a variety of programs available to residents within the project area to facilitate improvement of their services from the property line to the house, specifically:

Project timing

Preliminary and detailed design: Fall 2016 – Winter 2017/2018
Design assignment completion: Spring 2018
Construction start: 2018 at the earliest

Budget

Project funds approved to date are $10.39 million.

Public involvement

A public information session is being held on June 26, 2017 to present the preliminary design drawings to the public. At this time, attendees will be able to review the design, ask questions and provide comment on the proposed works.

For further information or to provide comments, please contact the City’s project manager:

Julie Lyons, P.Eng.
Senior Engineer, Infrastructure Projects
Planning, Infrastructure and Economic Development Department
Design and Construction Municipal Branch
100 Constellation Drive, Sixth Floor West
Ottawa ON K2G 6J8
City of Ottawa
Tel: 613-580-2424 ext. 13343

Two week look ahead schedule (November 12 to 30, 2018)

Letchworth Road

Private concrete steps - November 12 to 13, 2018
Pave driveways - November 19, 2018

Burnham Road

Private concrete steps  - November 13 to 14, 2018
Pave driveways - November 19, 2018

Beckwith Road

Private concrete steps - November 15 to 16, 2018
Pave driveways - November 19, 2018

Glengarry Road

Watermain connection - November 13, 2018
Fine grade granular B and A - November 12 to 14, 2018
Pave - November 15, 2018
Pave driveways - November 16, 2018
Adjustments - November 16, 2018
Private steps - November 19 to 20, 2018
Topsoil - November 19 to 23, 2018
Hard landscaping - November 12 to 16, 2018

Onslow Crescent

Watermain connection - November 14, 2018
Service transfers - November 14, 2018
Sidewalk - November 15 to 19, 2018
Curb - November 19 to 20, 2018
Private steps - November 21 to 23, 2018
Fine grade granular B and A - November 26 to 28, 2018
Pave - November 29, 2018
Pave driveways - November 30, 2018
Adjustments - November 30, 2018
Topsoil - November 26 to December 3, 2018
Hard landscaping - November 26 to December 3, 2018

Belgrave Road

Watermain connection - November 14 and 16, 2018
Service transfers - November 19, 2018
Sidewalk north - November 12 to 14, 2018
Sidewalk south - November 20 to 23, 2018
Private steps - November 26 to 30, 2018
Fine grade granular B and A - November 26 to 28, 2018
Pave - November 29, 2018
Pave driveways - November 30, 2018
Adjustments - November 30, 2018
Topsoil - November 26 to December 3, 2018
Hard landscaping - November 19 to December 3, 2018

Property reinstatement (May 2019)

As you are aware, the City of Ottawa has begun construction to finish up the remaining work in the Brantwood Park area. This notice is to provide an update regarding the reinstatement of properties impacted by the construction work.

Who: Ottawa Greenbelt is the contractor who will complete these replacements for the City of Ottawa.

Why: The purpose of the project is to renew the aging infrastructure on the affected streets.

What: The project works for 2019 include the completion of:

  • Sidewalks and pavement
  • Infrastructure adjustments
  • Hard landscaping, such as driveways and walkways
  • Soft landscaping, such as sod and plantings

When: This work is planned to start in early May 2019 and be finished by the end of June 2019. As per last year, a two week look ahead schedule will be available.

Where: The streets included as part of this project are:

  • Onslow Crescent from Elliot Avenue to Burnham Road, and through the park to Clegg Street
  • Belgrave Road
  • Glengarry Road
  • Beckwith Road from Marlowe Crescent to Onslow Crescent
  • Burnham Road
  • Letchworth Road

Soft landscaping

For those properties that had grass in impacted areas, the City will reinstate the area with new topsoil and sod. For those properties that had gardens in impacted areas, the City will reinstate the gardens, including new planting soil. While the City has identified many of the plant species within the project area, we want to ensure that our plant list is appropriate. The figure in the link below depicts the proposed plant species that are to be utilized throughout the project area. If you had plants that are not in this figure and would like them reinstated, please contact the contractor by Friday, May 17, 2019 via email or telephone to submit a list that identifies the type and quantity of plants impacted by construction. The contractor will endeavour to replace the impacted plants with plants of the same species; however, please keep in mind that we can only replace what is commercially available at this time.

Proposed trees, perennials, shrubs, grass and groundcover [ PDF- 1.87 MB]

Accessibility

Accessibility is an important consideration for the City of Ottawa. The City makes every effort to provide access through and around construction sites. If you require special accommodations, please contact the undersigned.

