College Avenue - Sidewalk Closure - October 2023
October 2023
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, the westbound Transitway and the sidewalk between Algonquin Station and Woodroffe Avenue will be closed allowing crews to continue work related to the new pedestrian bridge.
What
Closure of the westbound Transitway and sidewalk between Algonquin Station and Woodroffe Avenue.
When
Tuesday, October 3, from 9:30 a.m. to 3 p.m.
Why
Preparation for concrete work related to the new pedestrian bridge at Algonquin Station.
Where
Work will be located on the Transitway, between Algonquin Station and Woodroffe Avenue.

Anticipated Impacts
The north sidewalk along College Avenue between the ACCE building and Algonquin Station (south building) will be closed to facilitate these works and ensure safety. Signage on site will direct pedestrians north to Navaho Drive.
Noise and vibration from trucks and heavy equipment is expected.
Pedestrians and cyclists should use extra caution and adhere to posted signage when localized detours are in-place, to ensure safety.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Algonquin Station”. For other accommodations, or questions, please contact:
Dianna Ashworth
Dianna.Ashworth1@ottawa.ca
Stakeholder Relations | Relations avec les intervenants de l'Est
Rail Construction Program | Programme de construction du train léger
Transit Services Department | Direction générale des transports
City of Ottawa | Ville d’Ottawa
ottawa.ca/stage2 | ottawa.ca/etape2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Byron Avenue - Recurring Closures - October 2023
October 2023
As part of the Stage 2 O-Train Light Rail Transit (LRT) project’s Cut & Cover Tunnel construction, sections of Byron Avenue will be temporarily closed for the pouring of concrete and deliveries. Each pour requires 10 to 15 hours to complete as well as to stage delivery vehicles, cranes, and concrete trucks. Please note that concrete pours must be performed continuously until completed to ensure the quality of the concrete.
In addition, station construction is underway at New Orchard and Sherbourne Stations until winter 2024-2025. Temporary closures on Byron, near those two stations, will also be periodically required for stations work.
What
Byron Avenue continues to require *daylong closures of approximately one block to allow for work staging as the Cut and Cover Tunnel progresses. The sidewalk on the south side of Byron Avenue will remain open and accessible. Traffic will be detoured around the established work zone. Flag persons will be onsite, as required.
*Cranes and equipment will be demobilized at the end of each day, reopening Byron Avenue to general traffic.
When
Concrete works are ongoing and anticipated weekly throughout 2023.
7:00 a.m. to 10:00 p.m. Monday to Saturday and 9:00 a.m. to 5:00 p.m. on Sunday. Note that pours may extend beyond the end time.
Road closures begin with the mobilization of the delivery vehicles, cranes, and concrete trucks as well as the temporary road closure. Please note that KEV is targeting 10:00 p.m. completion time (5:00 p.m. on Sundays) per occurrence, however, as mentioned each pour will proceed until completed and may proceed into the night.
Why
A crane, as well as several delivery vehicles and concrete trucks, will be staged to accommodate the work on the Byron Tunnel. The size of the equipment and nature of the operations require daylong closure of a section of Byron Avenue.
*Construction vehicles are not permitted on residential streets and flaggers are utilized to ensure vehicles adhere to this City and Project requirement.
Where
Work will occur via Byron Avenue between New Orchard and Sherbourne Avenues.

Anticipated Impacts
Traffic will be restricted from travelling on Byron Avenue, and the cross-street where the work is occurring and will be redirected around the work zone.
Pedestrian mobility will be maintained using the south sidewalk on Byron Avenue.
Residents can expect noise from delivery vehicles, concrete trucks, and cranes.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Sherbourne Station” and/or “New Orchard Station”. For other accommodations, or any questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Tunney's Pasture to Roosevelt Avenue - Night Work - October to December 2023
October 2023
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, crews and equipment will be working during the daytime and overnight in the LRT Guideway (former Transitway trench) between the temporary Transitway bridge and Tunney’s Pasture Station.
What
Night work is required in the LRT Guideway, between the temporary Transitway bridge and Tunney’s Pasture Station. Night work may include excavation and hauling required for the installation of utilities (storm drainage/subdrain/culvert) and duct banks, Westboro Station construction, and to prepare the guideway for LRT track installation.
Pile drilling, rock breaking, vacuum truck excavation is NOT permitted overnight.
When
Night work will be undertaken as required, October through December 2023, subject to a valid noise by-law exemption. This is in addition to daytime activities on weekdays and weekends.
Daytime hours of construction are Monday to Saturday, 7:00 a.m. to 10:00 p.m. and 9:00 a.m. to 10:00 p.m. Sunday and on Statutory Holidays.
Why
To complete critical project work that is time sensitive and/or required during off-peak hours.
Where
Within the Transitway trench, between Roosevelt Avenue (temporary Transitway bridge) and Tunney’s Pasture Station.
*Night Work is NOT permitted in the Kichi Sibi Station area

Anticipated Impacts
Noise and vibration from crews and equipment is expected. Impacts from night work should be limited, as the work moves throughout the LRT guideway trench. There will be no rock-breaking overnight.
All construction vehicles and equipment working overnight will be equipped with broadband back-up alarms to minimize operational noise. Trucks use approved haul routes and workers and contractors park in designated parking areas.
Site lighting for overnight work will be required. Crews will place and/or direct the light to mitigate impact on residents at the surface.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Ward 15 – Weekly Night Work Summary Distribution List
A weekly summary of night work is shared with Councillor Leiper at the outset of each week. If you are interested in receiving a weekly update from the Councillor’s office, please contact Ben Inwood (Ben.Inwood@Ottawa.ca) to be added to the distribution list.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Kìchì Sìbì, and/or Westboro Stations”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Corkstown Road east of Moodie - Night Work & Lane Reductions - September 2023
September 2023
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, crews and equipment will be working overnight on Corkstown Road east of Moodie Drive. Motorists should anticipate impacts to traffic as crews complete necessary construction activities.
What
Corkstown Road, night work and westbound lane closure. Traffic will be maintained with spotters supporting single lane alternating traffic.
When
Friday, September 22 at 7:00 p.m. until Sunday, September 24 at 5:00 a.m.
Why
Watermain inspection and roadway reinstatement.
Where
Corkstown Road east of Moodie Drive.

Anticipated Impacts
Noise and vibration from crews and heavy equipment can be expected.
All construction vehicles and equipment, working overnight will be equipped with broadband back-up alarms. Trucks use approved haul routes and workers and contractors park in designated parking areas.
Site lighting for overnight work will be required and crews will place and/or direct the light to mitigate impact on residents.
Single lane alternating traffic (SLAT) will be in place along the closed segment of the Corkstown Road westbound lane. Flaggers and spotters will be onsite to direct traffic for the duration of the work.
Motorists should adhere to detours, traffic control signage, posted speed limits, allow for added travel time and use extra caution when moving through active construction corridors as traffic patterns change.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Ward 7 Night Work Summary Distribution List
A weekly summary of night work, providing greater detail as to the type and location of activities, is shared at the outset of each week. If you would like to receive the Ward 7 Weekly Night Work Summary, please email damon.berlin@ottawa.ca to be added to the distribution list.
Future work is required in this area. Additional construction updates will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Moodie Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Byron and Parkway Tunnels - Night Work - October 2023
October 2023
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, crews and equipment will be working overnight in the Parkway/Byron Tunnel.
Cut and cover tunnel structures (concrete tunnel floor, walls, and roof) along Kichi Zībī Mīkan will be completed this year, with tunnel backfill operations continuing into next year. Overall, at the end of August the Parkway/Byron Tunnel was 73% complete. It will be fully backfilled in 2024 and station construction will proceed.
What
Night work is required in the Parkway/Byron Tunnel, as work proceeds on the cut and cover tunnel structures activities. Night work may include excavation (digging with a small excavator) and hauling, installation of form work, concrete pouring, fueling, equipment maintenance and servicing, and site housekeeping.
Note: Pile drilling, rock breaking, vacuum truck excavation is NOT permitted overnight.
When
KEV anticipates that periodic night work will be required throughout 2023. Night work will occur subject to a valid noise by-law exemption, in addition to daytime activities on weekdays and weekends.
Daytime hours of construction are Monday to Saturday, 7:00 a.m. to 10:00 p.m. and 9:00 a.m. to 10:00 p.m. Sunday and on Statutory Holidays.
Why
To complete critical project work that is time sensitive and/or required during off-peak hours.
Where
Parkway/Byron Tunnel from Rochester Field along Kichi Zībī Mīkan and along Byron Linear Park to north Lincoln Fields.

Anticipated Impacts
Noise and vibration from crews and heavy equipment may be expected.
All construction vehicles and equipment, working overnight on the Parkway/Byron Cut and Cover Tunnel, will be equipped with broadband back-up alarms. Trucks use approved haul routes and workers and contractors park in designated parking areas.
Generators are required to run equipment in the tunnels and/or wrapped in noise barriers.
Site lighting for overnight work is required to maintain safe working conditions for workers. The use of lights will be minimized where possible and special attention paid to ensure that it is not impacting nearby residences.
The City of Ottawa thanks residents for their patience as we work to complete these construction activities.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Ward 7 Night Work Summary Distribution List
A weekly summary of nightwork providing greater detail as to type and location of activities, is shared at the outset of each week. If you would like to receive the Ward 7 Weekly night work summary, please email damon.berlin@ottawa.ca to be added to the distribution list.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect. Be sure to select updates for “New Orchard Station”, “Sherbourne Station” and/or “Kichi Sibi Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
LRT Guideway - Highway 417 to Algonquin Station and Pinecrest Creek Pond - Night Work - October 2023
October 2023
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, crews and equipment will be working overnight in the LRT guideway (former Transitway trench) from the Queensway Transitway Station to Iris Station and Algonquin Station. There will also be overnight work at the Pinecrest Creek Pond.
What
Night work is required as work proceeds on bridges, structures, utilities, roads, and the LRT guideway. Overnight activities may include excavation and hauling, concrete pouring, paving, and grading.
When
Night Work: Monday to Saturday 10:00 p.m. to 7:00 a.m. and 10:00 p.m. to 9:00 a.m. Sundays and Statutory holidays - will occur, as required, through December 2023.
Night work will be undertaken in conjunction with daytime activities on weekdays and weekends.
Why
To complete critical project work that is time sensitive and/or required during off-peak hours.
Where
Queensway Transitway Station to Iris Station and Algonquin Station, along the LRT guideway, as well as at the Pinecrest Creek Pond.

Anticipated Impacts
Noise and vibration from crews and heavy equipment can be expected.
Use of equipment like vac trucks, required to locate utilities and excavate, and activities like hoe-ramming, roller compacting etc. are only permitted during daytime hours.
All construction vehicles and equipment, working overnight will be equipped with broadband back-up alarms. Trucks use approved haul routes and workers and contractors park in designated parking areas. Trucks use approved haul routes and workers and contractors park in designated parking areas.
Site lighting for overnight work is required to maintain safe working conditions for workers. Light plants, generators and compressors are placed onsite as far away from neighbouring homes and/or wrapped in Echo Barrier.
All pedestrian, cycling, bus, and vehicular movements will generally be maintained during construction, with some detours. Temporary multi-use pathway (MUP) closures may be required to allow for construction work to proceed safely.
Pedestrians and cyclists should use extra caution when localized detours are in place and adhere to all posted signage, when travelling to ensure safety, as patterns may have changed.
The City of Ottawa thanks residents for their patience as we work to complete these construction activities.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require disability-related accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Iris and/orAlgonquin Stations”. For other accommodations, or questions, please contact:
Dianna Ashworth
Dianna.Ashworth1@ottawa.ca
Stakeholder Relations | Relations avec les intervenants de l'Est
Rail Construction Program | Programme de construction du train léger
Transit Services Department | Direction générale des transports
City of Ottawa | Ville d’Ottawa
ottawa.ca/stage2 | ottawa.ca/etape2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Iris to Baseline Eastside MUP Closure - September 2023
September 2023
*Apologies and thank you for your patience regarding the ongoing impacts to this important MUP network while required LRT work occurs in proximity.
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, a section of MUP network while required LRT work occurs in proximity.
What
The MUP on the east side of the Transitway/LRT guideway is closed.
When
The MUP will close on Monday, September 25 at 7:00 a.m. Work is expected to take approximately three weeks to complete. The MUP will reopen as soon as possible.
Why
Removal of asphalt, grading and re-paving of the section of the east MUP connecting to Iris Street to create a permanent MUP access point.
Where
MUP between Iris Street and Baseline Road.

