Skip to main content

Klondike Road Multi-Use Pathway

Project Status: 
Underway

Overview

Project description

The Klondike Road Multi-use Pathway project involves design and construction of an asphalt Multi-Use Pathway along the south side of Klondike Road between March Road and Sand Hill Road. This work will involve extension of the storm water culvert in Shirley’s Brook near March Road so that the pathway can cross the Brook. In order to construct the pathway, excavation of new ditches adjacent to the road, through driveway entrances and along shoulders is required including reinstatement of disturbed areas in the construction area as warranted. Complete re-construction of the asphalt roadway of Klondike Road between March Road and Sand Hill Road is also included in this project.

The project is required to provide a safe pedestrian and bicycle connection between March Road and Sand Hill Road.

Timelines

Design completion: Winter 2016
Construction start: Spring / Summer 2016
Anticipated Construction completion: Fall 2016

 Budget

Design and Construction -  $1.215 M 

For more information 

Jeff de Laat, Project Manager
Planning, Infrastructure and Economic Development Department
Design and Construction - Branch 2
City of Ottawa, 100 Constellation Drive, 6th Floor
Ottawa, ON K2G 6J8
Tel.: 613-580-2424, ext. 21916

Road closure notice - July 2016

Further to the June 2016 Construction Notice, the City of Ottawa (City) has begun construction work in your neighbourhood. This work is being conducted to build a Multi-Use Pathway in your community. The City wishes to advise you that a short term closure of Klondike Road is required as part of this project for the safe unloading and placement of a concrete culvert in Shirley’s Brook. 

Who: The City of Ottawa has hired Ottawa D-Squared Construction Limited to complete the work. 

Why:This work is needed to provide a safe pedestrian and cycling link in your community.   

What: The work will involve the short term closure of Klondike Road to vehicular traffic for the safe unloading and placement of a concrete culvert in Shirley’ Brook. Once the culvert has been placed, work will continue so that the new Pathway can be constructed over the Brook. 

Where:The road closure and work will be conducted within the City’s right-of-way at Shirley’s Brook, on Klondike Road between March Road and Sandhill Road.  Every effort is being made to reduce the duration of the construction impacts in your community. 

When: The closure of Klondike Road is scheduled to occur on July 8, 2016 from 12:50pm to 1:50 pm to accommodate the culvert installation. Construction activities are expected to resume immediately after the noted period and last until the end of September 2016. 

The City of Ottawa Noise By-law (2004-253) allows construction activity to occur weekdays between 7:00 a.m. and 10:00 p.m.  On Saturdays, work is permitted between 7:00 a.m. and 10:00 p.m., while Sunday and statutory holiday work is allowed between 9:00 a.m. and 10:00 p.m. The Contractor has advised the City that typical construction hours will be weekdays from 7:00 a.m. to 5:30 p.m.

Accessibility

Accessibility is an important consideration for the City of Ottawa. The City makes every effort to provide access through and around construction sites. If you require special accommodation, please contact the Contractor’s Administrator or the City’s Project Manager noted below.

Construction Disruptions

Ottawa D-Squared Construction Limited is assuming full responsibility for the construction work until the work is entirely complete in 2016. The Contractor will take every precaution necessary to minimize interruptions to the everyday life of your family and/or operation of your business, but as you can appreciate, there may be some inconvenience during the course of the work, such as delays and traffic detours when travelling through the construction zone, noise, dust and vibration. We would like to thank you in advance for your patience and co-operation. 

Access to homes, businesses and the Church on the closed section of Klondike Road shall be maintained during the closure period. Detour routes will be posted. 

For those using OC Transpo Route #93 before, after and during the closure period, your bus stop and route may be affected. Refer to the OC Transpo Travel Planner for specific alternative bus stops, detours or impacts. 

In the event that access to your driveway is restricted due to construction activities, the On-Site Inspector will provide you with a temporary On-Street Parking Permit (orange form) to authorize on-street parking within a few blocks of your residence.

It should also be noted that, the Contractor assumes full responsibility for the construction work until completion as well as for any damages to private property resulting from these construction activities. In the event of such occurrences, all claims for damages should be immediately reported both verbally and in writing to the Contractor and to the On-Site Inspector. This will ensure prompt notification of appropriate authorities to complete the claim investigations. Also, the City will be taking photographs to ensure private properties are returned to their original or better condition.

Contact Information

Should you have any questions or concerns, please do not hesitate to contact:

Contractor’s Representative:
Luigi Di Nuzzo
Ottawa D-Squared Construction Limited
(613) 822-1042 ext. 109   

Contract Administrator:
Michael Thivierge, P.Eng.
Stantec Consulting Ltd
(613) 784-2263 

On-Site Inspector:
Jordan Beukeboom
Stantec Consulting Ltd
(613) 722-4420 Ext 2278

City’s Project Manager:
Jeff de Laat, P.Eng.
Senior Project Manager
Construction Services Division – West   
(613) 580-2424 Ext 21916
   

Community Town Hall Information Meeting – January 20, 2016

For more information on the scope of work, refer below for the aerial plan and preliminary drawings from the Community Town Hall? information meeting held on January 20, 2016. 

This project is now moving forward. Work will include widening the culvert, creating a cycling lane with a pre-cast cement curb barrier between the cycling lane and the road, road paving, installing a multi-use pathway on the south side of the road and installation of some LED street lights. 

Work will go to tender this winter and construction is expected to start spring 2016.

Aerial Site Plan [ PDF - 8119 KB ]

Preliminary Plan - 1 [ PDF - 427 KB ]

Preliminary Plan - 2 [ PDF - 385 KB ]