Cumberland Sanitary Pumping Stations 2, 3 & 4 Rehabilitation

On this page
Project status
Construction underway

Project overview

Project description

The City of Ottawa is undertaking the design and construction planning to rehabilitate the following three (3) existing sanitary pumping stations (SPS):

  • Cumberland SPS 2, 361 Roxdale Avenue, Ward 1, built in 1982
  • Cumberland SPS 3,1571 St Georges Street, Ward 1, built in 1978
  • Cumberland SPS 4, 327 Du Grand Bois Avenue, Ward 19, built in 1986

The main objective is to improve the reliability of operation for these SPSs by replacing equipment that has reached the end of their life expectancy, improving City Operations’ staff ability to safely and efficiently operate and maintain them and reduce station down time during failures or extreme weather conditions.

The locations of the pumping stations are shown in the images below:

Cumberland SPS 2

This is an image of a map showing the location of the Cumberland Sanitary Pumping Station 2 at 361 Roxdale Avenue at the intersection with Prestwick Drive.

 

Cumberland SPS 3

 

Cumberland SPS 4

This is an image of a map showing the location of the Cumberland Sanitary Pumping Station 4 on 327 Du Grand Bois Avenue at the intersection with Prestwick Drive.

 

The planned work includes:

  • Replacement of equipment and components that have reached the end of their useful life.
  • Required rehabilitation and upgrades of these stations’ wet wells and access safety components.
  • Upgrades of electrical, controls and communication elements to the current City standards.
  • Installation of new underground bypass chambers at Cumberland SPS 2 and Cumberland SPS 4

Notice to residents will be sent out to advise of works prior to commencement.

The City makes every effort to minimize the impacts of construction on the community. Work will be implemented in sequence – one station at a time. It is expected that there will not be any interruption to the service for the duration of this project. Traffic will be impacted when the temporary bypass piping system is being installed and tested. Access for pedestrians and cyclists will be maintained.

Project timing

Construction:     

  • SPS 2 – expected to be completed in July 2024
  • SPS 3 – expected to start in spring 2025
  • SPS 4 – expected to start in summer 2024

Project budget

Approved project funds to date are $5.2 M.

Accessibility

Accessibility is an important consideration for the City of Ottawa. The City makes every effort to provide access through and around construction sites. If you require a disability-related accommodation, please contact the project team listed below. Accessible formats and communication supports are available, upon request.

Safety

The City of Ottawa is committed to safety in and around project sites. The project team continues to work closely with the industry and to comply with recommendations provided by municipal, provincial and federal health officials, as well as the Ministry of Labour, Immigration, Training and Skills Development.

Contact information

For any emergency outside normal working hours, please call the City at 3-1-1.
For general project information, please contact the City’s Project Manager.
For construction related questions or concerns, please contact the Contractor Representative.

City Project Manager
Kim Pearce
Senior Project Engineer
Design and Construction – Buildings
100 Constellation Drive, Ottawa, ON K2G 6J8
Tel.: 613-580-2424, ext. 25594

City On-Site Inspector
Roberto Bascelli
Construction Technician
Design and Construction – Facilities
100 Constellation Drive, Ottawa, ON K2G 6J8
Tel.: 613-880-0855

Contractor Representative
Emal Sataar, Project Manager
Black & McDonald Ltd.
Tel.: 613-913-4202