Anticipated Impacts
Pedestrians and cyclists will be able travel between Iris Street and Baseline Road using the MUP on the west side of the Transitway/LRT guideway. Pedestrians and cyclists should use extra caution and adhere to posted signage as mobility patterns change to ensure safety.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Iris Station”. For other accommodations or questions, please contact:
Dianna Ashworth
Dianna.Ashworth1@ottawa.ca
Stakeholder Relations | Relations avec les intervenants de l'Est
Rail Construction Program | Programme de construction du train léger
Transit Services Department | Direction générale des transports
City of Ottawa | Ville d’Ottawa
ottawa.ca/stage2 | ottawa.ca/etape2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Re-opening of Richmond Road to Eastbound Traffic
September 2023
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, Richmond Road will be re-opened to eastbound vehicles travelling between McEwen Avenue and New Orchard Avenue. Westbound vehicles will continue to be detoured along Ambleside Drive.
What
Richmond Road will be re-opened to motorists travelling eastbound between McEwen
Avenue and New Orchard Avenue. Westbound vehicles will continue to be detoured along Ambleside Drive until further notice.
Note: Three short-term closures, estimated to be seven days each, will be needed on Richmond Road next year (2024) to complete additional concrete work. Residents and businesses will be notified of these closures in advance.
When
Richmond Road eastbound will reopen to general traffic the night of Friday, September 22, 2023.
Why
Construction work impacting eastbound traffic on Richmond Road between McEwen Avenue and New Orchard Avenue has been completed early, allowing for the re-opening of the roadway. Crews will remain in the area to continue work on the Byron cut and cover tunnel.
Where
Eastbound Richmond Road between New Orchard Avenue and McEwen Avenue.

Detour
Motorists travelling westbound on Richmond Road will continue to detour onto New Orchard Avenue, travel west along Ambleside Drive, travel south along McEwen Avenue and re-enter Richmond Road at McEwen Avenue.
Motorists should be mindful of pedestrian rights-of-ways at the pedestrian crossings on Ambleside Drive and on New Orchard Avenue.
Richmond Road businesses within the detoured corridor remain open and accessible. Motorists looking to access businesses on Richmond Road between McEwen Avenue and New Orchard Avenue should follow the signage posted onsite.
Access to properties along Richmond Road and Byron Avenue between McEwen Avenue and Ancaster Avenue, will continue to be maintained from the Richmond Road/McEwen Avenue intersection, unless temporarily closed for construction.
Richmond Road will continue to be closed to truck traffic between Carling Avenue and Woodroffe Avenue until December 2023.
Anticipated Impacts
Pedestrians, cyclists, and motorists should use extra caution and adhere to posted detours, traffic control signage, posted speed limits, allow for added travel time, and use extra caution when moving through active construction corridors as traffic patterns change.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “New Orchard Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Connaught Park - Light Maintenance and Storage Facility (LMSF) - Notice of Night Work
October 2023
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, crews and equipment will be working overnight from Connaught Park to the the Light Maintenance and Storage Facility (LMSF), west of Moodie Drive.
What
Night work is required from Connaught Park to the LMSF as work proceeds on bridges, structures, utilities, roads, stockpiles, berms, and the LRT guideway. Night work may include excavation and hauling, earth berm stockpiling, preparation, maintenance, sloping and removal, concrete pouring, grading, and lane closures.
*Unless otherwise notified, rock breaking, and vacuum truck excavation is NOT permitted overnight.
When
KEV anticipates that periodic night work will be required and ongoing throughout 2023. Night work will occur subject to a valid noise by-law exemption, in addition to daytime activities on weekdays and weekends.
Daytime hours of construction are Monday to Saturday, 7:00 a.m. to 10:00 p.m. and 9:00 a.m. to 10:00 p.m. Sunday and on Statutory Holidays.
Why
To complete critical project work that is time sensitive and/or required during off-peak hours.
Where
Connaught Park to the Light Maintenance and Storage Facility (LMSF)

Anticipated Impacts
Noise and vibration from crews and heavy equipment can be expected.
Construction workers are oriented, trained and consistently reminded to be good neighbours by not yelling when working.
All construction vehicles and equipment, working overnight will be equipped with broadband back-up alarms. Trucks use approved haul routes and workers and contractors park in designated parking areas.
Street sweeping, and cleaning will be ongoing along truck routes and around construction zones.
Site lighting for overnight is required to maintain safe working conditions for workers. The use of lights will be minimized where possible and special attention paid to ensure that it is not impacting nearby residences.
All pedestrian, cycling, bus, and vehicular movements will generally be maintained during construction, with some detours. Pedestrians and cyclists should use extra caution when localized detours are in place and adhere to all posted signage, when travelling to ensure safety, as patterns may have changed.
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
The City of Ottawa thanks residents for their patience as we work to complete these construction activities.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Ward 7 Night Work Summary Distribution List
A weekly summary of night work, providing greater detail as to the type and location of activities, is shared at the outset of each week. If you would like to receive the Ward 7 Weekly Night Work Summary, please email damon.berlin@ottawa.ca to be added to the distribution list.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Queensview, Pinecrest, Bayshore and/or Moodie Stations”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Baseline Road - Notice of Road Closure - September 19 & 20
September 2023
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, a section of Baseline Road will be closed to vehicles between Constellation Avenue and Woodroffe Avenue for rehabilitation of the bridge crossing the Transitway.
What
Staggered closure of westbound and eastbound Baseline Road between Constellation Avenue and Woodroffe Avenue.
When
Baseline Road westbound will be fully closed on Tuesday, September 19 at 8:00 p.m. until approximately 1:00 a.m. on Wednesday, September 20 between Woodroffe Avenue and Constellation Avenue. Eastbound lanes will remain open during this time.
Baseline Road eastbound will be fully closed overnight on Wednesday, September 19 from 1:00 a.m. until 6:00 a.m. between Constellation Avenue and Woodroffe Avenue. Westbound lanes will remain open during this time.
Why
Rehabilitation of the bridge that crosses the Transitway.
Where
Baseline Road between Constellation Avenue and Woodroffe Avenue.

Anticipated Impacts
Motorists travelling eastbound along Baseline Road will be detoured north on Greenbank Road/Pinecrest Road to Richmond Road. They will travel eastbound on Richmond Road and then turn right onto Carling Avenue to continue travelling east. At Woodroffe Avenue they will turn right and travel south until they connect back up with Baseline Road.
Motorists travelling westbound along Baseline Road will be detoured north on Woodroffe Avenue to Carling Avenue. After turning left, they will travel westbound and then turn left onto Richmond Road. They will turn left onto Pinecrest Road and travel south on Pinecrest Road/Greenbank Road until they connect with Baseline Road.
Motorists should adhere to detours, traffic control signage, posted speed limits, allow for added travel time and use extra caution when moving through active construction corridors as traffic patterns change.
There will continue to be impacts to the Pinecrest Creek multi-use pathway (MUP) north of Baseline Road. The pathway west of the Transitway remains closed, while the pathway east of the Transitway (with access off Woodroffe Avenue) remains open. Pedestrians and cyclists traveling east along Baseline Road will cross Baseline Road at Constellation Avenue and continue along the sidewalk on the north side of the road. Pedestrians and cyclists travelling west on Baseline Road will cross Baseline Road at Woodroffe Avenue and continue along the sidewalk on the south side of the road.
Pedestrians and cyclists should use extra caution and adhere to posted signage when localized detours are in-place, to ensure safety.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Algonquin Station”. For other accommodations, or questions, please contact:
Dianna Ashworth
Dianna.Ashworth1@ottawa.ca
Stakeholder Relations | Relations avec les intervenants de l'Est
Rail Construction Program | Programme de construction du train léger
Transit Services Department | Direction générale des transports
City of Ottawa | Ville d’Ottawa
ottawa.ca/stage2 | ottawa.ca/etape2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Carling Avenue between Edgeworth Avenue and the Transitway - Lane Reductions and Overnight Work - August 25-28
Updated Dates:
Friday, September 22 at 10:00 p.m. to Monday, September 25 at 6:00 a.m. Daytime and overnight.
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, traffic lanes on Carling Avenue will be shifted and lanes reduced to one lane in either direction from west of Edgeworth Avenue to east of the Transitway, as crews complete necessary utility works.
What:
Lane reductions and construction activities on Carling Avenue.
When:
Friday, September 22 at 10:00 p.m. to Monday, September 25 at 6:00 a.m. Daytime and overnight.
Why:
The reduction of lanes along Carling Avenue are required to complete watermain connections at Lincoln Fields Station, and to reinstate the roadway.
Where:
Carling Avenue between Edgeworth Avenue and the Transitway.

The construction work outlined in this notice is subject to change.
Work may be delayed or extended due to weather or other unforeseen circumstances.
Anticipated Impacts:
Noise and vibration from trucks and heavy equipment is expected. Construction activities will include: asphalt removal, excavation and grading work using excavators, bulldozers, and compactors, installation of a trench box, trucks bringing granular material and hauling away excavated materials, paving and line painting.
Site lighting for overnight work will be required and crews will place and/or direct the light to mitigate impact on residents nearby.
Motorists should adhere to detours, traffic control signage, posted speed limits, allow for added travel time and use extra caution when moving through active construction corridors as traffic patterns change.
Pedestrians and cyclists should use extra caution and adhere to posted signage when localized detours are in-place, to ensure safety.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility:
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and click ‘Connect with Us’ and select updates for “Lincoln Fields Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Transitway Closure Between Iris Street and Carling Avenue - Weekend and Night Work
Update - New Dates Listed Below
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, the Transitway between Iris Street and Carling Avenue will be fully closed for weekend and overnight work on multiple weekends throughout August and early September.
What:
Full closure of the Transitway between Iris Street and Carling Avenue for weekend and overnight work.
When:
- Friday, August 11 at 9:00 p.m. to Monday, August 14 at 6:00 a.m.
- Friday, August 25 at 9:00 p.m. to Monday, August 28 at 6:00 a.m.
- Friday, September 8 at 9:00 p.m. to Monday, September 11 at 6:00 a.m.
Why:
Construction and rehabilitation of catch basins.
Where:
Transitway between Iris Street and Carling Avenue.

Anticipated Impacts:
Noise and vibration from trucks and heavy equipment is expected. Please note that hydrovac excavation and rock breaking equipment may be required overnight. If this equipment is needed, the work must take place overnight as the Transitway cannot be closed during the day. We apologize for the inconvenience and will make every effort to minimize any noise.
Site lighting for overnight work will be required and crews will place and/or direct the light to mitigate impact on residents.
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Accessibility:
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2 and click ‘Connect with Us’ and select updates for “Lincoln Fields Station”, “Queensview Station”, and “Iris Station”. For other accommodations, or questions, please contact:
Dianna Ashworth – Ward 8 (South of Highway 417)
Stakeholder Relations, Rail Construction Program, City of Ottawa
Dianna.Ashworth1@ottawa.ca / www.ottawa.ca/stage2
Damon Berlin – Ward 7 (North of Highway 417)
Stakeholder Relations, Rail Construction Program, City of Ottawa
damon.berlin@ottawa.ca / www.ottawa.ca/stage2
SJAM Parkway - Island Park Drive and Woodroffe Avenue - Lane Closures and Construction - 15 August to 21 November
Update: New Start Date and Time
August 2023
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, there will be temporary lane closures and construction activities on the Sir John A. Macdonald (SJAM) Parkway between Island Park Drive and Woodroffe Avenue.
What
SJAM Parkway temporary lane closures between Island Park Drive and Woodroffe Avenue.
On weekdays, general traffic will be reduced to one lane of traffic in both directions.
On weekends, general traffic will be reduced to one lane of traffic in both directions, however, during the NCC Weekend Bikedays traffic will be reduced to one lane of traffic eastbound only. For SJAM Parkway westbound, motorists will follow the routine NCC Bikedays detour.
Note: NCC Weekend Bikedays end on Monday, October 9.
When
Construction will occur during daytime hours only. Monday to Saturday from 7:00 a.m. to 6:00 p.m., and Sundays from 9:00 a.m. to 6:00 p.m.
Tuesday, August 15 at 10:00 p.m. to Tuesday, November 21 at 6:00 a.m. 2023.
Why
Construction activity at the Kitchissippi Lookout intersection and the Lanark pedestrian underpass that crosses under the SJAM Parkway.
Where
The work zone is on the SJAM Parkway, east of the Transitway off ramp to just past Westboro Beach.

