Stage 2 LRT Confederation Line Tree Removal

Project Status: 
Underway

Stage 2 LRT Confederation Line Tree Removal

Overview

Please be advised that as part of the Stage 2 O-Train Light Rail Transit (LRT) project, crews and equipment will begin area clearing as part of site preparation work for guideway and station construction. This includes site mobilization, tree and vegetation removal and area clearing in October and November 2019.

Area restoration, tree replacement and greenspace re-seeding will be completed as part of the final local area finishing works. An overall average tree replacement ratio of 2:1 (two trees for every one removed) will be replanted along the Stage 2 LRT alignment.

Tree Loss Mitigation and Replacement

The following measures will be taken to mitigate tree loss:

  • Limit clearing to only where required in temporary easement areas
  • Leave trees along property lines (backyards, businesses, parks) where possible
  • Design of pathways to incorporate existing trees
  • Inventory and compensate (ratio dependent on size, species) where removal is unavoidable
  • Critical Root Zone protection for trees along limits

Schedule

Area clearing is currently scheduled during daytime construction hours between 7am and 10pm Monday to Saturday, and between 9am to 10pm on Sunday’s and holidays.

Moodie Station

Status: In prgress since late November

Tree clearing activities taking place near Moodie Station.

Bayshore Station

Status: Anticipated to begin in December  

Tree clearing activities taking place near Bayshore Station.

Pinecrest Station

Status: Complete

Tree clearing activities taking place near Pinecrest Station.

Queensview Station

Status: In progress since early November

Tree clearing activities taking place near Queensview Station.

Iris Station to Baseline Station

Status: In progress since early October

Tree clearing activities taking place between Iris Station and Baseline Station

Baseline Stormwater Pond

Status: Anticipated to begin in mid-November

Tree clearing activities taking place near the future Baseline Stormwater Management Pond

Connaught Park & Southwest Transitway

Status: In progress since mid-November

Tree clearing activities taking place near Connaught Park

Lincoln Fields Station

Status: Anticipated to begin in December

Tree clearing activities taking place near Lincoln Fields Station.

Byron Linear Park

Status: In progress since early November

McEwen Avenue to Woodroffe Avenue

Tree clearing activities taking place between McEwen Avenue to Woodroffe Avenue.

Woodroffe Avenue to Cleary Avenue

Tree clearing activities taking place between Woodroffe Avenue and Cleary Avenue.

Sir John A Macdonald Parkway

Status: In progress since November

Tree clearing activities taking place on the Sir John A. Macdonald Parkway.

Kitchisippi Lookout

Status: Anticipated to begin late November

Tree clearing activities taking place near Kitchissippi Lookout

Sir John A Macdonald Parkway (Churchill Avenue)

Status: Anticipated to begin in December

Tree clearing activities taking place on the Sir John A. Macdonald Parkway near Churchill Avenue

OR174 Blair to Green's Creek

Status: In progress since October

Tree clearing activities taking place on the OR174 between Blair and Green's Creek

OR174 Jeanne D'arc to Orleans Boulevard

Status: In progress since November

Tree clearing activities taking place on the OR174 between Jeanne D'Arc to Orleans Boulevard

OR174 Champlain to Parkrose Private

Status: In progress since November

Tree clearing activities taking place on the OR174 between Champlain and Parkrose Private

OR174 Trim

Status: In progress since November

Tree clearing activities taking place on the OR174 at Trim Road

Questions

For more information on this project, please contact Stage2@ottawa.ca or call 3-1-1.