Project overview
Project description
The West Urban Community Wastewater Collection System Master Servicing Plan (WUC-WCSMSP) study was finalized in July 2012. This study confirmed completing the North Kanata Trunk Sewer (NKTS), connecting it to the Marchwood Trunk Sewer, and converting the March Road PS to a low lift station as the preferred option for wastewater servicing of the Kanata North Development. The NKTS construction project was completed in September, 2021.
The existing March Road Wastewater pumping station will be converted from a high-lift to a new low-lift station, discharging into the North Kanata Trunk sewer on Legget Drive. The project involves establishing the station bypass pumping operation, connecting to the completed North Kanata Trunk sewer, constructing a new diversion structure and pre-fabricated FRP wet well immediately west of the existing pumping station, removing the existing control building, abandoning the existing wet well, constructing a new control building, decommissioning the last section of the East March Trunk Sewer and constructing a new 240m section of sanitary trunk sewer in the adjacent Farrar Road right of way.
Project timing
Design assignment completion: spring 2021
Tender Project and Award: summer 2021
Sewer and On-site construction: fall 2021- summer 2025
Project budget
Approved project funds to date are revised to $14,825,000.
Public engagement
Related work has been underway at the Pumping Station site at 305 Legget Drive since 2019. This project will continue that work and additional information regarding the scope of the project can be found with this website or by contacting the City project manager listed below.
Accessibility
Accessibility is an important consideration for the City of Ottawa. The City makes every effort to provide access through and around construction sites. If you require a disability-related accommodation, please contact the project team listed below. Accessible formats and communication supports are available, upon request.
Safety
The City of Ottawa is committed to safety in and around project sites. The project team continues to work closely with the industry and to comply with recommendations provided by municipal, provincial and federal health officials, as well as the Ministry of Labour, Immigration, Training and Skills Development.
Contact information
Should you have any inquiries, please do not hesitate to contact:
City Project Manager
Marc Tremblay, C.E.T.
Senior Project Manager, Infrastructure Projects
100 Constellation Drive, Ottawa, ON K2G 6J8
Tel.: 613-580-2424, ext. 14391
Consultant Contract Administrator
Christian Gagné, C.E.T.
Jacobs Engineering Group
1565 Carling Ave., Ottawa, ON K1Z 8R1
Cell: 613-266-7044
Contractor Project Manager
Sean McNamee
Black & McDonald
2460 Don Reid Drive, Ottawa, ON K1H 1E1
Tel.: 613-903-7700
Cell: 613-223-9081
Construction update (July 2024)
The City of Ottawa would like to take this opportunity to thank you for your patience during the construction of this project. We acknowledge the disruptions and inconvenience that you have faced and would like to let you know how much we appreciate your support and cooperation throughout the construction process.
What: The existing Wastewater Pumping Station located at 305 Legget Drive will be demolished and replaced with a new low-lift pumping station, complete with a standby diesel generator to power the station in the event of a loss of utility power. A new trunk sanitary sewer is being installed in the undeveloped portion of the Farrar Road right of way to facilitate the conversion. The final stage of the sanitary sewer work, located south of Marsh Sparrow Private, is now scheduled to proceed.
Why: The pump station conversion project is part of the final stage of the 2012 Master Servicing Plan for North Kanata, to reliably increase sewer capacity with increased emphasis on gravity flow through the recently completed North Kanata Trunk Sewer.
When: The final stage of the sanitary sewer work will begin in August 2024, with completion expected by fall 2024. The demolition of the existing Wastewater Pumping Station and establishment of the new station is scheduled for completion by spring 2025.
Where: The existing East March Trunk Sewer will be intercepted 240 metres north of Legget Drive and will be re-aligned to flow along the undeveloped portion of the Farrar Road right of way to the new pumping station location, constructed adjacent to the existing facility on Legget Drive. Additional smaller service piping lines will be constructed to connect the system, which are located within the City’s right of way or on existing service easements.
Who: The City has retained the general contractor, Black & McDonald with their civil sub-contractor R.W. Tomlinson Ltd., to complete the work.
Traffic impacts
On Legget Drive, the contractor will generally maintain a minimum of one lane of traffic in each direction when completing the work. During the installation of certain tie-ins to utilities or services, there will be short periods when Legget Drive will be reduced to a single lane controlled by flag persons during the day and signage over night. Pedestrian and cycling access will be maintained throughout the construction period.
Impact on the right of way and adjacent private properties
The reconstruction is within the City’s right of way but may result in some disruption to part of the private property directly adjacent to the work. The City will reinstate sections of landscaping, driveways and walkways that are disturbed by construction.
Construction disruptions
The Black & McDonald / R.W. Tomlinson Ltd. team will take every precaution to minimize interruptions to the everyday life of your family and/or operation of your business but, as you can appreciate, there may be some inconvenience during the course of the work, such as delays when travelling around the construction zone, noise and dust. You may also feel vibrations due to heavy equipment operations. Vibrations from construction activities are quite common and rarely cause any problems. The contractor may need to have dewatering pumps operating overnight during select times, but this equipment will be situated to minimize noise disturbances. We would like to thank you in advance for your patience and co-operation. For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255).
Construction notice (October 2021)
This notice is to inform you of construction work within a municipal right of way near your property, as part of the sewer system upgrades associated with the March Road WWPS Conversion Project. This work is being carried out by a Contractor retained by the City of Ottawa on both Legget Drive and the undeveloped portion of the Farrar Road right of way.
What: The existing Wastewater Pumping Station located at 305 Legget Drive will be demolished and replaced with a new low-lift pumping station, complete with a standby diesel generator to power the station in the event of a loss of utility power. A new trunk sewer and related underground infrastructure will be installed to facilitate the conversion.
Why: The pump station conversion project is part of the final stage of the 2012 Master Servicing Plan for North Kanata, to reliably increase sewer capacity with increased emphasis on gravity flow through the recently completed North Kanata Trunk Sewer.
When: The work will begin in November 2021, with completion expected by summer 2023.
Where: The existing East March Trunk Sewer will be intercepted 240 metres north of Legget Drive and will be re-aligned to flow along the undeveloped portion of the Farrar Road right of way to the new pumping station location, constructed adjacent to the existing facility on Legget Drive. Additional smaller service piping lines will be constructed to connect the system, which are located within the City’s right of way or on existing service easements.
Who: The City has retained the General Contractor, Black & McDonald with their civil sub-contractor R.W.Tomlinson Ltd., to complete the work.
Traffic impacts
On Legget Drive, the Contractor will generally maintain a minimum of one lane of traffic in each direction when completing the work. During the installation of certain tie-ins to utilities or services, there will be short periods when Legget Drive will be reduced to a single lane controlled by flag persons during the day and signage over night. Pedestrian and cycling access will be maintained throughout the construction period.
Impact on the right of way and adjacent private properties
The reconstruction is within the City’s right of way but may result in some disruption to part of the private property directly adjacent to the work. The City will reinstate sections of landscaping, driveways and walkways that are disturbed by construction. However, if you have plants or any other assets located within the City’s right of way that you want to preserve, we suggest that you move the plants/assets in preparation for the construction work.
Construction disruptions
The Black & McDonald/R.W. Tomlinson Ltd. team will take every precaution to minimize interruptions to the everyday life of your family and/or operation of your business but, as you can appreciate, there may be some inconvenience during the course of the work, such as delays when travelling around the construction zone, noise and dust. You may also feel vibrations due to heavy equipment operations. Vibrations from construction activities are quite common and rarely cause any problems. We would like to thank you in advance for your patience and co-operation. For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255).