Anticipated Impacts
Excavators, wheel loaders, bulldozers, drill rigs, graders, asphalt pavers, and compactors will be used for construction and bridge rehabilitation. This includes storm sewer, guiderail, traffic signal and street light installation as well as paving and line painting. Rock breaking during the first month of construction will be required.
Noise from equipment will be audible and some equipment may cause vibrations.
Trucks will deliver granular material, asphalt, and concrete to the site and will haul away excavated material. Noise from equipment and moving of material will be audible.
Motorists should adhere to traffic control signage, posted speed limits, allow for added travel time and use extra caution when moving through active construction corridors as traffic patterns change.
During this scope of work, the multi-use pathway (MUP) north and south of SJAM Parkway will be maintained outside of the Kitchissippi Lookout Construction project limits. The MUP connection between Lanark Underpass and the MUP north of SJAM west of Westboro Beach has also been paved and will be available.
Pedestrians and cyclists should use extra caution and adhere to posted signage when localized detours are in-place, to ensure safety.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Sherbourne Station”, “Kìchì Sìbì Station” and “Westboro Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Opening of the Woodroffe Pedestrian Bridge
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, we are happy to share that the new Woodroffe Pedestrian Bridge is scheduled to open to the public! In addition, there continues to be a closure of a portion of the north/south multi-use pathway (MUP) east of the Woodroffe Pedestrian Bridge south of Carling Avenue.
What:
Closure of the north/south MUP on the east side of the Woodroffe Pedestrian Bridge between Carling Avenue and the connections to Rosewood Avenue and to Woodroffe High School.
When:
• Friday, August 4 at 7:00 a.m. – Opening of the Woodroffe Pedestrian Bridge
• Friday, August 4 at 7:00 a.m. to Friday, September 1 at 5:00 p.m. 2023 – Temporary MUP closure. Work will occur during the daytime and nighttime. Work on weekends may also be required.
Why:
The closure is required to rebuild the north/south MUP between the east side of the Woodroffe Pedestrian Bridge and Carling Avenue. Work also includes installing conduit for a new communications cable.
Where:
South of Carling Avenue near Woodroffe High School, east of the Transitway. The segment of the MUP between Carling Avenue and Woodroffe High School and the connection to Rosewood Avenue will be closed for this construction. Pedestrians and cyclists will be detoured on to Rosewood Avenue to Edgeworth Avenue or to the MUP on the west side of the Transitway.

Anticipated Impacts:
Residents living south of Carling Avenue to the Woodroffe Pedestrian Bridge can expect the following construction activities to take place during the day and night:
- Excavators, compactors, and asphalt equipment will be used to rebuild the eastside north/south MUP. Noise from equipment will be audible and some equipment may cause vibrations.
- Trucks will deliver material to the site. Noise from equipment and moving of material will be audible.
- Site lighting and generators will be used to power lights which are a safety requirement for overnight work. Crews will place and/or direct the light away from residences to mitigate any impacts.
Signage will be in place in advance of these works advising of the detour route. Pedestrians and cyclists should use extra caution and adhere to posted signage when localized detours are in-place, to ensure safety.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility:
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Weekly Ward 7 Night Work Distribution List
Residents should be aware that throughout 2023, there will be an increased requirement for nightwork across the alignment. A weekly summary of nightwork providing greater detail as to location and activities, is shared at the outset of each week. If you would like to be included in the Ward 7 weekly night work summary, please email damon.berlin@ottawa.ca to be added to the distribution list.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Lincoln Fields Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Iris Street - Night Work and Temporary Road Closure
July 2023
Dear resident,
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, Iris Street between Parkway Drive and Adirondack Drive is temporarily closed to general traffic.
In addition to the ongoing daytime construction, night work is required to shift the temporary construction barriers (TCB). Night work is scheduled to take place between:
- Thursday, July 27 at 11:00 p.m. to Friday, July 28 at 5:00 a.m.
- Monday, July 31 at 11:00 p.m. to Tuesday, August 1 at 5:00 a.m.
- * The TCB relocation work is not expected to take the entire night to complete and disruption to residents is expected to be minimal.
Please note that during the TCB shifting night work, Iris Street will be closed to all traffic including OC Transpo. Access to both northbound and southbound Adirondack Drive will be closed at Iris Street and the intersection will not be available to the general public while contractors relocate the TCBs.

Iris Street will reopen over the weekend to accommodate local traffic in accessing the neighbourhood during the installation of the Queensview Pedestrian Bridge. The installation necessitates a full closure of Highway 417 between Woodroffe and Pinecrest from Friday, July 28 at 9:00 p.m. until Monday, July 31 at 6:00 a.m. Please note that in response to community concerns and requests, “local traffic only” signs will be posted along Iris Street.
After the Highway 417 reopens and the TCBs are reinstalled, work will resume on Iris Street, as per the Iris Street – Update letter dated July 19, 2023.
Thank you for your understanding, and please do not hesitate to reach out should you have any questions.
Regards,
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
MUP (west side) between Iris Street to Navaho Drive - Notice of Closure
Update - New Opening Date Below
July 2023
*Apologies and thank you for your patience regarding the ongoing impacts to this important MUP network while required LRT work occurs in proximity.
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, a section of MUP between Iris Street and Navaho Drive is closed.
What
The MUP on the west side of the Transitway/LRT guideway is closed. The crossover section will become part of the construction zone and is now permanently closed.
When
Monday, July 24, 2023 to Friday, September 22, 2023.
Why
The MUP west of the Transitway/LRT guideway and south of the crossover remains closed for watermain and catch basin work.
Where
MUP between Iris Street and Navaho Drive.

Anticipated Impacts
Pedestrians and cyclists will be able travel between Iris Street and Navaho Drive using the existing MUPs on the east. Impacts to travel times are expected to be minimal.
Pedestrians and cyclists should use extra caution and adhere to posted signage as mobility patterns change to ensure safety.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Iris Station”. For other accommodations or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Iris Street Update
July 18, 2023
Dear Resident,
As you are aware, as part of the Stage 2 O-Train Light Rail Transit (LRT) project, Iris Street between Parkway Drive and Adirondack Drive is temporarily closed to general traffic and is scheduled to reopen in the Fall of 2023.
This closure is necessary to perform utility relocations and renewals to improve the quality of drinking water in response to community concerns and requests, as well as to complete road work.
Progress to date includes:
- The installation of the watermain on the south side of Iris Street at Adirondack has been completed and is being tested. Currently, the plan is to tie it in to the main system this week, (dependent on City crew availability) and tie-in local services next week.
Did You Know?
The City of Ottawa’s streets cover a labyrinth of utilities that service every home, business, institution, and everything in between.
Did you know Iris Street and the Pinecrest Creek Corridor are two intersecting utility corridors that allow the passageway for many different utilities that service your community and beyond? Above and below the surface, these two corridors house water, sewer, sanitary, telecommunication, electricity, and gas infrastructure. Corridors allow for the grouping of utility lines in a single, accessible space, eliminate conflicts between those lines, minimize or eliminate trenching and reduce or eliminate manholes.
As part of the Stage 2 LRT project, the Pinecrest Creek, and existing City owned, and third party owned utilities had to be relocated to allow for the conversion of the Transitway to the LRT Guideway and the construction of Iris Station.
Upcoming work includes:
- Traffic will be relocated to the south side of Iris Street on the weekend of July 22/23. This will require a full closure overnight (10:00 p.m. to 5:00 a.m.) of Iris Street between Adirondack Avenue and the Transitway to shift traffic control barriers (TCBs). Local traffic will be allowed through, however, not from the south side (northbound) of Adirondack.
- Paving will precede the shifting of the TCBs.
- Once this occurs, general traffic will be able to access and egress Adirondack (south of Iris) to and from Woodroffe Avenue.
- Sanitary sewer work will begin shortly after shifting TCBs and is anticipated for approximately six weeks.
- Iris Street will be open to two-way traffic from July 28 to July 31 during the Highway 417 full closure for the installation of the Queensview Pedestrian Bridge, just east of Pinecrest. Iris Street will then revert to OC Transpo access only until the Fall of 2023.
- In early August, electrical work will take place for approximately one week.
- Reinstatement of roads and sidewalks, by the Fall of 2023 (with the exception of work required for installation of an Enbridge gas line). Please note that these works are not yet scheduled.
This work is nearly complete and the final phase of relocating and installing new utilities (water, sewer, power, gas, telecommunication) to supply Iris Station is underway. In addition to Station related works, the Iris Street watermain is being replaced, in response to community concerns and requests to improve the quality of drinking water for area residents.


It is anticipated that in the fall of 2023, Enbridge will install natural gas to Iris Stations’ switch heaters. In addition, as Iris Station works progress, telecom will also be connected.
Thank you for your patience and understanding. Please do not hesitate to reach out should you have any questions.
Regards,
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Hanlon Avenue at Connaught Avenue - Notice Temporary Road Closure
Updated Date of Completion - Friday, July 21, 2023
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, Hanlon Avenue at Connaught Avenue will be closed temporarily to vehicular traffic. Pedestrians and cyclists will not be impacted.
What
Closure of Hanlon Avenue is necessary to install catch basins. Connaught Avenue just south of Hanlon will be reduced to a single lane only to install curbs. Flaggers will be present to facilitate the flow of traffic.
When
***Updated Date of Completion - Friday, July 21, 2023
Tuesday, July 18 and Wednesday, July 19, from 7:00 a.m. to 5:00 p.m.
Why
Installation of a catch basins and curbs.
Where
Hanlon Avenue at Connaught Avenue.

