Lepage Avenue, Larkin Street, Larose Avenue – Road, Sewer, Watermain

On this page
Project status
Underway

Project overview

Project description

The City of Ottawa is undertaking the design and construction to replace the existing sanitary sewers and watermains on sections of Lepage Avenue, Larkin Street and Larose Avenue. The existing sanitary sewers and watermains and select sections of the storm sewers have reached the end of life and require replacement. The project limits are highlighted on Figure 1:

This is an image of a key map showing the project limits, including Larkin Street, Larose Avenue between McBride and Larkin Streets, and Lepage Avenue between Larkin and Cavan Streets.

The proposed work includes:

  • LAROSE Avenue from McBride Street to Larkin Avenue
    • Replacement of watermain and service connections
    • Replacement of sanitary sewer main and service connections
    • Replacement of stormwater sewer main and catch basins
    • Full road reconstruction with traffic calming measures
    • New concrete sidewalk on north side of street
    • New curb on south side of street
  • LEPAGE Avenue from Cavan Street to Larkin Street
    • Replacement of watermain and service connections
    • Replacement of sanitary sewer main and service connections
    • Replacement of stormwater sewer main and catch basins
    • Full road reconstruction with traffic calming measures
    • New curbs
  • LARKIN Avenue from Lepage Avenue to Laperriere Avenue
    • Replacement f sanitary sewer main and connections
    • Full rad reconstruction with traffic calming measures
    • New concrete sidewalk on west side of street
    • New curbs n east side of street

Project timing

2021 Construction start:

  • The contractor will mobilize to the job site end of July/beginning of August 2021.
  • Work will proceed with excavation work on Lepage Avenue between Cavan Street and Larkin Street starting with the installation of temporary watermains and followed by the replacement of the mainline watermains and sewers
  • Base lift asphalt paving and landscaping re-instatement along Lepage Avenue between Cavan Street and Larkin Street to be completed by end of 2021
  • Installation of the underground services at the following locations will also take place fall 2021/early winter 2022:
    • Larkin Street and Larse Avenue
    • Larkin Street and Raven Avenue
    • Larkin Street and Chatelaine Avenue
    • Larkin Street and Lepage Avenue

2022

  • All underground infrastructure work has been completed. 
  • Base lift of asphalt completed. 
  • Driveways re-instated.

2023
Final landscaping and top lift of asphalt will take place in spring/early summer 2023 when sod is available.

Project budget

Approved project funds to date are $7,434,000.

Public engagement

A public information session was held in the fall of 2019, to present the design drawings to the public. At that time attendees were able to review the design, ask questions and provide comments on the proposed works.

Accessibility

Accessibility is an important consideration for the City of Ottawa. The City makes every effort to provide access through and around construction sites. If you require a disability-related accommodation, please contact the project team listed below. Accessible formats and communication supports are available, upon request.

COVID-19

The City of Ottawa, in its commitment to protecting people and the community, continues to work closely with the industry and to comply with recommendations provided by municipal, provincial and federal health officials, as well as the Ministry of Labour, Training and Skills Development.

Contact information

For any emergency outside normal working hours, please call the City at 3-1-1.
For general project information, please contact the City’s Project Manager.
For construction related questions or concerns, please contact the Contractor Representatives.

City Project Manager
Kevin Gibbs, P.Eng.
Senior Engineer, Infrastructure Projects
100 Constellation Drive, Ottawa, ON K2G 6J8
Tel.: 613-580-2424 ext. 16633

Contract Administrator
Daniel Lefebvre, C.E.T.
J.L. Richards & Associates Limited
Tel.: 343-804-5372

City On-Site Representative
Dustin MacPhail
Construction Technician
City of Ottawa
Tel.: 613-807-5306

Contractor Representatives
Travis Jones, P.Eng.
Project Manager
AECON Construction Ontario East Limited
Tel.: 613-314-7690

Sheldon Wells
Site Superintendent
AECON Construction Ontario East Limited
Tel.: 613-315-7403

Construction notice (March 2022)

In April 2022, the City of Ottawa will resume construction for the replacement of underground sewers and watermains, and a full road reconstruction in your neighbourhood.

