12.          MOTION TO DEFER THE PAYMENT OF DEVELOPMENT CHARGES AND BUILDING PERMIT FEES, AND WAIVE THE ROAD ENCROACHMENT FEES, FOR ALL PHASES OF THE RESIDENTIAL DEVELOPMENT PROPOSED BY GROUPE LEPINE ON BLOCK 6 (PLAN 4M-1325)

 

                MOTION VISANT À REPORTER LE PAIEMENT DES REDEVANCES D’EXPLOITATION ET DES DROITS DE PERMIS DE CONSTRUIRE, ET À RENONCER AUX DROITS D’EMPIÈTEMENT POUR TOUTES LES PHASES DU LOTISSEMENT RÉSIDENTIEL PROJETÉ PAR LE GROUPE LÉPINE SUR L’ÎLOT 6 (PLAN 4M-1325)

 

 

COMMITTEE RECOMMENDATION AS AMENDED

 

That Council waive the road encroachment fees, for all Phases of the residential development proposed by Groupe Lepine on Block 6 (Plan 4M-1325).

 

 

Recommandation MODIFIÉES DU Comité

 

Que le Conseil renonce aux droits d’empiètement pour toutes les phases de l’ensemble résidentiel projeté par le Groupe Lépine sur l’îlot 6 (Plan 4M-1325)

 

 

 

 

 

 

Documentation

 

1.         Corporate Services and Economic Development Committee’s report dated 26 March 2010 (ACS2010-CMR-CSE-0018).

 

2.         Extract of Draft Minute, 4 May 2010 to be distributed prior to Council.

 

 


Report to/Rapport au :

 

Corporate Services and Economic Development Committee

Comité des services organisationnels et du développement économique

and Council / et au Conseil

 

26 March 2010 / le 26 mars 2010

 

Submitted by/Soumis par : Kanata North Ward/quartier Kanata-Nord Councillor/Conseillère Marianne Wilkinson

 

Contact Person/Personne ressource :Marianne Wilkinson,

Councillor, Kanata North Ward / conseiller, quartier Kanata-Nord

(613) 580-2474, Marianne.Wilkinson@ottawa.ca

 

Kanata North (4) Kanata-Nord

Ref N°: ACS2010-CMR-CSE-0018

 

 

SUBJECT:

MOTION TO DEFER THE PAYMENT OF DEVELOPMENT CHARGES AND BUILDING PERMIT FEES, AND WAIVE THE ROAD ENCROACHMENT FEES, FOR ALL PHASES OF THE RESIDENTIAL DEVELOPMENT PROPOSED BY GROUPE LEPINE ON BLOCK 6 (PLAN 4M-1325)

 

 

OBJET :

MOTION VISANT À REPORTER LE PAIEMENT DES REDEVANCES D’EXPLOITATION ET DES DROITS DE PERMIS DE CONSTRUIRE, ET À RENONCER AUX DROITS D’EMPIÈTEMENT POUR TOUTES LES PHASES DU LOTISSEMENT RÉSIDENTIEL PROJETÉ PAR LE GROUPE LÉPINE SUR L’ÎLOT 6 (PLAN 4M-1325)

 

REPORT RECOMMENDATIONS

 

That the Corporate Services and Economic Development Committee recommend that Council:

 

1.                  Defer the payment of development charges and building permit fees for a period of 24 months from the date of issuance of each building permit, without interest or penalty,

 

2.                  Waive the road encroachment fees, for all Phases of the residential development proposed by Groupe Lepine on Block 6 (Plan 4M-1325).

 

 

RECOMMANDATIONS DU RAPPORT

 

Que le Comité des services organisationnels et du développement organisationnel recommande au Conseil :

 

1.                  De reporter le paiement des redevances d’exploitation et des droits de permis de construire pour une période de 24 mois à compter de la date de délivrance de chaque permis de construire, sans intérêt ni pénalité;

 

2.                  De renoncer aux droits d’empiètement pour toutes les phases de l’ensemble résidentiel projeté par le Groupe Lépine sur l’îlot 6 (Plan 4M-1325)

 

 

BACKGROUND

 

The rental housing market, particularly in communities outside the Greenbelt, remains low, particularly for affordable rates.  In Kanata, where there are about 43,000 jobs, the rental situation is particularly difficult with long waits associated with getting a rental unit. 