Anticipated Impacts
Excavators, vac trucks, compactors, concrete trucks, and backhoes will be used for construction. Noise from equipment will be audible and some equipment may cause vibrations.
Motorists should adhere to, traffic control signage, posted speed limits, allow for added travel time and use extra caution when moving through active construction corridors as traffic patterns change.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Pinecrest Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Highway 417 between Woodroffe and Pinecrest - Notice of Full Closure
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, motorists travelling Highway 417 as well as residents whose homes are near Highway 417, should anticipate weekend mobility impacts as crews work to install a new pedestrian bridge across the highway. To facilitate this work, Kiewit Eurovia Vinci (KEV) is working with the Ministry of Transportation Ontario and the City of Ottawa to implement traffic control staging on Highway 417 and surrounding streets.
What
Highway 417 full closure and various ramps which are listed below.
When
Friday, July 28 at 9:00 p.m. until Monday, July 31 at 6:00 a.m., 2023. Work will be occurring day and night.
Why
KEV will undertake the lifting and installation of a new pedestrian bridge to facilitate pedestrian connectivity from the future Queensview Station on the north side of Highway 417 to Baxter Road on the south side of Highway 417.
Where
Highway 417 between Woodroffe Avenue and Pinecrest Road interchanges.
Various ramps will be closed to isolate the work area as well as control traffic impacts.
Highway 417 westbound on-ramps (full closure to all vehicular traffic – follow detour):
- Maitland Avenue on-ramp
- Woodroffe Avenue on-ramp
Highway 417 eastbound on-ramps (full closure to all vehicular traffic – follow detour):
- Richmond Road on-ramp
- Pinecrest Road on-ramp

Anticipated Impacts
Noise from equipment will be audible and some equipment may cause vibrations.
Signed traffic detours will be in effect during this road closure. Motorists should adhere to detours, traffic control signage, posted speed limits, allow for added travel time and use extra caution when moving through active construction corridors as traffic patterns change.
Site lighting and generators will be used to power lights which are a safety requirement for overnight work. Crews will place and/or direct the light away from residences to mitigate any impacts.
Construction fencing with barriers will be in place around the work area.
Please be advised, that the Queensview Pedestrian Bridge will be installed but will not be available to the public until the West Extension begins revenue service.
When the West Extension begins revenue service, the public not just transit users will be able to use the Queensview Pedestrian Bridge.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Pinecrest Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
South of Iris Street Notice of Temporary MUP Closure - July 15 to 24, 2023
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, sections of the MUPs between Iris Street and Baseline Road are closed.
What
The MUP on the east side of the Transitway/LRT guideway, north of the crossover remains closed. The MUP on the west side of the Transitway/LRT guideway, south of the crossover section will be closed. The crossover section will be open.
When
Saturday, July 15 at 7:00 a.m. to Monday, July 24 at 7:00 a.m. 2023.
Why
The MUP east of the Transitway/LRT guideway and north of the crossover remains closed for paving and sidewalk resurfacing on Iris Street. The MUP west of the Transitway/LRT guideway and south of the crossover will be closed for watermain and catch basin work.
Where
MUPs between Iris Street and Baseline Road.

Anticipated Impacts
Pedestrians and cyclists will be able travel between Iris Street and Baseline Road using sections of the existing MUPs on the east and west sides using the crossover. Any impacts to travel times are expected to be minimal.
Pedestrians and cyclists should use extra caution and adhere to posted signage as mobility patterns change, to ensure safety.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Iris Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Byron Avenue - Notice of Temporary Closures
As part of the Stage 2 O-Train Light Rail Transit (LRT) project’s Cut & Cover Tunnel construction, sections of Byron Avenue will be temporarily closed for the pouring of concrete. Each pour requires 10 to 15 hours to complete as well as to stage delivery vehicles, cranes, and concrete trucks. Please note that concrete pours must be performed continuously until completed to ensure the quality of the concrete.
In addition, station construction is underway at New Orchard and Sherbourne Stations until winter 2024-2025. Temporary closures on Byron, near those two stations, will also be periodically required for stations work.
What
Byron Avenue continues to require daylong closures of approximately one block to allow for work staging as the Cut and Cover Tunnel progresses. The sidewalk on the south side of Byron Avenue will remain open and accessible. Traffic will be detoured around the established work zone. Signage and flag persons will be onsite, as required.
When
7:00 a.m. to 10:00 p.m. Monday to Saturday and 9:00 a.m. to 5:00 p.m. on Sunday. Note that pours may extend beyond the end time.
Concrete works are ongoing and anticipated weekly until approximately Fall 2023.
Road closures begin with the mobilization of the delivery vehicles, cranes, and concrete trucks as well as the temporary road closure. Please note that KEV is targeting 10:00 p.m. completion time (5:00 p.m. on Sundays) per occurrence, however, as mentioned each pour will proceed until completed and may proceed into the night.
Why
A crane, as well as several delivery vehicles and concrete trucks, will be staged to accommodate the work on the Byron Tunnel. The size of the equipment and nature of the operations require daylong closure of a section of Byron Avenue.
*Construction vehicles are not permitted on residential streets and flaggers are utilized to ensure vehicles adhere to this City and Project requirement.
Where
Work will occur via Byron Avenue between New Orchard and Sherbourne Avenues.

Anticipated Impacts
Traffic will be restricted from travelling on Byron Avenue, and the particular cross street where the work is occurring, and will be redirected around the work zone, with posted signage in place.
Pedestrian mobility will be maintained using the south sidewalk on Byron Avenue.
Residents can expect noise from delivery vehicles, concrete trucks, and cranes.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Sherbourne Station” and/or “New Orchard Station”. For other accommodations, or any questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
MUP south of Iris Street - Notice of Closure
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, sections of the MUPs between Iris Street and Baseline Road are closed.
What
The MUP on the east side of the Transitway/LRT guideway and the section that crosses over will be closed.
When
Until Saturday, July 15 at 7:00 a.m.
Why
The MUP east of the Transitway/LRT guideway is closed for paving and sidewalk resurfacing on Iris Street. The MUP which crosses the Transitway/LRT is closed for bridge rehabilitation.
Where
MUPs between Iris Street and Baseline Road.

Anticipated Impacts
Pedestrians and cyclists will be able travel between Iris Street and Baseline Road using the existing MUP on the west side. Any impacts to travel times are expected to be minimal.
Pedestrians and cyclists should use extra caution and adhere to posted signage as mobility patterns change, to ensure safety.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Iris Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Sir John A. Macdonald Parkway - Between Island Park Drive and Woodroffe Avenue - Notice of Temporary Lane Closures
Updated Dates - Monday, July 17 at 7:00 a.m. to Saturday, July 22 at 8:00 a.m.
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, there will be temporary lane closures and construction activities on the Sir John A. Macdonald (SJAM) Parkway between Island Park Drive and Woodroffe Avenue.
What
SJAM Parkway temporary lane closures between Island Park Drive and Woodroffe Avenue. One lane in each direction will remain open.
When
Daytime hours only. 7:00 a.m. to 6:00 p.m., Monday to Saturday. 9:00 a.m. to 6:00 p.m., on Sundays.
Monday, July 17 at 7:00 a.m. to Saturday, July 22 at 8:00 a.m. (new dates)
Why
Construction of a new ramp for temporary lane reconfiguration.
Where
The work zone is on the SJAM Parkway, east of the Transitway off ramp and just west of Westboro Beach.

Anticipated Impacts
Excavators, wheel loaders, bulldozers, graders, asphalt pavers, and compactors will be used for construction. This includes paving and line painting.
Noise from equipment will be audible and some equipment may cause vibrations.
Trucks will deliver granular material, and asphalt to the site and will haul away excavated material. Noise from equipment and moving of material will be audible.
Motorists should adhere to traffic control signage, posted speed limits, allow for added travel time and use extra caution when moving through active construction corridors as traffic patterns change.
During this scope of work, the multi-use pathway (MUP) north and south of SJAM Parkway will be maintained per current conditions outside of the Kitchissippi Lookout Construction project limits. The MUP connection between Lanark Underpass and the MUP north of SJAM west of Westboro Beach has also been paved.
Pedestrians and cyclists should use extra caution and adhere to posted signage when localized detours are in-place, to ensure safety.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Sherbourne Station”, “Kìchì Sìbì Station” and “Westboro Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
South of Carling Temporary MUP closures
Updated dates: Tuesday, July 4 at 7:00 a.m. to Friday, July 21 7:00 a.m.
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, the closure of a portion of MUP south of Carling Avenue is required to complete the connections to the new pedestrian bridge.
What
Finalize the connections to the east side of the Woodroffe Pedestrian Bridge and rebuild the north/south multi-use pathway (MUP).
When
Tuesday, July 4 at 7:00 a.m. to Friday, July 21 at 7:00 a.m. 2023. Work will occur during the daytime and nighttime. Work on weekends may also be required.
Why
Completion of the tie-ins to the east side of the Woodroffe Pedestrian Bridge, including rebuilding and paving the MUP.
Where
The north/south MUP south of Carling Avenue, between Carling Avenue and Woodroffe High School.

Anticipated Impacts
Residents near the Woodroffe Pedestrian Bridge can expect the following construction activities to take place during the day and night:
- Excavators, compactors, and asphalt equipment will be used to construct the new MUP. Noise from equipment will be audible and some equipment may cause vibrations.
- Trucks will deliver material to the site. Noise from equipment and moving of material will be audible.
- Site lighting and generators will be used to power lights which are a safety requirement for overnight work. Crews will place and/or direct the light away from residences to mitigate any impacts.
The segment of the MUP between Carling Avenue and Woodroffe High School will be closed for this construction. Pedestrians and cyclists will be detoured on to Rosewood Avenue or to the MUP on the west side of the Transitway. A new MUP in the north and south direction under the new Woodroffe Pedestrian Bridge will be available.
Signage will be in place in advance of these works advising of the detour route. Pedestrians and cyclists should use extra caution and adhere to posted signage when localized detours are in-place, to ensure safety.
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Weekly Ward 7 Night Work Distribution List
Residents should be aware that throughout 2023, there will be an increased requirement for nightwork across the alignment. A weekly summary of nightwork providing greater detail as to location and activities, is shared at the outset of each week. If you would like to be included in the Ward 7 weekly night work summary, please email damon.berlin@ottawa.ca to be added to the distribution list.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connectand select updates for “Lincoln Fields Station” and “Queensview Statin”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances
College Transitway Sidewalk - Notice of Temporary Closure
Postpone - New Date Pending
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, the westbound Transitway between Algonquin College and Algonquin Station will be reduced to one lane to allow crews to complete the finishes of the new pedestrian bridge.
What
Temporary closure of sidewalk and one lane of the westbound Transitway.
When
July 4 at 7:00 a.m. to Friday, September 1, at 7:00 p.m., 2023.
Why
The construction required to complete the finishes on the new pedestrian bridge, that include the installation of deck panels and windows. The most efficient and safest solution requires a closure to complete the necessary work.
Where
Work will be on the Transitway, between Algonquin College and Algonquin Station.
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.

Anticipated Impacts
The north sidewalk along College Avenue between the ACCE building and Algonquin Station (south building) will be closed to facilitate these works and ensure safety. Signage on site will direct pedestrians north to Navaho Drive.
Pedestrians and cyclists should use extra caution and adhere to posted signage when localized detours are in-place, to ensure safety.
Site lighting for overnight work will be required and crews will place and/or direct the light to mitigate impact on residents.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Algonquin Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Algonquin Station to Queensway Bus Station and the Pinecrest Creek Pond - Notice of Night Work
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, crews and equipment will be working overnight in the LRT guideway (former Transitway trench) from the Queensway Transitway Station to Iris Station and Algonquin Station. There will also be overnight work at the Pinecrest Creek Pond.
What
Night work is required as work proceeds on bridges, structures, utilities, roads, and the LRT guideway. Overnight activities may include excavation and hauling, concrete pouring, paving, and grading.
When
Night Work: Monday to Saturday 10:00 p.m. to 7:00 a.m. and 10:00 p.m. to 9:00 a.m. Sundays and Statutory holidays - will occur, as required, through September 2023.
Night work will be undertaken in conjunction with daytime activities on weekdays and weekends.
Why
To complete critical project work that is time sensitive and/or required during off-peak hours.
Where
Queensway Transitway Station to Iris Station and Algonquin Station, along the LRT guideway, as well as at the Pinecrest Creek Pond.