What: The Contractor is expected to complete the following works:

  • Tree pruning on Larose Avenue and Larkin Street
  • Underground sewer and watermain replacement on Larose Avenue, including installation of temporary water services
  • Underground sewer replacement on Larkin Street
  • Base course paving in some locations on Larkin Street and Larose Avenue and temporary road reinstatement as required
  • Curbs and sidewalk reinstatement at Lepage Avenue / Cavan Street
  • Final Landscaping along Lepage Avenue
  • Traffic calming measures throughout the project limits
  • Installation of a new sidewalk on the west side of Larkin Street
  • Replacement of the existing sidewalk on the north side of Larose Avenue

Why: This work is required to renew the aging infrastructure and to improve reliability. The implementation of traffic calming measures is intended to improve safety and help to reduce vehicle speeds.

Where: The streets included as part of this project are:

  • Larkin Street, between Lepage Avenue and Laperriere Avenue
  • Lepage Avenue, between Larkin Street and Cavan Street
  • Larose Avenue, between McBride Street and Larkin Street

When: This work is tentatively planned to recommence in April 2022 with the installation of temporary water servicing on Larose Avenue followed by sewer and watermain reconstruction on Larose Avenue, and sewer reconstruction on Larkin Street throughout the summer/fall 2022.

Some sections of base course asphalt and hard landscaping will be completed in late 2022, where required, temporary road reinstatements are anticipated to be installed ahead of the winter shut down.

Local road closures are expected on Larose Avenue, from April 4 to September 2, 2022 and on Larkin Street from May 2, 2022 to September 30, 2022.

The remainder of the works, including surface course asphalt, remaining sidewalk and curb and final landscaping being completed in 2023.

Who: The City of Ottawa has retained the contractor, AECON Construction Ontario East Limited, to complete the work.

Traffic management

In order to accommodate the proposed construction, Larkin Street, Lepage Avenue and Larose Avenue will be closed to all but local traffic while construction is taking place. Access to private properties including pedestrian and cycling access, will be maintained throughout the construction period unless otherwise communicated.

On-street parking and local access

As the various road reconstruction activities are in progress, on-street parking will be restricted. Local access will be maintained to residents, schools, parks and emergency vehicles.

The Contractor is required to ensure that homeowners have access to their property. In the event that access to your driveway is restricted for a short period due to construction activities, you will be contacted in advance by the project team and given a temporary On-Street Parking Permit that will allow on-street parking within two blocks of your residence when these disruptions occur.

Impact on the right of way and adjacent private properties

The reconstruction is within the City’s right of way but may result in some disruption to part of the private property directly adjacent to the work. The City will reinstate sections of landscaping, driveways and walkways that are disturbed by construction. However, if you have plants or any other assets located within the City’s right of way that you want to preserve, we suggest that you move the plants in preparation for the construction work.

Lawn irrigation systems

If you own a subsurface lawn irrigation system, please notify the City Project Manager identified below.

Pre-construction inspection

The Contractor already completed exterior pre-construction inspections of consenting homes in the work area in 2021. The purpose of the pre-construction survey was to document current building and landscape conditions before construction commences.

As part of this Contract, the Contractor is assuming full responsibility for the construction work until it is entirely complete as well as any damages to private property resulting from these construction activities. In the event of such occurrences, all claims for damages should be immediately reported both verbally and in writing to the Contractor and to the City on-site Representative. This will ensure prompt notification of appropriate authorities to complete the claim investigations.

Tree pruning

To facilitate the use of heavy equipment, the Contractor will be required to contract a certified arborist to complete pre and post-construction tree pruning on existing trees within the City’s right of way. City of Ottawa Forestry will be consulted prior to any pruning operations occurring on City of Ottawa owned trees.

Temporary water services

During the replacement of the watermain on Larose Avenue, water will be supplied to buildings by temporary water lines. While your property is on this temporary service, your water usage will be estimated as the temporary service is not metered. Your water bill will be based on the past average water usage for your address. If you have any questions regarding your water bill, please contact Revenue at 613-580-2444 or by email at WS-Billing@ottawa.ca.

Municipal fire suppression will continue during the construction period. Please note that private fire suppression systems may be impacted due to temporary water lines. If you have a private fire suppression system, it is recommended that you make arrangements with a fire protection services company in order to determine the extent of any impact. For information on minimizing your fire risk, contact the City’s Fire Services at 613-580-2424 ext. 15371 (East) or ext. 15372 (West).

