Elmridge Park Splash Pad

Project Status: 
Underway

Overview

The old children’s spray post and pad in Elmridge Park is being replaced under the lifecycle replacement program with an updated splash pad. The new splash pad will be relocated within the park to allow for the extra space needed to meet current standards. The old post and pad will be removed and reinstated as a grass. The community is invited to provide input on the proposed concepts.

Construction is scheduled for fall 2019, with the splash pad being fully operational in 2020. All other areas of the park will be available for use during construction.

The community is invited to provide comments on the proposed concept plan, as shown below.

Option 1 [ PDF - 1.75 MB ]
Option 2 [ PDF - 1.57 MB ]

If you wish to provide comments please send, no later than April 16, 2019 to the Park Planner listed below.

Update: August 6, 2019

Option B was the preferred option. Construction anticipated fall 2019; completion and opening 2020.

Contact

Jennifer Shepherd, Parks Planner
Parks & Facilities Planning Branch
Recreation, Cultural and Facility Services Department
City of Ottawa
613-580-2424 ext. 13771
Jennifer.Shepherd@ottawa.ca