Anticipated Impacts
Noise and vibration from crews and heavy equipment can be expected.
Use of equipment like vac trucks, required to locate utilities and excavate, and activities like hoe-ramming, roller compacting etc. are only permitted during daytime hours.
All pedestrian, cycling, bus, and vehicular movements will generally be maintained during construction, with some detours. Temporary multi-use pathway (MUP) closures may be required to allow for construction work to proceed safely.
Site lighting for overnight work is required to maintain safe working conditions for workers. Light plants, generators and compressors are placed onsite as far away from neighbouring homes and/or wrapped in Echo Barrier.
All pedestrian, cycling, bus, and vehicular movements will generally be maintained during construction, with some detours. Temporary multi-use pathway (MUP) closures may be required to allow for construction work to proceed safely.
Pedestrians and cyclists should use extra caution when localized detours are in place and adhere to all posted signage, when travelling to ensure safety, as patterns may have changed.
The City of Ottawa thanks residents for their patience as we work to complete these construction activities.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require disability-related accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Iris and/or Algonquin Stations”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Tunney's Pasture to Roosevelt Avenue - Notice of Night Work
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, crews and equipment will be working during the daytime and overnight in the LRT Guideway (former Transitway trench) between the temporary Transitway bridge and Tunney’s Pasture Station.
What
Night work is required in the LRT Guideway, between the temporary Transitway bridge and Tunney’s Pasture Station. Night work may include excavation and hauling required for the installation of utilities (storm drainage/subdrain/culvert) and duct banks, and to prepare the guideway (subgrade/sub ballast) for the laying of LRT tracks in the guideway this fall.
*Unless otherwise notified, rock breaking, and vacuum truck excavation is NOT permitted overnight.
When
Night work will be undertaken as required, July through September 2023, subject to a valid noise by-law exemption. This is in addition to daytime activities on weekdays and weekends.
Daytime hours of construction are Monday to Saturday, 7:00 a.m. to 10:00 p.m. and 9:00 a.m. to 10:00 p.m. Sunday and on Statutory Holidays.
Why
To complete critical project work that is time sensitive and/or required during off-peak hours.
Where
Within the Transitway trench, between Roosevelt Avenue (temporary Transitway bridge) and Tunney’s Pasture Station.
*Night Work is NOT permitted in the Kichi Sibi Station area

Anticipated Impacts
Crews will be installing utilities using an excavator, as well as hauling excavated materials. Noise and vibration from crews and equipment is expected. Impacts from night work should be limited, as the work moves throughout the LRT guideway trench. There will be no rock-breaking overnight.
All construction vehicles and equipment working overnight will be equipped with broadband back-up alarms to minimize operational noise. Trucks use approved haul routes and workers and contractors park in designated parking areas.
Site lighting for overnight work will be required. Crews will place and/or direct the light to mitigate impact on residents at the surface.
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Ward 15 – Weekly Night Work Summary Distribution List
A weekly summary of night work is shared with Councillor Leiper at the outset of each week. If you are interested in receiving a weekly update from the Councillor’s office, please contact Ben Inwood (Ben.Inwood@Ottawa.ca) to be added to the distribution list.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Kìchì Sìbì, and/or Westboro Stations”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Byron/Parkway Tunnel - Notice of Night Work
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, crews and equipment will be working overnight in the Parkway/Byron Tunnel.
What
Night work is required in the Parkway/Byron Tunnel, as work proceeds on the cut and cover tunnel structures (concrete tunnel floor, walls, and roof) activities. Night work may include excavation (digging with a small excavator) and hauling, welding activities, hoisting operations, installation of form work for tunnel walls and roof, concrete pouring, fueling, equipment maintenance and servicing, and site housekeeping.
Pile drilling, rock breaking, vacuum truck excavation is NOT permitted overnight.
When
KEV anticipates that periodic night work will be required throughout 2023. Night work will occur subject to a valid noise by-law exemption, in addition to daytime activities on weekdays and weekends.
Daytime hours of construction are Monday to Saturday, 7:00 a.m. to 10:00 p.m. and 9:00 a.m. to 10:00 p.m. Sunday and on Statutory Holidays.
Why
To complete critical project work that is time sensitive and/or required during off-peak hours.
Where
Parkway/Byron Tunnel from Rochester Field along the Sir John A. Macdonald Parkway (SJAM), and along Byron Park to north Lincoln Fields.

Anticipated Impacts
Noise and vibration from crews and heavy equipment may be expected.
All construction vehicles and equipment, working overnight on the Parkway/Byron Cut and Cover Tunnel, will be equipped with broadband back-up alarms. Trucks use approved haul routes and workers and contractors park in designated parking areas.
Generators are required to run equipment in the tunnels and/or wrapped in noise barriers.
Site lighting for overnight work is required to maintain safe working conditions for workers. The use of lights will be minimized where possible and special attention paid to ensure that it is not impacting nearby residences.
The City of Ottawa thanks residents for their patience as we work to complete these construction activities.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Ward 7 Weekly Night Work Summary Distribution List
A weekly summary of nightwork providing greater detail as to type and location of activities, is shared at the outset of each week. If you would like to receive the Ward 7 Weekly night work summary, please email damon.berlin@ottawa.ca to be added to the distribution list.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect. Be sure to select updates for “New Orchard Station”, “Sherbourne Station” and/or “Kichi Sibi Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Connaught Park - Light Maintenance and Storage Facility (LMSF) - Notice of Night Work
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, crews and equipment will be working overnight from Connaught Park to the the Light Maintenance and Storage Facility (LMSF), west of Moodie Drive.
What
Night work is required from Connaught Park to the LMSF as work proceeds on bridges, structures, utilities, roads, stockpiles, berms, and the LRT guideway. Night work may include excavation and hauling, earth berm stockpiling, preparation, maintenance, sloping and removal, concrete pouring, grading, and lane closures.
*Unless otherwise notified, rock breaking, and vacuum truck excavation is NOT permitted overnight.
When
KEV anticipates that periodic night work will be required and ongoing throughout 2023. Night work will occur subject to a valid noise by-law exemption, in addition to daytime activities on weekdays and weekends.
Daytime hours of construction are Monday to Saturday, 7:00 a.m. to 10:00 p.m. and 9:00 a.m. to 10:00 p.m. Sunday and on Statutory Holidays.
Why
To complete critical project work that is time sensitive and/or required during off-peak hours.
Where
Connaught Park to the Light Maintenance and Storage Facility (LMSF).

Anticipated Impacts
Noise and vibration from crews and heavy equipment can be expected.
Construction workers are oriented, trained and consistently reminded to be good neighbours by not yelling when working.
All construction vehicles and equipment, working overnight will be equipped with broadband back-up alarms. Trucks use approved haul routes and workers and contractors park in designated parking areas.
Street sweeping, and cleaning will be ongoing along truck routes and around construction zones.
Site lighting for overnight is required to maintain safe working conditions for workers. The use of lights will be minimized where possible and special attention paid to ensure that it is not impacting nearby residences.
All pedestrian, cycling, bus, and vehicular movements will generally be maintained during construction, with some detours. Pedestrians and cyclists should use extra caution when localized detours are in place and adhere to all posted signage, when travelling to ensure safety, as patterns may have changed.
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
The City of Ottawa thanks residents for their patience as we work to complete these construction activities.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Ward 7 - Weekly Night Work Summary Distribution List
A weekly summary of night work, providing greater detail as to the type and location of activities, is shared at the outset of each week. If you would like to receive the Ward 7 Weekly Night Work Summary, please email damon.berlin@ottawa.ca to be added to the distribution list.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Queensview, Pinecrest, Bayshore and/or Moodie Stations”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Lincoln Fields to Connaught Park - Notice of Night Work
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, crews and equipment will be working overnight in the Lincoln Fields, Carling Avenue, and Connaught Park areas including along the Transitway. Work will take place daily with periodic night shifts across the alignment of the West extension.
What
Night work is required from the area of Lincoln Fields Station, Carling Avenue, the as work proceeds on bridges, structures, utilities, and roads and the LRT guideway. Night work may include excavation and hauling, concrete pouring, grading, and lane closures.
When
KEV anticipates that periodic night work will be required and ongoing throughout 2023. Night work will occur subject to a valid noise by-law exemption, in addition to daytime activities on weekdays and weekends.
Daytime hours of construction are Monday to Saturday, 7:00 a.m. to 10:00 p.m. and 9:00 a.m. to 10:00 p.m. Sunday and on Statutory Holidays.
Why
To complete critical project work that is time sensitive and/or required during off-peak hours.
Where
Lincoln Fields Station area and on Carling Avenue, Connaught Park, along the Transitway and LRT guideway.

Anticipated Impacts
Noise and vibration from crews and heavy equipment can be expected.
Use of equipment like vac trucks, required to locate utilities and excavate, and activities like hoe-ramming, roller compacting etc. are done during daytime hours.
All construction vehicles and equipment, working overnight will be equipped with broadband back-up alarms. Trucks use approved haul routes and workers and contractors park in designated parking areas.
Construction workers are oriented, trained and consistently reminded to be good neighbours by not yelling when working.
Site lighting for overnight is required to maintain safe working conditions for workers. Light plants, generators and compressors are placed onsite and as far away from neighbouring homes to the extent possible.
Dust control will be in place, as needed. Street sweeping, and cleaning will be ongoing along truck routes and around construction zones.
All pedestrian, cycling, bus, and vehicular movements will generally be maintained during construction, with some detours. Pedestrians and cyclists should use extra caution when localized detours are in place and adhere to all posted signage, when travelling to ensure safety, as patterns may have changed.
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
The City of Ottawa thanks residents for their patience as we work to complete these construction activities.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Ward 7 - Night Work Summary Distribution List
A weekly summary of night work, providing greater detail as to the type and location of activities, is shared at the outset of each week. If you would like to receive the Ward 7 Weekly Night Work Summary, please email damon.berlin@ottawa.ca to be added to the distribution list.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Lincoln Fields, and/or Queensview Stations”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Woodroffe Pedestrian Bridge - Notice of Temporary Closure of Segment of Multi-Use Pathway (MUP) South of Carling Avenue
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, the closure of a portion of MUP south of Carling Avenue is required to advance the completion of the new pedestrian bridge.
What
Construction of the permanent embankment and tie-ins to the west side of the Woodroffe Pedestrian Bridge.
Note: There will be impacts to the MUPs on the east side of the Woodroffe Pedestrian Bridge, both to finalize the connection to the bridge and to rebuild the N-S MUP. The details will be included in a future public notice.
When
Monday, June 26 at 7:00 a.m. to Monday, July 17 at 7:00 a.m.2023. Work will occur during the daytime and nighttime. Work on weekends may also be required.
Why
Completion of the permanent embankment and tie-ins to the west side of the Woodroffe Pedestrian Bridge, including paving of the MUP.
Where
East-west MUP south of Carling Avenue, between Sackville Street/Connaught Avenue and the Transitway.

Anticipated Impacts
Residents near the Woodroffe Pedestrian Bridge can expect the following construction activities to take place during the day and night:
- Excavators, compactors, and asphalt equipment will be used to construct the new MUP. Noise from equipment will be audible and some equipment may cause vibrations.
- Trucks will deliver material to the site. Noise from equipment and moving of material will be audible.
- Site lighting and generators will be used to power lights which are a safety requirement for overnight work. Crews will place and/or direct the light away from residences to mitigate any impacts.
The segment of the MUP between Sackville Street/Connaught Avenue and the Transitway will be closed for this construction. Pedestrians and cyclists will be detoured further south on Connaught Avenue or north to Carling Avenue to connect to the Pinecrest Creek Pathway. A new MUP in the north and south direction under the new Woodroffe Pedestrian Bridge will be available.
Signage will be in place in advance of these works advising of the detour route. Pedestrians and cyclists should use extra caution and adhere to posted signage when localized detours are in-place, to ensure safety.
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Weekly Ward 7 Night Work Distribution List
Residents should be aware that throughout 2023, there will be an increased requirement for nightwork across the alignment. A weekly summary of nightwork providing greater detail as to location and activities, is shared at the outset of each week. If you would like to be included in the Ward 7 weekly night work summary, please email damon.berlin@ottawa.ca to be added to the distribution list.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Lincoln Fields Station” and “Queensview Statin”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Kichi Sibi Station - Construction Update
Kìchì Sìbì Station area was handed over to the station constructor PCL and they will begin to mobilize on-site as early as June 12, 2023. With the beginning of station construction, there will be lots of construction activities taking place in the area.