We apologize in advance for any disruptions in water service during construction. Any problems with the temporary water services can be directed to the City on-site representative or call the City of Ottawa at 3-1-1 in the evenings or weekends.

Private water services

If your house/building was built prior to 1955, there is a possibility that your private water service may have been constructed using lead pipe (modern pipes are copper or HDPE). For those homes with a lead water pipe supplying water to the water meter, there is information regarding the City’s Lead Pipe Replacement Program available on the City’s website or call 3-1-1.

Construction disruptions

The Contractor will take every precaution to minimize interruptions to the everyday life of your family and/or operation of your business, but, as you can appreciate, there may be some inconvenience during the course of the work, such as traffic delays, noise and dust. You may also feel vibrations due to heavy equipment operations. Vibrations from construction activities are quite common and rarely cause any problems. We would like to thank you for your patience and co-operation. For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255).

Construction Notice (July 2021)

In late July 2021, the City of Ottawa will begin construction for the replacement of underground sewers and watermains, and a full road reconstruction in your neighbourhood.

What: The work involves the replacement of underground sewers and watermains, and full road reconstruction, including the installation of vertical and horizontal traffic calming measures. It also includes the installation of a new sidewalk on the west side of Larkin Street, from Lepage Avenue to Laperriere Avenue, and the replacement of the sidewalk on the north side of Larose Avenue, from McBride Street to Larkin Street.

Why: This work is required to renew the aging infrastructure and to improve reliability.

Where: The streets included as part of this project are:

  • Larkin Street, between Lepage Avenue and Laperriere Avenue
  • Lepage Avenue, between Larkin Street and Cavan Street
  • Larose Avenue, between McBride Street and Larkin Street

When: This work is tentatively planned to begin in late July 2021 and be completed by summer 2023.

Who: The City of Ottawa has retained the contractor, AECON Construction Ontario East Limited, to complete the work.

Accessibility

Accessibility is an important consideration for the City of Ottawa. The City makes every effort to provide access through and around construction sites. If you require special accommodations, please contact the undersigned. Accessible formats and communication supports are available, upon request, at the following link: www.ottawa.ca/accessibleformat

Traffic Management

In order to accommodate the proposed construction, Larkin Street, Lepage Avenue and Larose Avenue will be closed to all but local traffic while construction is taking place.

Access to private properties including pedestrian and cycling access, will be maintained throughout the construction period unless otherwise communicated.

On-Street Parking and Local Access

As the various road reconstruction activities are in progress, on-street parking will be restricted. Local access will be maintained to residents, schools, parks and emergency vehicles.

The Contractor is required to ensure that homeowners have access to their property. In the event that access to your driveway is restricted for a short period due to construction activities, you will be contacted in advance by the project team and given a temporary On-Street Parking Permit that will allow on-street parking within two blocks of your residence when these disruptions occur.

Impact on the Right of Way and Adjacent Private Properties

The reconstruction is within the City’s right of way but may result in some disruption to part of the private property directly adjacent to the work. The City will reinstate sections of landscaping, driveways and walkways that are disturbed by construction. However, if you have plants or any other assets located within the City’s right of way that you want to preserve, we suggest that you move the plants in preparation for the construction work.

Lawn Irrigation Systems

If you own a subsurface lawn irrigation system, please notify the City Project Manager identified below.

Pre-Construction Inspection

The Contractor will be completing interior and exterior pre-construction inspections of consenting homes in the work area, if the homeowner is in agreement. The purpose of the pre-construction survey is to document current building and landscape conditions before construction commences. In addition, you may wish to complete your own survey of pre-construction conditions on your property. Your survey should include photographs.

As part of this Contract, the Contractor is assuming full responsibility for the construction work until it is entirely complete as well as any damages to private property resulting from these construction activities. In the event of such occurrences, all claims for damages should be immediately reported both verbally and in writing to the Contractor and to the City on-site Representative. This will ensure prompt notification of appropriate authorities to complete the claim investigations.

Temporary Water Services

During the replacement of the watermain on Lepage Avenue and Larose Avenue, water will be supplied to buildings by temporary water lines. While your property is on this temporary service, your water usage will be estimated as the temporary service is not metered. Your water bill will be based on the past average water usage for your address. If you have any questions regarding your water bill, please contact Revenue at 613-580-2444 or by email at WS-Billing@ottawa.ca.