 

As stated in the report on the Holmstead Holdings Report attached as Attachment B, a healthy rental market is needed to sustain a healthy local economy.  Few local companies have taken the risk of building rental units due to high land and construction costs. The Lepine Group has found it marginal to build such units and has asked for the same consideration as given to Holmstead in 2002.  The Holmstead apartments are full, despite high rental rates, indicating the need for more rental housing.

 

The Lepine development consists of 4 high rise apartment buildings that will eventually contain approximately 750 units.  The site is close to the location of a transitway station, part of the east-west transitway that is scheduled to be built as part of the Transportation Master Plan.  The environmental assessment has been completed and design of that portion of the transitway is presently underway.  Hence this development is being designed to encourage transit use and will have hundreds of bicycle parking areas for tenants as well as one or more vrtucars.

 

The first phase of development is for one building of 146 units, with 30% meeting the city’s affordability criteria as shown in attachment A.  The site is located in the Kanata Town Centre area designated as Central Business District.  This area is to have high density housing and employment, to meet the objectives of the Official Plan.  It is in a new subdivision so the roads adjacent to the site have not yet been fully completed and there is no local traffic on the road on which this building is to be located.  On the other side is a storm water pond.  The road has just been connected to Kanata Ave.  That link will be used for construction access but is not yet open for public use.  Hence there is no obstruction to the public for any short term use of the road allowance for construction purposes as there would be in central Ottawa.  Council has recently waived encroachment fees for rental units being constructed in Ottawa Centre and this would make sense for this project as well.

 

In 2002 staff recommended the deferral of development charges and fees for the Holmstead project until each building was constructed.  They pointed out that it was to promote new high-rise rental buildings where there is a shortage such as in the west-end of the city.  That shortage continues to exist and this deferral will help to keep the number of affordable units at 30%.  All required fees will be paid in full at the end of the deferral period.

 

The Councillor submitted the following motion for consideration at the Corporate Services and Economic Development Committee meeting on 4 May 2010.

 

WHEREAS, the applicant, Groupe Lepine, has submitted a Site Plan Control Application for the property known municipally as 1001 Canadian Shield Avenue in order to permit the development of a residential apartment complex; and

 

WHEREAS, Site Plan Control approval has been issued for Phase 1 of the proposed development on February 16, 2010 and the Site Plan Agreement is imminent; and

 

WHEREAS Phase 1 of the development includes 146 rental apartment units within a ten- (10) storey building, as well as a club house for residents, and this complex will be an important contribution to the local housing market as it will constitute only the second rental development in the Kanata Town Centre; and

 

WHEREAS a substantial portion of the units will meet the City’s housing affordability criteria and, further, these units will contribute to meeting the housing demand for rental units in Kanata and will increase the diversity of housing supply in Kanata; and

 

WHEREAS this development is within walking distance of the Transitway planned through Kanata; and

 

WHEREAS a similar request was obtained for Holmstead Holdings as a means of encouraging the construction of rental units outside the Greenbelt; and

 

WHEREAS the roads in the vicinity are new subdivision roads with no other development presently using them so that any encroachment will not cause any disruption of traffic; and

 

WHEREAS the project will ultimately provide a total of 739 rental units in

Kanata Town Centre at full build-out;

 

THEREFORE BE IT RESOLVED that the Corporate Services and Economic Development Committee recommend to Council deferral of the payment of development charges and building permit fees, and waive the road encroachment fees, for all Phases of the residential development proposed by Groupe Lepine on Block 6 (Plan 4M-1325) for a period of 24 months from the date of issuance of each building permit, without interest or penalty.

 

RURAL IMPLICATIONS

 

There are no rural implications.

 

 

CONSULTATION

 

This item will be advertised in the local dailies as part of the Public Meeting Advertisement on Friday preceding the Corporate Services and Economic Development Committee Meeting.

 

Planning and Growth Management Comments

 

The following information is provided:

 

The arrangements with Holmstead Holdings reflected the regulatory landscape of 2001 and 2002 when deferrals of local development charges were not contemplated in the then development charge by-laws.  Unique circumstances necessitated the arrangement as a means of permitting the project to proceed despite additional financial hurdles presented by a front-end agreement.  Thus, in addition to arranging for the deferral of the development charges by way of a report to Council, it was agreed to allow for the deferral of the building permit fees as well. 

 

It is noted that the statutory and regulatory parameters have since changed, requiring a different approach should Council agree to provide the relief being sought.