Construction disruptions

Ottawa Greenbelt will take every precaution to minimize interruptions to the normal life of your family and / or operation of your business, but as you can appreciate, there may be some inconvenience during the course of the operation of the work. We would like to thank you in advance for your patience and co-operation.

Contact information

For any emergency outside normal working hours on weekdays and weekends, please call the City at 3-1-1.

For further information about this project, please contact the City’s project manager:

City’s project manager:
Julie Lyons, P.Eng.
Senior Engineer, Infrastructure Projects
100 Constellation Drive
Ottawa, ON K2G 6J8
Tel.: 613-580-2424, ext. 13343

City’s contract administrator:
Christian Bougie, P.Eng.
Civil Engineer
J. L. Richards & Associates Limited
Tel.: 613-728-3571

City’s on-site representative:
Ken Barton, Construction Technician
Infrastructure Services, City of Ottawa
Cell: 613-762-8349

Contractor’s representative:
Renzo Burri, Assistant Operations Manager
Ottawa Greenbelt
Cell: 613-223-5054

Construction notice (April 2019)

Starting early May, the City of Ottawa will commence construction to finish up the remaining work in the Brantwood Park area.

Who: Ottawa Greenbelt is the contractor who will complete these replacements for the City of Ottawa.

Why: The purpose of the project is to renew the aging infrastructure on the affected streets.

What: The project works for 2019 include the completion of:

  • Sidewalks and pavement
  • Infrastructure adjustments
  • Hard landscaping, such as driveways and walkways
  • Soft landscaping, such as sod and plantings

When: This work is planned to start in early May 2019 and be finished by the end of June 2019. As per last year, a two week look ahead schedule will be available.

Where: The streets included as part of this project are:

  • Onslow Crescent from Elliot Avenue to Burnham Road, and through the park to Clegg Street
  • Belgrave Road
  • Glengarry Road
  • Beckwith Road from Marlowe Crescent to Onslow Crescent
  • Burnham Road
  • Letchworth Road

Accessibility

Accessibility is an important consideration for the City of Ottawa. The City makes every effort to provide access through and around construction sites. If you require special accommodations, please contact the undersigned.

Construction disruptions

Ottawa Greenbelt will take every precaution to minimize interruptions to the normal life of your family and / or operation of your business, but as you can appreciate, there may be some inconvenience during the course of the operation of the work. We would like to thank you in advance for your patience and co-operation.

Contact information

For any emergency outside normal working hours on weekdays and weekends, please call the City at 3-1-1.

For further information about this project, please contact the City’s project manager:

City's project manager:
Julie Lyons, P.Eng.
Senior Engineer, Infrastructure Projects
100 Constellation Drive
Ottawa, ON K2G 6J8
Tel.: 613-580-2424, ext. 13343

City’s contract administrator:
Christian Bougie, P.Eng.
Civil Engineer
J. L. Richards & Associates Limited
Tel.: 613-728-3571

City’s on-site representative:
Ken Barton, Construction Technician
Infrastructure Services, City of Ottawa
Cell: 613-762-8349

Contractor’s representative:
Renzo Burri
Assistant Operations Manager
Ottawa Greenbelt
Cell: 613-223-5054

Private water services notice (August 2018)

As you are aware, the City of Ottawa has begun construction on the new sewers, watermains, roads and sidewalks, within the Brantwood Park area. This notice is to provide an update in regarding to the replacement of water service laterals.

Who:  Ottawa Greenbelt is the contractor who will complete these replacements for the City of Ottawa.

Why: The purpose of the project is to renew the aging infrastructure on the affected streets.

What: The project works include the rehabilitation and/or replacement of:

  • Sidewalks, road structure and pavement
  • Watermains and sewers
  • Lateral services to the property line

When: This work is planned to continue through the summer and fall, and be substantially finished by the end of November, with completion by the summer of 2019.

Where: The streets included as part of this project are:

  • Onslow Crescent from Elliot Avenue to Burnham Road, and through the park to Clegg Street
  • Belgrave Road
  • Glengarry Road
  • Beckwith Road from Marlowe Crescent to Onslow Crescent
  • Burnham Road
  • Letchworth Road

Private water services

As previously noted in other notices and during the Public Information sessions, there is the possibility of lead water services due to the age of the neighbourhood.  There is information available on the City’s website Ottawa.ca regarding lead in drinking water, how to determine if you have lead plumbing pipes and the City’s Lead Pipe replacement Program.  The City will also notify you if we find lead services during excavation.