Municipal fire suppression will continue during the construction period. Please note that private fire suppression systems may be impacted due to temporary water lines. If you have a private fire suppression system, it is recommended that you make arrangements with a fire protection services company in order to determine the extent of any impact. For information on minimizing your fire risk, contact the City’s Fire Services at 613-580-2424 ext. 15371 (East) or ext. 15372 (West).

We apologize in advance for any disruptions in water service during construction. Any problems with the temporary water services can be directed to the City on-site representative or call the City of Ottawa at 3-1-1 in the evenings or weekends.

Private Water Services

If your house/building was built prior to 1955, there is a possibility that your private water service may have been constructed using lead pipe (modern pipes are copper or HDPE). For those homes with a lead water pipe supplying water to the water meter, there is information regarding the City’s Lead Pipe Replacement Program available on the City’s website, Ottawa.ca/leadpipes, or call 3-1-1.

Construction Disruptions

The Contractor will take every precaution to minimize interruptions to the everyday life of your family and/or operation of your business, but, as you can appreciate, there may be some inconvenience during the course of the work, such as traffic delays, noise, dust and vibration. You may also feel vibrations due to heavy equipment operations. Vibrations from construction activities are quite common and rarely cause any problems. We would like to thank you for your patience and co-operation. For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255).

Project update (July 2021)

As part of the City’s ongoing commitment to mitigate construction impacts to residents and business and maintain service delivery, there are regular meetings with coordinating City departments and external agencies to plan, organize and assess all construction projects in the city. The Lepage, Larkin, Larose Infrastructure Renewal Project was coordinated with LRT work, resulting in the project being tendered in 2021. As a result of the public tendering process, the City has retained the contractor AECON Construction Ontario East Limited, to complete the work.

The City has a proactive approach to communications and will provide updates on the timeline of the project as they become available.

Traffic Calming Measures (June 2020)

The City of Ottawa is undertaking the design and construction to replace the existing sanitary sewers and watermains on sections of Lepage Avenue, Larkin Street and Larose Avenue. The existing and aged sanitary sewers and watermains and select sections of the storm sewers require replacement. The project is expected to start in the summer of 2020 and scheduled to be completed by fall 2022.

What: In December 2019, Council approved the principles of a Safe Systems approach to road safety in road design and that when reconstruction occurs on local residential streets, these roads be designed for a 30 km/h operating speed.

Why: To align with the Safe Systems approach, additional traffic measures on the roads listed below will be implemented as part of the project.

When: Construction is expected to start in summer 2020 and is expected to be completed by fall 2022.

Where: Curb extensions (horizontal traffic calming measures)

Curb extensions to visually and physically narrow the roadway and create safer and shorter pedestrian crossing distances.

  • Woodward Avenue at Larkin Street:
    • All four corners (narrowing Woodward)
  • Larose Avenue at Larkin Street:
    • North-East corner on Larose Avenue (narrowing Larose)
    • South-West corner on Larose Avenue (narrowing Larose)
  • Chatelain Avenue at Larkin Street:
    • North-East corner on Chatelain Avenue (narrowing Chatelain)
    • South-West corner on Chatelain Avenue (narrowing Chatelain)
  • Lepage Avenue at Larkin Street:
    • North-East corner on Lepage Avenue (narrowing Lepage)
    • North-West corner on Lepage Avenue (narrowing Lepage)
  • Cavan Street at Lepage Avenue:
    • North-West corner on Cavan Street (narrowing Cavan)
    • South-West corner on Lepage Avenue and Cavan Street (narrowing both streets)

Vertical traffic calming measures

Raised facilities to improve pedestrian safety and reduce traffic speed

  • Larkin Street: Installation of raised intersections at the following cross streets:
    • Woodward Avenue
    • Larose Avenue
    • Chatelain Avenue
    • Avenue
  • Lepage Avenue:
    • Raised crosswalk in the north-south direction on the west side of the intersection at Cavan Street
  • Larose Avenue:
    • Installation of a speed table, a traffic calming devise to raise the entire wheelbase of a vehicle to reduce traffic speed.

Construction Disruptions

The Contractor will take every precaution to minimize interruptions to the everyday life of your family and/or operation of your business, but as you can appreciate, there may be some inconvenience during the course of the construction work. We would like to thank you for your patience and co-operation. For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255).