Station Construction
The first step in constructing an LRT station is the longest and most labour intensive; the concrete stage. At this stage, the concrete slabs that will serve as the station’s main concourse are poured and the concrete walls are erected.
This is where the next stage in the process, the structural phase, begins. The steel pieces used to create the framework of the station are 3D modelled in advance, to ensure they fit perfectly into place.
After the steel structure is completed, work begins to install the roofing, exterior walls and the mechanical and electrical rough-ins. LRT stations have four main rooms: mechanical, electrical, communication, and signal control. During this stage, these rooms are outfitted with the necessary equipment required for the operation of the train system.
Once the electrical and mechanical foundation is set, the finishing work can begin. This work involves closing interior walls, installing fixtures, and completing exterior finishes that include glazing (windows) and cladding. Communications features including the public address (PA) systems and television screens, as well as landscaping, are some of the last items to be completed.
The site will be accessed from various points depending on the type and location of the work being performed. Station construction access is expected to be from the SJAM, Westboro Station, and Berkley/Dominion.
A tower crane will be used to maximize efficiencies and minimize community impacts from construction. Tower cranes are commonly used in construction, with several currently in use in Westboro. Rather than being located on the periphery of the construction zone closer to homes, the tower crane will be installed inside the guideway trench (between Dominion/Berkley and Workman Ave).
Once installed, the tower crane at Kichi Sibi Station area will be in place until approximately August 2024.
Other infrastructure that will be installed as a part of the station includes a Traction Power Substation (TPSS). TPSS are spread approximately equidistant across the alignment to balance the electrical load. TPSS are approximately the size of a shipping container (15m long, 5m wide, 4m high). The noise is minimal and there are no environmental impacts. The TPSS will be installed in the trench at track level just west of the station.
In addition to station construction, there will be other work taking place in and around the Kìchì Sìbì Station area to complete the Stage 2 West Extension. This work includes guideway construction (on-going), rock breaking, utilities installation, track installation), wire installation (overhead catenary system, signaling, train control), and testing and commissioning.
At this time, station construction is expected to be completed by early 2025 and substantial completion for the Stage 2 West Extension is anticipated for the end of 2026.
Anticipated Impacts
Noise and vibration from trucks and heavy equipment is expected. Noise and vibration monitoring will be performed throughout the work.
Construction activities include:
- Rock breaking, excavation and hauling
- Delivery of materials and equipment
- Hoisting work using crane operations
- Concrete form work and pouring
- Structural steel installation and welding operations
- Underground services
- Mechanical and electrical installation
- Street sweeping and snow clearing
- Site lighting
Station construction activities typically occurs on weekdays, during daytime hours:
- Monday to Saturday from 7:00 a.m. to 10:00 p.m.
- Sunday from 9:00 a.m. to 10:00 p.m.
Night work is only permitted with an approved Noise By-law Exemption. At this time, the only activities approved overnight at Kichi Sibi Station area are the operation and maintenance of pumps, refueling, dewatering, and housekeeping activities.
Vehicular, cyclist and pedestrian mobility will be maintained. Pedestrians and cyclists should use extra caution and adhere to posted signage when localized detours are in-place, to ensure safety.
The City of Ottawa thanks residents for their patience as we work to complete these construction activities.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Weekly Ward 15 Night Work Distribution List
Residents should be aware that throughout 2023, there will be an increased requirement for nightwork across the alignment. A weekly summary of nightwork providing greater detail as to location and activities, is shared at the outset of each week. If you would like to be included in the Ward 15 weekly night work summary, please email ben.inwood@ottawa.ca to be added to the distribution list.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Kichi Sibi Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Sir John A. Macdonald Parkway: Between Island Park Drive and Woodroffe Avenue - Notice of Temporary Lane Closures and Construction Activities
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, there will be temporary lane closures and construction activities on the Sir John A. Macdonald (SJAM) Parkway between Island Park Drive and Woodroffe Avenue.
What
SJAM Parkway temporary lane closures between Island Park Drive and Woodroffe Avenue.
On weekdays, there will be one lane in each direction, available to general traffic on the SJAM Parkway just east of the Transitway off-ramp to just past Westboro Beach.
On weekends, during the NCC Weekend Bikedays a paved surface will be available for cyclists.
When
Daytime hours only. 7:00 a.m. to 6:00 p.m., Monday to Saturday. 9:00 a.m. to 6:00 p.m., on Sundays.
Monday, June 12 at 6:00 a.m. to Saturday, September 30 at 6:00 a.m. 2023.
Why
Construction activity at the Kitchissippi Lookout intersection and the Lanark pedestrian underpass that crosses under the SJAM.
Where
The work zone is on the SJAM Parkway, east of the Transitway off ramp to just past Westboro Beach.

Anticipated Impacts
Excavators, wheel loaders, bulldozers, drill rigs, graders, asphalt pavers, and compactors will be used for construction and bridge rehabilitation. This includes storm sewer, guiderail, traffic signal and street light installation as well as paving and line painting. Rock breaking during the first month of construction will be required.
Noise from equipment will be audible and some equipment may cause vibrations.
Trucks will deliver granular material, asphalt, and concrete to the site and will haul away excavated material. Noise from equipment and moving of material will be audible.
Motorists should adhere to traffic control signage, posted speed limits, allow for added travel time and use extra caution when moving through active construction corridors as traffic patterns change.
During this scope of work, the multi-use pathway (MUP) north and south of SJAM Parkway will be maintained per current conditions outside of the Kitchissippi Lookout Construction project limits. There MUP connection between Lanark Underpass and the MUP north of SJAM west of Westboro Beach has also been paved.
Pedestrians and cyclists should use extra caution and adhere to posted signage when localized detours are in-place, to ensure safety.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Sherbourne Station”, “Kìchì Sìbì Station” and “Westboro Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Dumaurier Avenue - Notice of Night Work and Temporary Road Closure
*Updated to include new end date - Friday, August 25, 2023
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, Dumaurier Avenue south of Ramsey Crescent, will be closed temporarily to vehicular traffic. Pedestrian and cycling mobility in the area will be maintained throughout the detour with posted signage.
What
Closure of Dumaurier Avenue is necessary to perform critical utilities relocations and road work.
When
As early as Monday, May 29 until Friday, August 25, 2023. Work will be occurring day and night, on weekdays and weekends.
No hydro vac will occur between 10:00 p.m. and 7:00 a.m.
Why
Utilities relocation and road work is required for LRT construction. Installation of a water main, and sanitary services followed by sidewalk and curb construction and paving.
Where
Dumaurier Avenue at Ramsey Crescent (east intersection).

Anticipated Impacts
Excavators, vac trucks, backhoes, graders, dump trucks, asphalt pavers, and compactors will be used for construction. This includes water main and sanitary services installation as well as paving and line painting.
Noise from equipment will be audible and some equipment may cause vibrations.
Trucks will deliver granular material, asphalt, and concrete to the site and will haul away excavated material. Noise from equipment and moving of material will be audible.
Signed traffic detours will be in effect during this road closure. Motorists should adhere to detours, traffic control signage, posted speed limits, allow for added travel time and use extra caution when moving through active construction corridors as traffic patterns change.
Pedestrian mobility will be maintained, with posted signage and changes to the detour as work advances. Pedestrians and cyclists should use extra caution when localized detours are in place.
Site lighting and generators will be used to power lights which are a safety requirement for overnight work. Crews will place and/or direct the light away from residences to mitigate any impacts.
Construction fencing with barriers will be in place around the work area.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Pinecrest Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Guideway between Queensway and Algonquin Stations, and Pinecrest Creek Pond - Notice of Night Work
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, crews and equipment will be working overnight in the LRT guideway (former Transitway trench) from the Queensway Transitway Station to Iris Station and Algonquin Station. There will also be overnight work at the Pinecrest Creek Pond.
What:
Night work is required as work proceeds on bridges, structures, utilities, roads, and the LRT guideway. Overnight activities may include excavation and hauling, concrete pouring, paving, and grading.
When:
Night Work: Monday to Saturday 10:00 p.m. to 7:00 a.m. and 10:00 p.m. to 9:00 a.m. Sundays and Statutory holidays - will occur, as required, through June 2023.
Night work will be undertaken in conjunction with daytime activities on weekdays and weekends.
Why:
To complete critical project work that is time sensitive and/or required during off-peak hours.
Where:
Queensway Transitway Station to Iris Station and Algonquin Station, along the LRT guideway, as well as at the Pinecrest Creek Pond.

Anticipated Impacts:
Noise and vibration from crews and heavy equipment can be expected.
Use of equipment like vac trucks, required to locate utilities and excavate, and activities like hoe-ramming, roller compacting etc. are only permitted during daytime hours.
All construction vehicles and equipment, working overnight will be equipped with broadband back-up alarms. Trucks use approved haul routes and workers and contractors park in designated parking areas.
Site lighting for overnight work is required to maintain safe working conditions for workers. Light plants, generators and compressors are placed onsite as far away from neighbouring homes and/or wrapped in Echo Barrier.
All pedestrian, cycling, bus, and vehicular movements will generally be maintained during construction, with some detours. Temporary multi-use pathway (MUP) closures may be required to allow for construction work to proceed safely.
Pedestrians and cyclists should use extra caution when localized detours are in place and adhere to all posted signage, when travelling to ensure safety, as patterns may have changed.
The City of Ottawa thanks residents for their patience as we work to complete these construction activities.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility:
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require disability-related accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Iris Station” and or “Algonquin Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Corkstown Road between Moodie Drive and March Road - Temporary Closures
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, Corkstown Road will be reduced to one lane open to eastbound traffic between the westernmost entrance to Wesley Clover Parks and the easternmost entrance to Wesley Clover Parks.
What:
Construction work along Corkstown Road, between the westernmost entrance and the easternmost entrance to Wesley Clover Parks. Traffic will be reduced to one lane open to eastbound traffic.
When:
As soon as Monday, May 15 2023 for approximately eight weeks. Work will be occurring from 7:00 a.m. to 5:00 p.m., on weekdays and weekends.
Why:
This work is to reinstate Corkstown Road. Activities include road widening and ditch digging, swale construction, concrete work for slipform barriers and sidewalks, grading, paving, line painting, followed by the application of topsoil and seeding. This work will be occurring along the north and south side of Corkstown Road. Day and night construction is necessary to complete critical project work that is time sensitive, and to limit the traffic impacts of the closure.
Where:
Corkstown Road between the westernmost entrance to Wesley Clover Parks and the easternmost entrance to Wesley Clover Parks.

Anticipated Impacts:
Wesley Clover Parks and Wesley Clover Parks Campground will be accessible via March Road and Moodie Drive.
Local traffic will be able to access Corkstown Road from March Road up to the westernmost entrance to Wesley Clover Parks and from Moodie Drive up to the easternmost entrance to Wesley Clover Parks. Flaggers will be present at the two entranceways to facility flow of vehicles to and from Wesley Clover Parks. Flaggers will be present to control the opposing traffic movements in the single lane available during the working hours of 7:00 a.m. to 5:00 p.m.
Excavators, bulldozers, concrete trucks, compactors, and pavers will be used for construction and road rehabilitation. Noise from equipment will be audible and some equipment may cause vibrations.
Trucks will deliver granular material, asphalt, and concrete to the site, and will haul away excess excavated material. Noise from equipment and moving of material will be audible.
Site lighting and generators will be used to power lights which are a safety requirement for overnight work. Crews will place and/or direct the light away from residences to mitigate any impacts.
Motorists should adhere to detours, traffic control signage, posted speed limits, allow for added travel time and use extra caution when moving through active construction corridors as traffic patterns change.
Pedestrians and cyclists should use extra caution and adhere to posted signage when localized detours are in-place, to ensure safety.
Accessibility:
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Moodie Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Iris Street - Notice of Temporary Road Closure
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, Iris Street, between Parkway Drive and Adirondack Drive, will be closed temporarily to vehicular traffic. Pedestrian and cycling mobility in the area will be maintained throughout the detour with posted signage.
What:
Closure of Iris Street is necessary to perform critical utilities relocations and road work. Vehicular traffic will be detoured around the area. Buses will be permitted through the area to not impact service locations. Changes to pedestrian and cycling detours will occur between Parkway Drive and Adirondack Drive as construction activities in the area progress.
When:
As early as Monday, May 1 until Thursday, August 31, 2023. Construction will occur during daytime hours only, however, the closure will remain in place 24/7.
Why:
Utilities relocation and road work is required for Iris Station and LRT construction. Installation of a water main, sanitary services, and electrical utilities followed by sidewalk and curb construction and paving. This work will bring the area between the Iris LRT station and Adirondack Drive to its final configuration.
Where:
Iris Street between Parkway Drive and Adirondack Drive.

