Greenbank Realignment and Southwest Transitway Extension

On this page
Project status
Planned

Project overview

Project description

The objective of the project is to complete an updated functional design, preliminary design and detailed design of the realigned Greenbank Road and Southwest Transitway Extension between Marketplace Avenue/ Chapman Mills Drive in the north and Barnsdale Road in the south including a new 610 mm diameter transmission watermain along the realigned Greenbank Road from Market Place to the south side of the Jock River.

The project will include the design of a new 4-lane arterial roadway with 2-lane segregated median Bus Rapid Transit and facilities for pedestrians and cyclists along the corridor. The project also includes a new bridge over the Jock River, a Park and Ride facility near the southern terminus of the future transitway corridor, and design of new watermains and sewers.

The project will be guided by the work completed as part of past Environmental Assessment (EA) studies, which each involved an extensive study process and included consultation with the public. In advance of the preliminary design, an updated functional design will be developed to reflect newer design standards developed since the following various EAs were completed:

  • Greenbank Road (from Malvern Drive to Cambrian Road) Class EA Study (December 2006);
  • Southwest Transitway Extension (from Strandherd Drive to Cambrian Road) Individual EA Study (December 2006);
  • Realigned Greenbank Road and Southwest Transitway Extension (Cambrian Road to Barnsdale Road) EA Study (July 2014);
  • Chapman Mills Drive Extension (Longfields Drive to Strandherd Drive) and Bus Rapid Transit Corridor (Greenbank Road to Borrisokane Road) EA Study (November 2016); and
  • Greenbank Watermain EA (October 2017).

Field investigations in support of design (e.g., geotechnical, hydrogeological and environmental drilling, natural environment studies, topographic surveying, etc.) will be undertaken in 2021. Impacts to residents are anticipated to be minimal and affected residents will be notified. Affected landowners will be contacted for Consents to Enter, as required.

Land acquisitions requirements vary along the corridor. The exact property requirements will be determined during detailed design in coordination with ongoing development. Tendering and construction of this project is not currently included in the scope of this project.

Key plan [ 298 KB ]

Project timing

A general summary of the estimated design timelines are as follows:

  • Winter 2020/2021 – Consultant selection and updated functional design start
  • Late Spring/Summer 2021 – First Public Information Session
  • Spring/Fall 2021 – Field Investigations
  • Winter 2024 – Finalize Preliminary Design
  • Fall 2025 – Finalize Detailed Design
  • 2024-2025 – Property Acquisition

The above timelines are estimated and may change as the project progresses.

The construction timelines are yet to be determined and will be dependent on future budget approval and coordination with other infrastructure projects across the City. Currently, construction is planned to start in 2030 or later and will depend on future Council budget deliberations and transit affordability considerations. The construction phase of this project will occur over multiple years. The Greenbank Road Realignment and Southwest Transitway Extension (Chapman Mills to Cambrian) is tentatively scheduled to begin construction in 2031.

The City is completing an update of the Transportation Master Plan which is currently scheduled for completion in fall 2024. As part of this work, the City will be reviewing the prioritization and timing of future infrastructure projects, including the re-alignment of Greenbank Road and Southwest Transitway Extension. Based on this review, the timing of future projects may be adjusted based on network needs and available funding.

Public engagement

Stay tuned on this webpage and our social media pages for information about our public information sessions and how you can contribute feedback to the project!

Our first public information session was held on June 24, 2021 to present the updated functional design drawings to the public. As part of the online engagement session between June 24 and July 8, residents were to review the design, ask questions and provide comment on the proposed works. Presentation materials are available for review below.

Additional public information sessions will be scheduled and held throughout the design process. Residents will be notified of these events.

Accessibility

Accessibility is an important consideration for the City of Ottawa. The City makes every effort to provide access through and around construction sites. If you require a disability-related accommodation, please contact the project team listed below. Accessible formats and communication supports are available, upon request.

Safety

The City of Ottawa is committed to safety in and around project sites. The project team continues to work closely with the industry and to comply with recommendations provided by municipal, provincial and federal health officials, as well as the Ministry of Labour, Immigration, Training and Skills Development.

Contact information

For further information or to provide comments, please contact the City’s project manager.

City Project Manager
Patrick Duquette, P.Eng.
Senior Engineer, Infrastructure Projects
100 Constellation Drive, Ottawa, ON K2G 6J8
Tel.: 613-580-2424, ext. 16038

Consultant Project Manager
Gordon Chamberlain, P.Eng.
Principal, Transportation
Stantec Consulting Ltd.
Suite 400 - 1331 Clyde Avenue, Ottawa, ON K2C 3G4
Tel: 613-724-4390

Plans presented at the online engagement opportunity (June 24 to July 8, 2021)

The City of Ottawa continues to take precautionary steps to protect members of the public. As an alternative to hosting in-person public information sessions, information is being posted to Ottawa.ca and virtual information sessions are being held. The City remains committed to keeping the public informed of projects occurring in your neighborhood.

The City of Ottawa invites you to review and provide comments on the Greenbank Realignment and Southwest Transitway Extension Project by July 8, 2021.

A virtual public information session was held on Thursday, June 24, 2021, at 5 pm.

For further information about this project and/or to submit comments on the project, please contact the City project manager.