Project overview
Project description
The project involves the installation of a new 1350mm diameter overflow storm sewer on Fisher Avenue between Meadowlands Drive and Dynes Road. The new overflow storm sewer will connect the existing storm collector sewer on Meadowlands Drive to the existing outlet storm sewer on Dynes Road. The watermain will be replaced on Fisher Avenue between Meadowlands Drive and Dynes Road.
The project also includes full road reconstruction with sidewalks, dedicated bike lanes along Fisher Avenue from Meadowlands Drive to Dynes Road and a fully protected intersection at Fisher Avenue and Meadowlands Drive.
Project timing
Design completion: spring 2025
Construction start: summer 2025
Construction completion: fall 2026
Project budget
Approved project funds to date are $16 million.
Public engagement
A public information session will be held prior to construction.
The project’s scope was originally included as part of the recently completed Wallford, Deer Park, Hilliard & Farlane integrated project.
Previous consultations as part of the original project included:
- Consultation with residents regarding road geometry (May 2018)
- Pre-construction public information session (February 2020)
Accessibility
Accessibility is an important consideration for the City of Ottawa. The City makes every effort to provide access through and around construction sites. If you require a disability-related accommodation, please contact the project team listed below. Accessible formats(link opens email application) and communication supports are available, upon request.
Safety
The City of Ottawa is committed to safety in and around project sites. The project team continues to work closely with the industry and to comply with recommendations provided by municipal, provincial and federal health officials, as well as the Ministry of Labour, Immigration, Training and Skills Development.
Contact information
Should you have any inquiries, please do not hesitate to contact:
City Project Manager
Matthew Raymond(link opens email application), P.Eng.
Senior Engineer, Infrastructure Projects
Design and Construction – Municipal
100 Constellation Drive, Ottawa, ON K2G 6J8
Tel.: 613-580-2424, ext. 21813