The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Anticipated Impacts:
Excavators, vac trucks, backhoes, graders, dump trucks, asphalt pavers, and compactors will be used for construction. This includes water main, sanitary services, and electrical utilities installation and street light installation as well as paving and line painting.
Noise from equipment will be audible and some equipment may cause vibrations.
Trucks will deliver granular material, asphalt, and concrete to the site and will haul away excavated material. Noise from equipment and moving of material will be audible.
Motorists should adhere to detours, traffic control signage, posted speed limits, allow for added travel time and use extra caution when moving through active construction corridors as traffic patterns change.
Signed traffic detours will be in effect during this road closure. Pedestrian mobility will be maintained, with posted signage and changes to the detour as work advances. Pedestrians and cyclists should use extra caution when localized detours are in place.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility:
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Iris Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Sir John A Macdonald Parkway - Notice of Lane Closures
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, there will be temporary lane closures and construction activities on the Sir John A. Macdonald (SJAM) Parkway between Island Park Drive and Woodroffe Avenue.
What
SJAM Parkway temporary lane closures between Island Park Drive and Woodroffe Avenue.
On weekdays, there will be one lane in each direction, available to general traffic on the SJAM Parkway just east of the Transitway off-ramp to just past Westboro Beach.
On weekends, there will be one SJAM Parkway eastbound lane and two SJAM Parkway westbound lanes; however, during the NCC Weekend Bikedays there will be only one lane eastbound available. For SJAM Parkway westbound, motorists will follow the routine NCC Bikedays detour.
When
Saturday, April 15 at 7:00 a.m. to Sunday, July 9 at 11:30 a.m. 2023.
Daytime hours only. 7:00 a.m. to 6:00 p.m., Monday to Saturday. 9:00 a.m. to 6:00 p.m., on Sundays.
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Why
Construction activity at the Kitchissippi Lookout intersection and the Lanark Pedestrian Bridge that crosses over the SJAM Parkway.
Where
The work zone is on the SJAM Parkway, east of the Transitway off ramp to just past Westboro Beach.

Anticipated Impacts
Excavators, wheel loaders, bulldozers, drill rigs, graders, asphalt pavers, and compactors will be used for construction and bridge rehabilitation. This includes storm sewer, guiderail, traffic signal and street light installation as well as paving and line painting. Rock breaking during the first month of construction will be required. Rock breaking is NOT permitted overnight.
Noise from equipment will be audible and some equipment may cause vibrations.
Trucks will deliver granular material, asphalt, and concrete to the site and will haul away excavated material. Noise from equipment and moving of material will be audible.
Motorists should adhere to traffic control signage, posted speed limits, allow for added travel time and use extra caution when moving through active construction corridors as traffic patterns change.
During this scope of work, the multi-use pathway (MUP) north and south of SJAM Parkway will be maintained per current conditions outside of the Kitchissippi Lookout Construction project limits. There will also be a newly paved MUP connection between Lanark Underpass and the MUP north of SJAM west of Westboro Beach.
Pedestrians and cyclists should use extra caution and adhere to posted signage when localized detours are in-place, to ensure safety.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect and select updates for “Sherbourne Station”, “Kìchì Sìbì” Station and “Westboro Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Byron and Parkway Tunnels - Notice of Night Work
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, crews and equipment will be working overnight in the Parkway/Byron Tunnel.
What
Night work is required in the Parkway/Byron Tunnel, as work proceeds on the cut and cover tunnel structures (concrete tunnel floor, walls, and roof) activities. Night work may include excavation (digging with a small excavator) and hauling, welding activities, hoisting operations, installation of form work for tunnel walls and roof, concrete pouring, fueling, equipment maintenance and servicing, and site housekeeping.
Pile drilling, rock breaking, vacuum truck excavation is NOT permitted overnight.
When
KEV anticipates that periodic night work will be required throughout 2023. Night work will occur subject to a valid noise by-law exemption, in addition to daytime activities on weekdays and weekends.
Daytime hours of construction are Monday to Saturday, 7:00 a.m. to 10:00 p.m. and 9:00 a.m. to 10:00 p.m. Sunday and on Statutory Holidays.
Why
To complete critical project work that is time sensitive and/or required during off-peak hours.
Where
Parkway/Byron Tunnel from Rochester Field along the Sir John A. Macdonald Parkway (SJAM), and along Byron Park to north Lincoln Fields.

Anticipated Impacts
Noise and vibration from crews and heavy equipment may be expected.
All construction vehicles and equipment, working overnight on the Parkway/Byron Cut and Cover Tunnel, will be equipped with broadband back-up alarms. Trucks use approved haul routes and workers and contractors park in designated parking areas.
Generators are required to run equipment in the tunnels and/or wrapped in noise barriers.
Site lighting for overnight work is required to maintain safe working conditions for workers. The use of lights will be minimized where possible and special attention paid to ensure that it is not impacting nearby residences.
The City of Ottawa thanks residents for their patience as we work to complete these construction activities.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Ward 7 - Night Work Summary - Distribution List
A weekly summary of nightwork providing greater detail as to type and location of activities, is shared at the outset of each week. If you would like to receive the Ward 7 Weekly night work summary, please email damon.berlin@ottawa.ca to be added to the distribution list.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect. Be sure to select updates for “New Orchard Station”, “Sherbourne Station” and “Kichi Sibi Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Connaught Park to Moodie LMSF - Night Work
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, crews and equipment will be working overnight from Connaught Park to the the Light Maintenance and Storage Facility (LMSF), west of Moodie Drive.
WHAT:
Night work is required from Connaught Park to the LMSF as work proceeds on bridges, structures, utilities, roads, stockpiles, berms, and the LRT guideway. Night work may include excavation and hauling, earth berm stockpiling, preparation, maintenance, sloping and removal, concrete pouring, grading, and lane closures. *Unless otherwise notified, rock breaking, and vacuum truck excavation is NOT permitted overnight.
WHEN:
KEV anticipates that periodic night work will be required and ongoing throughout 2023. Night work will occur subject to a valid noise by-law exemption, in addition to daytime activities on weekdays and weekends.
Daytime hours of construction are Monday to Saturday, 7:00 a.m. to 10:00 p.m. and 9:00 a.m. to 10:00 p.m. Sunday and on Statutory Holidays.
WHY:
To complete critical project work that is time sensitive and/or required during off-peak hours.
WHERE:
Connaught Park to the Light Maintenance and Storage Facility (LMSF).

ANTICIPATED IMPACTS:
Noise and vibration from crews and heavy equipment can be expected.
Construction workers are oriented, trained and consistently reminded to be good neighbours by not yelling when working.
All construction vehicles and equipment, working overnight will be equipped with broadband back-up alarms. Trucks use approved haul routes and workers and contractors park in designated parking areas.
Street sweeping, and cleaning will be ongoing along truck routes and around construction zones.
Site lighting for overnight is required to maintain safe working conditions for workers. The use of lights will be minimized where possible and special attention paid to ensure that it is not impacting nearby residences.
All pedestrian, cycling, bus, and vehicular movements will generally be maintained during construction, with some detours. Pedestrians and cyclists should use extra caution when localized detours are in place and adhere to all posted signage, when travelling to ensure safety, as patterns may have changed.
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
The City of Ottawa thanks residents for their patience as we work to complete these construction activities.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
ACCESSIBILITY:
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require disability-related accommodation, please contact stage2@ottawa.ca.
Ward 7 Night Work Summary Distribution List
A weekly summary of night work, providing greater detail as to the type and location of activities, is shared at the outset of each week. If you would like to receive the Ward 7 Weekly Night Work Summary, please email damon.berlin@ottawa.ca to be added to the distribution list.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2connect. Be sure to select updates for “Queensview Station, Pinecrest, Bayshore or Moodie Station”. For other accommodations, or any questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Notice of Cut and Cover Tunneling Activities and Night Work - Richmond Road, at Cleary Avenue
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, Cut and Cover tunnel construction operations will be ongoing in the Cut and Cover Tunnel across Richmond Road, at Cleary Avenue. Daytime and overnight work is required to accommodate various operations occurring simultaneously and to minimize project delays.
What
Support of Excavation (SOE) and excavation activities, followed by tunnel construction.
Daytime: More impactful work will be scheduled, like the drilling of soldier piles (approximately 50 steel shafts), support of excavation (SOE), excavation and backfill with excavators, dump trucks, hydrovac operations, hauling and concrete pouring.
Nighttime: Less impactful activities, including servicing heaters and generators, and excavation, will be scheduled.
Activity during the day and night will include hoisting work using cranes, welding operations, and excavation. As well, generators, pumps and heaters will be operating, to support construction.
When
Equipment is expected to mobilize the week of March 20th with pile drilling anticipated to being week of April 3rd and will continue through 2023, subject to a valid Noise By-Law Exemption Permit. 24-hours a day, Monday to Friday. Daytime and nighttime work on weekends may also be required.
Why
These works will eventually connect the Parkway and Byron Cut and Cover Tunnels.
Nightwork is required as this work is schedule critical on the delivery of this large and complex project.
Where
Richmond Road and Cleary Avenue.

Anticipated Impacts
Noise and vibration from trucks and heavy equipment is expected. Noise and vibration monitoring will be performed throughout the work to ensure compliance with project limits.
Site lighting is required to maintain safe working conditions for workers. Use of large light plants will be minimized with special attention to ensure lights are directed away from residents and roadways.
Light plants, generators, pumps, compressors, and other equipment will be enclosed within Echo barriers, where possible.
Trucks will only use approved haul routes on Richmond Road and the Sir John A. Macdonald Parkway (SJAM.)
Motorists should adhere to detours, traffic control signage, posted speed limits, use extra caution, and allow for added travel time when moving through active construction corridors as traffic patterns change.
Pedestrian and cyclist mobility will not be impacted.
The City of Ottawa thanks residents for their patience as we work to complete these construction activities.
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
Ward 7 - Night Work Distribution List
A weekly summary of nightwork is shared at the outset of each week. If you would like to be included in the “Ward 7 Night Work Weekly Summary”, please email damon.berlin@ottawa.ca to be added to the distribution list.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2 and click ‘Connect with Us’ and select updates for “Sherbourne Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage2
Byron Avenue - Notice of Recurring Temporary Road Closure
This notice is to advise that, the Stage 2 O-Train Light Rail Transit (LRT) project excavation of the Cut & Cover Tunnel has progressed to pouring of the concrete “box”. Each pour requires 10 to 15 hours to complete as well as a temporarily closed section of Byron Avenue to stage delivery vehicles, cranes and concrete trucks. Please note that concrete pours must be performed continuously until completed to ensure the quality of the concrete.
What
Byron Avenue continues to require daylong closures of approximately 1 block to allow for work staging as the Cut and Cover Tunnel progresses to its new phase. The sidewalk on the south side of Byron Avenue will remain open and accessible. Traffic will be detoured around the established work zone. Signage and flag persons will be onsite.
When
6:00 a.m. to 10:00 p.m. Monday to Saturday and 9:00 a.m. to 5:00 p.m. on Sunday. Note that pours may extend beyond the end time.
Works are ongoing and anticipated every week until complete until approximately Fall 2023.
Road closures will begin with the mobilization of the delivery vehicles, cranes and concrete trucks as well as the temporary road closure. Please note that KEV is targeting 10:00 p.m. completion time (5:00 p.m. on Sundays) per occurrence however, as mentioned, each pour will proceed until completed and may proceed into the night.
Why
A crane, as well as several delivery vehicles and concrete trucks, will be staged to accommodate the work on the Byron Tunnel. The size of the equipment and nature of the operations require daylong closure of a section of Byron Avenue.
Where
Work will occur via Byron Avenue between New Orchard and Sherbourne Avenues.