 

Development Charges

 

With respect to development charges, the City harmonized the development charges by-laws in 2004.  The Development Charges Act, s. 27 specifically permits a municipality by agreement to collect a development charge at a time after a building permit is issued.  In accordance with this authority, the present Development Charges By-law 2009-216 provides for the deferral of development charges.  The standard practice is that interest at the rate of 10 per cent is charged.

 

Building Permit Fees

 

The Building Code Act requires the payment of building permit fees at the time of submission of the application.  This requirement was introduced July 1, 2005 as part of the many changes to the regulatory regime through the enactment of the Building Code Statute Law Amendment Act (Bill 124).  In contrast to the Development Charges Act, the Building Code Act, does not provide for payment at a time after the building permit is issued.  As a result, the building permit cannot be issued without full payment of all applicable fees.  The arrangement with Holmstead Holdings for the deferral of both the development charges and the building permit fees was made in 2001/2, prior to the new legislation. 

 

It is noted that large projects such as the one proposed are usually phased over a period of time with the phasing of permits and related fees and this, if optioned, would have the effect of deferring payments over a period of time, thus obtaining the relief being sought.

 

In addition, in October 2009, Council did approve a new program for providing grant funding for reimbursing development related fees, including building permit fees, for construction projects undertaken by certain charitable and non-profit organizations.  There is no program in place for providing grant funding to offset waivers of fees for other projects, such as this one, although Council can specifically approve a grant to offset development related fees, including building permit fees, through the City-Wide Capital Reserve Fund. 

 

Encroachment Fees

 

The arrangement in 2001/2 with Holmstead Holdings did not include a fee waiver of encroachment fees.  Waiver of encroachment fees may be provided only for registered charitable and non-profit organizations, such as the United Way and the Santa Claus Parade.

 

Should the fees be waived, the estimated lost revenue loss would be $43,000.

 

 

LEGAL/RISK MANAGEMENT IMPLICATIONS

 

As discussed above, it is within the jurisdiction of Council to defer development charges without interest and to waive the encroachment fees.  In the opinion of Legal Services, the fee for the building permit must be paid prior to building permit issuance.

 

 

FINANCIAL IMPLICATIONS

 

There are no financial implications associated with the deferral of payment of development charges; fees owed would be subject to annual interest of 10%, in accordance with the City’s standard practice.

 

As legislation does not permit deferral of building permit fees, financial implications are not applicable.

 

Estimated lost revenues of $43,000 are associated with the recommendation to waive road encroachment fees for a 24-month period from the date of issuance of each building permit.

 

 

SUPPORTING DOCUMENTATION

 

Document 1:   Chart of affordability of units

Document 2:   Report to Council from CSEDC on April 10, 2002 on Holmstead Holdings (ACS2002-DEV-POL-0011)

 

 

DISPOSITION

 

Staff to take appropriate action as directed by the Committee and Council.


 



Document 2

 

Report to/Rapport au :

 

Corporate Services and Economic Development Committee

Comité des services organisationnels et du développement économique

 

and Council/et au Conseil

 

21 March 2002 / le 21 mars 2002

 

Submitted by/Soumis par :  Ned Lathrop,  General Manager/Directeur général

Development Services Department / Services d’aménagement

 

Contact/Personne-ressource :  Ned Lathrop, General Manager/Directeur général,

Development Services Department / Services d’aménagement

580-2424,ext.25659, ned.lathrop@city.ottawa.on.ca

 

 

Ref N°:   ACS2002-DEV-POL-0011

 

 

SUBJECT:    DEFERRAL OF FEES – HOLMSTEAD HOLDINGS –
CASTLEFRANK ROAD AT CAMPEAU DRIVE

 

OBJET:          REPORT DE DROITS – HOLMSTEAD HOLDINGS – CHEMIN CASTLEFRANK, À L’ANGLE DE LA PROMENADE CAMPEAU

 

 

REPORT RECOMMENDATION

 

That the Corporate Services and Economic Development Committee recommend Council agree to defer the payment of development charges and building permit fees for the rental housing project owned by Holmstead Holdings on Castlefrank Road at Campeau Drive for a period of 24 months from the date of issuance of each building permit, with no interest penalty.

 

RECOMMANDATION DU RAPPORT

 

Que le Comité des services organisationnels et du développement économique recommande au Conseil municipal d’accepter de reporter le paiement des redevances d’exploitation et des droits de permis de construction, imputables au projet d’habitations à loyer appartenant à Holmstead Holdings, sur le chemin Castlefrank, à l’angle de la promenade Campeau, pendant une période de 24 mois à compter de la date d’émission de chaque permis de construction, sans pénalité d’intérêt.