The City will only replace the City-owned portion of the water service between the watermain and your front property line, at not cost to you. The private section of the water service (on your property) between the front property line and your building is known as the private water service. The private water service will not be replaced as part of the City project.

We have received many enquiries regarding lead water services and the options for replacement of said services on private property, from the property line to the building foundation.  The Contractor has let us know that they will not be replacing private services due to time constraints and the amount of work required to be completed. If you have a lead water service and wish to replace it, the remaining options are outlined below.

Option 1

You may choose to do the work yourself by hiring your own contractor. The only constraint is that you may not carry out your work while the City is working on the street and replacing your water service up to your property line. Concurrent work on your adjacent land may create a safety hazard for the City’s contractor and/or for your contractor. Once the City’s work is complete, you may replace your private water service at any time thereafter.

Option 2

The City does have a Lead Pipe Replacement Program where the City carries out the replacement on behalf of the property owner; however, it is not set up to work with any concurrent City road, sewer or watermain construction. The program covers the replacement of both the private water service and the City-owned portion of the water service when no other City construction is planned. Since, as part of the current City project, the water service will be replaced up to your front property line, the Lead Pipe Replacement Program will only be available to you up to 2 years after the completion of the planned watermain work. Under the Lead Pipe Replacement Program, the City cannot replace the private water service until the watermain work is completed for the same safety reasons described in Option 1. Please note that you are responsible for all costs under this program. Please contact the Water and Wastewater Services Customer Information at 3-1-1 (TTY: 613-580-2401) ext. 22300 if you have further questions about the Program. You can also find information of the City’s website https://ottawa.ca/en/residents/water-and-environment/drinking-water/drinking-water-programs.

Accessibility

Accessibility is an important consideration for the City of Ottawa. The City makes every effort to provide access through and around construction sites. If you require special accommodations, please contact the undersigned.

Construction disruptions

Ottawa Greenbelt will take every precaution to minimize interruptions to the normal life of your family and / or operation of your business, but as you can appreciate, there may be some inconvenience during the course of the operation of the work. We would like to thank you in advance for your patience and co-operation.

Contact information

For any emergency outside normal working hours on weekdays and weekends, please call the City at 3-1-1.

For further information about this project, please contact the City’s project manager:

City’s project manager:
Julie Lyons, P.Eng.
Senior Engineer, Infrastructure Services
100 Constellation Drive, Ottawa, ON K2G 6J8
Tel.: 613-580-2424, ext. 13343

City’s contract administrator:
Christian Bougie, P.Eng.
Civil Engineer
J. L. Richards & Associates Limited
Tel.: 613-728-3571

City’s on-site representative:
Kevin May, Construction Technician
Infrastructure Services, City of Ottawa
Cell: 613-862-3075

Contractor’s representative:
Renzo Burri, Assistant Operations Manager
Ottawa Greenbelt
Cell: 613-223-5054

General construction schedule (June 2018)

In early May, Ottawa Greenbelt began their pre-construction surveys and investigations for construction of the new sewers, watermains, roads and sidewalks, within the Brantwood Park area. Late May to early June has seen the start of temporary water servicing.

Who: Ottawa Greenbelt is the contractor who will complete these replacements for the City of Ottawa.

Why: The purpose of the project is to renew the aging infrastructure on the affected streets.

What: The project works include the rehabilitation and/or replacement of:

  • sidewalks, road structure and pavement
  • watermains and sewers
  • lateral services to the property line

Where: The streets included as part of this project are:

  • Onslow Crescent from Elliot Avenue to Burnham Road, and through the park to Clegg Street
  • Belgrave Road
  • Glengarry Road
  • Beckwith Road from Marlowe Crescent to Onslow Crescent
  • Burnham Road
  • Letchworth Road

When: This work is underway and will be substantially finished by the end of November 2018, with completion by the summer of 2019.

The following is a general construction schedule, as provided by Ottawa Greenbelt.

The installation of temporary water services is anticipated to be completed in the following order:

  • Letchworth Road by the end of June;
  • Burnham Road by the beginning of July;
  • Beckwith Road by the end of July;
  • Belgrave Road by the beginning of August;
  • Glengarry Road by the end of August; and
  • Onslow Crescent by the beginning of September.