Anticipated Impacts
Traffic will be restricted from travelling on Byron Avenue, and the cross street where the Byron work is occurring, and will be redirected around the work zone, with posted signage in place.
Pedestrian mobility will be maintained using the south sidewalk on Byron Avenue.
Residents can expect noise from delivery vehicles, concrete trucks, and cranes.
Spotters will be on-site, ensuring trucks do not infiltrate residential streets in the area.
Accessibility
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca(link opens email application).
The safety of the public and workers is paramount, and we thank you for your patience during construction.2
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2 and click ‘Connect with us.’ Be sure to select updates for “Sherbourne Station” and “New Orchard Station”. For other accommodations or any questions, please contact:
Damon Berlin,
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
damon.berlin@ottawa.ca
www.ottawa.ca/stage
Richmond Road at Cleary Avenue - Long Term Road Realignment
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, Richmond Road will be realigned at Cleary Avenue.
WHAT:
Long-term realignment of Richmond Road at Cleary Avenue, shifting Richmond Road approximately 15m south. A new signalized intersection has been constructed at Richmond Road and Redwood Avenue.
Cleary Avenue at Richmond Road was closed on November 21 and a new access road with a signalized intersection was opened from Richmond Road through Kristy’s (909 Richmond Road) to Cleary Avenue.
WHEN:
As early as Tuesday, January 17, 2023 until end of 2024.
WHY:
The realignment of Richmond Road is required to facilitate construction of the Cut and Cover Byron Tunnel, from Byron Linear Park to the Sir John A. Macdonald Parkway (SJAM), crossing Richmond Road.
WHERE:
Richmond Road at Cleary Avenue.

ANTICIPATED IMPACTS:
Motorists should adhere to detours, traffic control signage, posted speed limits, allow for added travel time and use extra caution when moving through active construction corridors as traffic patterns change.
New signalized intersections have been constructed at Richmond Road and Redwood Avenue and Richmond Road and Kristy’s (809 Richmond Road).
The existing sidewalk on the north side of Richmond Road, south of 75 Cleary Avenue will be closed. A new temporary pathway on the north side of Richmond Road and alongside the realigned roadway has been constructed
As part of the closure of Cleary Avenue, a new temporary pathway has been constructed from Richmond Road along the private roadway and north of the overflow parking lot.
Pedestrians and cyclists should use extra caution and adhere to posted signage to ensure safety.
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
ACCESSIBILITY:
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2 and click ‘Connect with Us’ and select updates for “Sherbourne Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
Reminder - Ashley Street - Notice of Closure
December 2022
In April 2022, the Transitway between Bayshore Mall and the Pinecrest interchange was closed for construction of the LRT guideway. Buses were detoured off the Transitway, onto Highway 417. As a part of this detour, buses traveling eastbound exit Highway 417 at the eastbound Pinecrest off ramp.
For this detour to be effective, the closure of Ashley Street was required. Ashley Street is a high contributor to the volume of vehicles using the Pinecrest off ramp. The interaction between these vehicles and traffic exiting the highway, including OC Transpo buses, would present a safety concern as well as create significant traffic and transit delays. During the closure, signed traffic detours will be in effect directing traffic from Ashley Street to Lisa Avenue, and to turn left from eastbound Lisa Avenue onto northbound Greenbank Road. It is anticipated Ashley Street will reopen upon the conclusion of the transit detour.
In consideration of the impacts of the Ashley Street closure on traffic in the area, improvements were made at the Lisa Avenue and Greenbank Road intersection. A left turn lane was added on Lisa Avenue to accommodate the extra volume of traffic detouring from Ashley Street.

The Stage 2 project appreciates your understanding and patience while we work towards completing this exciting project together.
If you have any questions or to receive updates on the above information, please sign up to receive the Stage 2 newsletter. Residents can subscribe by visiting ottawa.ca/stage2 or by emailing stage2@ottawa.ca.
If you have any questions regarding the above, please do not hesitate in emailing the Stakeholder Relations Lead for Ward 8; Meghan Alexander – Meghan.Alexander@Ottawa.ca
Cleary Avenue at Richmond Road - Notice of Long-Term Road Closure
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, Cleary Avenue will be closed to vehicles at Richmond Road.
WHAT:
This is a long-term closure of Cleary Avenue and Richmond Road intersection. A new access road with a signalized intersection has been constructed from Richmond Road through Kristy’s to Cleary Avenue.
WHEN:
The closure of Cleary Avenue and the opening of a new intersection at Kristy’s (809 Richmond Road) at Richmond Road, Monday, November 21 until the end of 2024.
WHY:
The closure of Cleary Avenue is required to facilitate construction of the Cut and Cover Byron Tunnel, from Byron Linear Park to the Sir John A. Macdonald Parkway (SJAM), across Richmond Road.
WHERE:
Cleary Avenue at Richmond Road.

ANTICIPATED IMPACTS:
A new access road with a signalized intersection has been constructed from Richmond Road through Kristy’s (809 Richmond Road) to Cleary Avenue. This road is an exclusive “Private Entrance” to the Unitarian Congregation and Unitarian House properties, the River Parkway Children’s Centre and 75 Cleary Avenue. This includes residents and approved visitors to these properties, as well as anyone attending the congregation or Children’s Centre, or conducting approved business access to the properties.
Space has been created to allow trucks and service delivery vehicles, etc., to 75 Cleary to make a 3-point turn to return back along Cleary Avenue and through the new access road to Richmond Road.
Motorists should adhere to detours, traffic control signage, posted speed limits, allow for added
travel time and use extra caution when moving through active construction corridors as traffic
patterns change.
Snow clearing activities will be maintained.
A temporary pathway has been constructed from Richmond Road along the private roadway and north of the overflow parking lot to connect to the multi-use pathway along the Sir John A. Macdonald Parkway (SJAM). Pedestrians and cyclists should use extra caution and adhere to posted signage to ensure safety.
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
ACCESSIBILITY:
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2 and click ‘Connect with Us’ and select updates for “Sherbourne Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations,
Rail Construction Program,
City of Ottawa
Westbound Richmond Road Between New Orchard Avenue and McEwen Avenue - Notice of Long-Term Closure and Detour
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, Richmond Road will be closed to vehicles travelling westbound between New Orchard Avenue to McEwen Avenue. Vehicles will be detoured along Ambleside Drive./span>
WHAT:
Motorists traveling westbound on Richmond Road will be detoured onto New Orchard Avenue, Ambleside Drive and McEwen Avenue to facilitate the closure of westbound Richmond Road between New Orchard Avenue and McEwen Avenue
WHEN:
Sunday September 11, 2022, until the end of 2023.
WHY:
Construction of the Byron Tunnel across Richmond Road from McEwen Park
takes place in a very constrained area. From Hartleigh Avenue to
Richardson Avenue the space between the tunnel area and the adjacent residential
properties is constrained. To support construction and schedule, only 1 lane
(eastbound traffic) can be maintained on Richmond Road.
WHERE:
Westbound Richmond Road, New Orchard Avenue to McEwen Avenue

ANTICIPATED IMPACTS
Motorists travelling westbound on Richmond Road will detour to New Orchard Avenue, travel west along Ambleside Drive, travel south along McEwen Avenue and re-enter Richmond Road at McEwen Avenue.
Eastbound motorists on Richmond Road will not be impacted.
Richmond Road businesses within the detoured corridor remain open and accessible. Access to businesses on Richmond between McEwen and New Orchard for eastbound motorists remains unchanged whereas westbound motorists will follow the signage posted on site.
Motorists should adhere to detours, traffic control signage, posted speed limits, allow for added travel time and use extra caution when moving through active construction corridors as traffic patterns change.
The sidewalk on the north side of Richmond Road will be closed from 955 Richmond (Ottawa Honda) to McEwen Avenue. Pedestrians and cyclists will be detoured along a temporary pathway north of the construction site across McEwen Park terminating at the intersection of Ambleside Avenue and McEwen Avenue, or along the new sidewalk on Ambleside Avenue.
Two new controlled pedestrian crossings have been installed on New Orchard Avenue and Ambleside Drive.
Pedestrians and cyclists should use extra caution and adhere to posted signage when localized detours are in-place, to ensure safety.
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2 and click ‘Connect with Us’ and select updates for “New Orchard Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations, Rail Construction Program, City of Ottawa
Richardson Avenue closed at Richmond Road - Notice of Long-Term Road Closure
As part of the Stage 2 O-Train Light Rail Transit (LRT) project, Richardson Avenue will be closed to vehicles between Richmond Road and Byron Avenue.
WHAT:
Long-term Closure, Richardson Avenue, between Richmond Road and Byron Avenue.
WHEN:
Sunday September 11, 2022, until Sunday November 19, 2023.
WHY:
The closure of Richardson Avenue is required to facilitate construction of the Cut andCover Byron Tunnel in this area.
WHERE:
Richardson Avenue between Richmond Road and Byron Avenue.

ANTICIPATED IMPACTS
Motorists traveling northbound on Richardson Avenue will have to turn right onto Byron Avenue. There will be no access to Richardson Avenue southbound from Richmond Road.
Motorists should adhere to detours, traffic control signage, posted speed limits, allow for added travel time and use extra caution when moving through active construction corridors as traffic patterns change.
Pedestrians and cyclists should use extra caution and adhere to posted signage when localized detours are in-place, to ensure safety.
The construction work outlined in this notice is subject to change. Work may be delayed or extended due to weather or other unforeseen circumstances.
Accessibility is an important consideration for the Stage 2 LRT project. The Stage 2 team makes every effort to provide access through and around construction sites. If you require special accommodation, please contact stage2@ottawa.ca.
The safety of the public and workers is paramount, and we thank you for your patience during construction.
Future work is required in this area. Additional construction updates, such as changes to work sequencing and the duration or impact of this work will be communicated via the Stage 2 project e-newsletter. To receive these electronic updates please sign up at Ottawa.ca/Stage2 and click ‘Connect with Us’ and select updates for “New Orchard Station”. For other accommodations, or questions, please contact:
Damon Berlin
Stakeholder Relations, Rail Construction Program, City of Ottawa
Westbound Pinecrest Road Off-ramp - Notice of Closure
Last updated: September 19, 2023
Date posted: May 31, 2023
The Stage 2 LRT team will undertake significant construction activities on the O-Train West extension in preparation for future tracks and stations. Starting overnight on November 1, Highway 417 westbound off-ramp to Pinecrest will be closed until fall 2023 to safely complete construction of the future LRT that will run along the existing Transitway corridor, on the north side of Highway 417. The guideway will run in a trench underneath Pinecrest Road and Moodie Drive. Select ramps at these locations must be re-built and/or shifted in order to accommodate construction activities for the guideway.
Construction activities have been scheduled to minimize the duration and extent of impacts on all modes of transportation and the local community. Cycling and pedestrian routes will remain open during construction. The final design includes some enhanced connectivity features at some locations, such as new sidewalks and multi-use pathways. For each closure, signed vehicle detours and variable portable message signs (VPMS) will be provided.
When: Until December 22, 2023
Where: Highway 417 westbound off-ramp to Pinecrest Road

From Hwy 417 to southbound Pinecrest Road
- Exit westbound Highway 417 using Woodroffe Avenue North
- Left on to Carling Avenue
- Left onto Pinecrest Road

From Hwy 417 to northbound Greenbank Road
- Exit westbound Highway 417 using Woodroffe Avenue South
- Right onto Baseline Road
- Right onto Greenbank Road
Have questions or comments?
We welcome your questions or comments on these works. Please reach out to the Stage 2 team at Stage2@ottawa.ca
Stay Connected!
Sign up for the Stage 2 LRT newsletter to stay up to date on Stage 2 progress.