 

BACKGROUND

 

Holmstead Holdings is in the process of developing a major rental housing complex at the intersection of Castlefrank Road and Campeau Drive in the former City of Kanata.  The project consists of three buildings, each fifteen stories in height, which will contain a total of 360 units when completed.  The property is located in the Central Business District of the Kanata Town Centre.  The developer has approached the City to defer the development charges and building fees associated with the project for a period of two years.  This would not include payment of the Terry Fox/Campeau Drive storm sewer levy or education development charges.

 

The reason for the request relates to the financial hardships associated with high-rise rental housing development in a climate of high construction costs.

 

DISCUSSION

 

Strong employment-driven population growth over the last five years, particularly in the west-end of the city, combined with a steady decline in new rental housing starts, has significantly reduced the availability of rental housing in Ottawa.  This is reflected in the current rental vacancy rate of 0.8% in October, 2001 for Ottawa, well below the 3% level indicative of a healthy rental market, and one of the lowest rates in the country.

 

A healthy rental market is needed to sustain a healthy local economy.  However, the private sector has been reluctant to undertake new rental projects as it involves relatively high risk compared to other forms of housing, and based on current building costs, new rental housing is not deemed to be profitable.  High-rise non-combustible construction, as in the case of the Holmstead project, requires the use of concrete which is considerably more expensive than wood frame construction.  Any assistance the city provides would help defray the up front cost of construction until the buildings are completed and occupancy permits are issued.  Twenty-four months from the time of issuance of the building permit is considered adequate time for this to occur.

 

The three new towers will be a welcome addition to the streetscape of the Kanata Town Centre.  The official plan of the former City of Kanata states that the Central Business District of the Kanata Town Centre “ is to become an urban place that provides the primary employment, civic and cultural focus for Kanata, complemented by higher density residential uses”.  The new rental project is in keeping with the high density land use designation and is conveniently located in close proximity to the transitway.  The new residential units will support the housing needs of the local high technology work force.  It is important for existing and potential employees to have access to a range of housing types and tenures and this has been lacking in the west end. This will be the first high-rise rental housing in the area and hopefully will encourage other builders to consider doing similar projects.  The deferral of the various charges cited in the recommendation is considered an experiment to promote new high-rise rental housing in areas where there is a shortage such as in the west-end of the city.   Staff recommend approval of the request for the deferral of development charges and fees for the subject property.

 

CONSULTATION

 

As this is an administrative matter, public consultation is not required.

 

FINANCIAL IMPLICATIONS

 

The following development charges and building permit fees associated with Tower A only (Towers B and C have yet to progress to building permit application stage) will be deferred for twenty-four months.  Based on these figures it is expected that similar amounts for Towers B and C will be deferred.

 

Fee/Charge

# of units

Rate

Subtotal

Total

RMOC DC

2 (1BR)

118 (2BR)

3453/unit

5428/unit

6,906

640,504

$647,410

Kanata DC

2

118

2452/unit

3855/unit

4,904

454,890

$459,794

Kanata Town Centre Sanitary Sewer Levy

2

118

211/unit

332/unit

422

39,176

$39,598

Building permit Fee

 

$10.50/$1000 based on

$8,343,315

87,604.81

$87,604.81

 

 

 

 

$1,234,406.80

 

The proposed deferral of fees for Tower A amount to $1.2 million.  See the table above.  The lost interest income on this revenue amounts to approximately $95,000 over the 24 months of deferral.

 

ATTACHMENTS

 

Document 1- Location Plan

 

DISPOSITION

 

Legal Services shall prepare and register against title an agreement to recognize the deferral and provide for the ultimate payment.

Document 1

Location Plan

 

 


                                                                                                                                                           


            DEFERRAL OF FEES – HOLMSTEAD HOLDINGS –
CASTLEFRANK ROAD AT CAMPEAU DRIVE

            REPORT DE DROITS – HOLMSTEAD HOLDINGS –
CHEMIN CASTLEFRANK, À L’ANGLE DE LA PROMENADE CAMPEAU

ACS2002-DEV-POL-0011

 

The report recommendation was approved during the consent agenda, with the noted dissent.

 

That the Corporate Services and Economic Development Committee recommend Council agree to defer the payment of development charges and building permit fees for the rental housing project owned by Holmstead Holdings on Castlefrank Road at Campeau Drive for a period of 24 months from the date of issuance of each building permit, with no interest penalty.

 

CARRIED with Councillor H. Kreling dissenting.