The construction of the sewers and watermain is anticipated to be carried out in the following order:

  • Letchworth Road between the end of June and the end of July;
  • Burnham Road between the beginning of July and the end of July;
  • Beckwith Road between the end of July and the end of August;
  • Belgrave Road between the beginning of August and mid-September;
  • Glengarry Road between the end of August and mid-October; and
  • Onslow Crescent between the beginning of September and the end of October.

The first course of roadway paving and the construction of curbs and sidewalks is anticipated to be carried out in the following order:

  • Letchworth Road between the end of July and mid-August;
  • Burnham Road between the end of July and mid-August;
  • Beckwith Road between the end of August and the end of September;
  • Belgrave Road between mid-September and mid-October;
  • Glengarry Road between mid-October and the beginning of November; and
  • Onslow Crescent between the end of October and the end of November.

Landscaping for the above mentioned streets is anticipated to start mid-August, with completion by the end of November.  Landscaping will generally follow the first course roadway paving and the installation of curbs and sidewalks on each street.

Work in Brantwood Park is anticipated from mid-September to the beginning of November. Landscaping in this area is anticipated to be completed by the end of November, with the final course of roadway paving to be completed in 2019.

As with all construction schedules, the schedule outlined above is subject to change without notice based on a variety of factors, such as availability of materials, labour, weather, unexpected site conditions, etc.

Residents can also contact the City’s on-site representative, Kevin May, contact information below, for current construction status, or if specific scheduling is needed.

Accessibility

Accessibility is an important consideration for the City of Ottawa. The City makes every effort to provide access through and around construction sites. If you require special accommodations, please contact the undersigned.

Construction disruptions

Ottawa Greenbelt will take every precaution to minimize interruptions to the normal life of your family and / or operation of your business, but as you can appreciate, there may be some inconvenience during the course of the operation of the work. We would like to thank you in advance for your patience and co-operation.

Contact information

For any emergency outside normal working hours on weekdays and weekends, please call the City at 3-1-1.

For further information about this project, please contact the City’s project manager:

City’s project manager:
Julie Lyons, P.Eng.
Senior Engineer, Infrastructure Projects
100 Constellation Drive, Ottawa, ON K2G 6J8
Tel.: 613-580-2424, ext. 13343

City’s contract administrator:
Christian Bougie, P.Eng.
Civil Engineer
J. L. Richards & Associates Limited
Tel.: 613-728-3571

City’s on-site representative:
Kevin May, Construction Technician
Infrastructure Services, City of Ottawa
Cell: 613-862-3075

Contractor’s representative:
Gary McNulty, Site Superintendent
Ottawa Greenbelt
Cell: 613-229-8553

Construction notice (April 2018)

Starting early May, the City of Ottawa will begin construction on the new sewers, watermains, roads and sidewalks, within the Brantwood Park area. Pre-construction surveys and investigation will take place prior to any ground breaking.

Who: Ottawa Greenbelt is the contractor who will complete these replacements for the City of Ottawa.

Why: The purpose of the project is to renew the aging infrastructure on the affected streets.

What: The project works include the rehabilitation and/or replacement of:

  • Sidewalks, road structure and pavement
  • Watermains and sewers
  • Lateral services to the property line

When: This work is planned to start in early May 2018 and be substantially finished by the end of November, with completion by the summer of 2019.

Where: The streets included as part of this project are:

  • Onslow Crescent from Elliot Avenue to Burnham Road, and through the park to Clegg Street
  • Belgrave Road
  • Glengarry Road
  • Beckwith Road from Marlowe Crescent to Onslow Crescent
  • Burnham Road
  • Letchworth Road

Accessibility

Accessibility is an important consideration for the City of Ottawa. The City makes every effort to provide access through and around construction sites. If you require special accommodations, please contact the undersigned.

Construction disruptions

Ottawa Greenbelt will take every precaution to minimize interruptions to the normal life of your family and / or operation of your business, but as you can appreciate, there may be some inconvenience during the course of the operation of the work. We would like to thank you in advance for your patience and co-operation.

Contact information

For any emergency outside normal working hours on weekdays and weekends, please call the City at 3-1-1.

For further information about this project, please contact the City’s project manager:

City’s project manager:
Julie Lyons, P.Eng.
Senior Engineer, Infrastructure Projects
100 Constellation Dr., Ottawa, ON K2G 6J8
Tel.: 613-580-2424, ext. 13343

City’s contract administrator:
Christian Bougie, P.Eng.
Civil Engineer
J. L. Richards & Associates Limited
Tel.: 613-728-3571

City’s on-site representative:
Kevin May, Construction Technician
Infrastructure Services, City of Ottawa
Cell: 613-862-3075

Contractor’s representative:
Gary McNulty, Site Superintendent
Ottawa Greenbelt
Cell: 613-229-8553

Pre-construction survey notice (May 2018)

DST Consulting Engineers Inc. is retained by Greenbelt Construction Ltd. on behalf of the City of Ottawa to carry out a pre-construction survey of the homes and buildings affected by the construction activities for the project noted above.

The purpose of the survey is to obtain videotaped and/or photographic records of the existing conditions of the interior and exterior of the affected buildings within the construction zone. This information may be of future assistance to all parties involved in the unlikely event that damage is caused to the building during construction operations. The time of the survey will depend on the size of your home or building. The survey is free of charge to the building/home owner.

All videotaped and/or photographic records collected by DST remain confidential and are handled in a manner that is compliant with the Municipal Freedom of Information and Protection of Privacy Act. Furthermore, in order to maintain impartiality should a legal claim for damages arise in the future, all collected records will be stored at DST Ottawa office and will not be released without your consent.

The surveys will commence on May 4, 2018. Therefore, please contact Kaitlin at 613-748-1415 to book an appointment as soon as possible. You may also send an e-mail with your name, address, phone number and availability.

Please note that if we are unable to reach you, and in order to protect your property, DST will survey the exterior of your home in your absence. If you do not wish for us to enter your property, please notify us as soon as possible.

Thank you in advance for your co-operation and patience. We look forward to hearing from you soon.

Shady Gebara, P.Eng.
Project Manager
DST Consulting Engineers Inc.
2150 Thurston Drive, Suite 203
Ottawa, ON K1G 5T9
Tel: 613-748-1415
Fax: 613-748-1356

Public information session display boards (November 30, 2017)

Thursday, November 30, 2017
6 to 8 pm
Saint Paul University
Room L120, Ground Floor
233 Main Street, Ottawa, ON  K1S 1C4

Welcome

Welcome to the public information session for the Brantwood Park integrated road, sewer and watermain renewal project.

The purpose of this public information session is to present the design and to inform residents of the upcoming construction activities.

Please feel free to circulate, review the information presented, discuss issues with the City and the design team and to provide your comments.

Project overview

  • Replacement of sanitary sewers and watermains
  • Replacement of sections of storm sewers
  • Replacement of the services to the property line
  • Rehabilitation of the road with new pavement structure and the replacement of existing sidewalks
  • Extension of the sidewalk on the north side of Burnham Road to Onslow Crescent

Project limits [ PDF- 1.59 MB]

Schedule

  • Review comments from this Public Information Session
  • Finalize the drawings and tender the project in the winter of 2018
  • Begin construction in the spring of 2018
  • Complete final paving and landscaping in the summer of 2019

Existing conditions / proposed conditions

  Road width (existing) Road width (proposed) Sidewalk width (existing) Sidewalk width (proposed) Parking restrictions (existing) Parking restrictions (proposed)
Letchworth Road 8.3m 8.0m 1.5m 1.8m none none
Burnham Road 9.0m 8.5m 1.5m 1.8m none none
Beckwith Road 7.25m 7.25m 1.5m 1.8m with localized narrowings none no parking on the north side (December 1 to March 31)
Glengarry Road 7.68m 7.5m 1.35m 1.8m with localized narrowings none no parking on the north side (December 1 to March 31)
Belgrave Road 9.0m 8.5m 1.35m 1.8m none none
Onslow Crescent 9.0m - 9.5m 9.0m 1.35m 1.8m west side: 35m north of Elliot Avenue to Elliot Avenue
east side: 45m north of Elliot Avenue to Burnham Road
west side: 35m north of Elliot Avenue to Elliot Avenue
east side: 45m north of Elliot Avenue to Burnham Road

Onslow Crescent [ PDF- 1.43 MB]

Letchworth Road and Burnham Road [ PDF- 1.13 MB]

Beckwith Road and Glengarry Road [ PDF- 2.65 MB]

Belgrave Road [ PDF- 1.88 MB]

Letchworth Road, Burnham Road and Onslow Crescent - landscape plan [ PDF- 4.34 MB]

Beckwith Road, Glengarry Road and Onslow Crescent - landscape plan [ PDF- 4.70 MB]

Belgrave Road and Onslow Crescent - landscape plan [ PDF- 4.84 MB]

Proposed trees, perennials, shrubs, grass and groundcover [ PDF- 1.87 MB]

Thank you

Thank you for your attendance. We encourage you to provide feedback on the upcoming construction by email or in writing using one of the comment sheets provided. Please deposit completed comment sheets in the box provided or mail/fax/email your comments to the address shown on the bottom of the comment sheet by December 22, 2017.

Julie Lyons, P.Eng.
Senior Engineer, Infrastructure Projects
City of Ottawa
100 Constellation Drive, 6th Floor
Ottawa, ON  K2G 6J8
Tel: 613-580-2424 ext. 13343
Fax: 613-560-6064

All information/comments received will be maintained on file for reference during the construction period. The information collected will only be used for the purposes for which it was collected and may be shared with the Ward Councillor for a consistent purpose. With the exception of personal information, all comments will become part of the public record.

Accessible formats and communication supports are available.

Public information session display boards (June 26, 2017)

Monday, June 26, 2017
6 to 8 pm
Saint Paul University, Normandin Room (Room 228)
Laframboise Hall, Second Floor
249 Main Street, Ottawa, ON K1S 1C4

Welcome

Welcome to the public information session for the Brantwood Park integrated road, sewer and watermain renewal project.

The purpose of this public information session is to present the preliminary design for the roadways and sidewalks and to inform residents of the upcoming construction activities.

Information regarding the sanitary sewer, storm sewer, and watermain design will be available at public information session no. 2.

Please feel free to circulate, review the information presented, discuss issues with the City and the design team and to provide your comments.

Project overview

  • Replacement of sanitary sewers and watermains
  • Replacement of sections of storm sewers
  • Replacement of the services to the property line
  • Rehabilitation of the road with new pavement structure and the replacement of existing sidewalks
  • Extension of the sidewalk on the north side of Burnham Road to Onslow Crescent

Road and sidewalk project limits [ PDF - 1.67 MB ]

Schedule

  • Review comments from this public information session
  • Finalize the preliminary design (summer 2017)
  • Finalize the detailed design (fall 2017)
  • Hold a second public Information session to review the final design in late 2017/early 2018
  • Construction is tentatively scheduled for the spring/summer of 2018 at the earliest.

Existing conditions / proposed conditions

 

Road width (existing)

Road width (proposed)

Sidewalk width (existing)

Sidewalk width (proposed)

Parking restrictions (existing)

Parking restrictions (proposed)
Letchworth Road 8.3m 8.0m 1.5m 1.8m none none
Burnham Road 9.0m 8.5m 1.5m 1.8m none none
Beckwith Road 7.25m 7.25m 1.5m 1.8m with localized narrowings none no parking on the north side
Glengarry Road 7.68m 7.5m 1.35m 1.8m with localized narrowings none no parking on the north side
Belgrave Road 9.0m 8.5m 1.35m 1.8m none none
Onslow Crescent 9.0m-9.5m 9.0m 1.35m 1.8m west side: 35m north of Elliot Avenue to Elliot Avenue
east side: 45m north of Elliot Avenue to Burnham Road
west side: 35m north of Elliot Avenue to Elliot Avenue
east side: 45m north of Elliot Avenue to Burnham Road

Letchworth Road and Burnham Road - road and sidewalk layout [ PDF - 3.05 MB ]
Beckwith Road and Glengarry Road - road and sidewalk layout [ PDF - 3.86 MB ]
Belgrave Road - road and sidewalk layout [ PDF - 3.59 MB ]
Onslow Crescent - road and sidewalk layout [ PDF - 3.76 MB ]

Letchworth Road, Burnham Road, Beckwith Road and Onslow Crescent - tree inventory [ PDF - 14.7 MB ]
Glengarry Road, Belgrave Road and Onslow Crescent - tree inventory [ PDF - 11.6 MB ]

Thank you

Thank you for your attendance. We encourage you to provide feedback on the upcoming construction by email or in writing using one of the comment sheets provided. Please deposit completed comment sheets in the box provided or mail/fax/email your comments to the address shown on the bottom of the comment sheet by July 6, 2017.

Julie Lyons, P.Eng.
Senior Engineer, Infrastructure Projects
City of Ottawa
100 Constellation Drive, 6th Floor 
Ottawa, ON  K2G 6J8
Tel: 613-580-2424 ext. 13343
Fax: 613-560-6064

All information/comments received will be maintained on file for reference during the construction period. The information collected will only be used for the purposes for which it was collected and may be shared with the Ward Councillor for a consistent purpose. With the exception of personal information, all comments will become part of the public record.

Accessible formats and communication supports are available, upon request.