Project overview
Project description
The following aging watermain and sanitary sewers are in poor condition and need replacement:
- Athlone Avenue between Scott Street and Byron Avenue
- Edgewood Avenue
- Lincoln Avenue between Churchill Avenue North and Edgewood Avenue
- Eden Avenue between Lincoln Avenue and Richmond Road
Full road reconstruction will be required on the streets in the locations where the sanitary sewer and the watermains are to be replaced. The street design will implement the City’s 30 km/h Local Residential Streets speed limit policy, and will include the introduction of new sidewalks in selected locations. Best efforts to mitigate project impacts on existing mature trees will be taken.
Project timing
Design: December 2023 to February 2025
Construction start: May 2025
Construction completion: December 2026
Project budget
Approved project funds to date are $8.5 million.
Public engagement
A public information session is expected to be held in September 2024 to present the design drawings to the public. At this time attendees will be able to review the design, ask questions and provide comment on the proposed works. Other methods to involve community stakeholders will be implemented.
Accessibility
Accessibility is an important consideration for the City of Ottawa. The City makes every effort to provide access through and around construction sites. If you require a disability-related accommodation, please contact the project team listed below. Accessible formats and communication supports are available, upon request.
Safety
The City of Ottawa is committed to safety in and around project sites. The project team continues to work closely with the industry and to comply with recommendations provided by municipal, provincial and federal health officials, as well as the Ministry of Labour, Immigration, Training and Skills Development.
Contact information
Should you have any inquiries, please do not hesitate to contact:
City Project Manager
Daniel Brazeau, C.E.T.
Senior Project Manager, Infrastructure Services
Design and Construction – Municipal
100 Constellation Drive, Ottawa, ON K2G 6J8
Tel: 613-580-2424, ext. 22318
Additional field investigations (September 2024)
The City of Ottawa will undertake hydrovac excavation investigations in your neighbourhood. This work is being done to locate existing Enbridge gas mains, Bell lines and crossing utilities as part of the design phase of the Athlone, Lincoln, Edgewood and Eden Avenues - Integrated Renewal project.
What: The investigation work will involve hydrovac excavation to locate Enbridge gas mains, Bell lines and crossing utilities at select locations. The work will confirm the horizontal and vertical location of the gas mains, Bell lines, and crossing utilities to inform the ongoing design. The excavations will be reinstated. The investigations will be done by workers and equipment, as needed. Parking lanes will be temporarily closed during the work.
Why: This work supports the Athlone, Lincoln, Edgewood and Eden Avenues – Integrated Renewal preliminary and detailed designs.
When: The field investigation work will commence in October 2024 and could take up to two days. The work will be conducted between the hours of 8 am and 5 pm, Monday to Friday.
Where: At localized spots along Athlone, Lincoln, Edgewood and Eden avenues.
Who: Parsons Inc. and their sub-consultants, Badger Daylighting and J.D. Barnes Limited, will coordinate the work for the City of Ottawa.
On-street parking
As the various road reconstruction activities are in progress on your street, on-street parking may be restricted. In the event that access to your driveway will be impacted, you will receive 24-hours’ notice and provided with a Temporary On-Street Parking Permit (orange form) to permit on-street parking within two blocks of your residence. Residents with electric vehicles will need to find alternative charging arrangements when access is restricted. The use of extension cords within the public right of way is not permitted. Should you have additional concerns about reduced access, such as business deliveries or accessibility requirements, please contact the project manager.
Field investigations (March 2024)
Beginning in April, the City of Ottawa will undertake a subsurface utility engineering (SUE) mapping, geotechnical, hydrogeological and environmental investigations in your neighbourhood. This work is being completed to determine the underground utility, soil and groundwater conditions to support the design of the road, watermain and sewer replacement on: Athlone Avenue (Scott Street to Byron Avenue); Edgewood Avenue (Lincoln Avenue to Richmond Road); Lincoln Avenue (Churchill Avenue N to Edgewood Avenue); and Eden Avenue (Lincoln Avenue to Richmond Road).
The purpose of this project is to renew aging underground infrastructure and reconstruct the roads and sidewalks. An invitation to an initial public consultation will be delivered later in 2024. At that meeting, we will present the preliminary design to the community and obtain feedback. The construction of the project is tentatively scheduled for 2025, subject to funding availability.
What: The work will involve using electromagnetic techniques to determine the existence and approximate horizontal position of subsurface utilities, the drilling of boreholes and obtaining soil and water samples for testing. The investigations will be done by workers and equipment, as needed. On-street parking will be temporarily removed during working hours.
Why: This work is needed to support the design of the road, watermain and sewer reconstruction.
When: The field investigation work will commence in mid-April 2024 and could take up to five (5) weeks. The work will be conducted between the hours of 8 am and 5 pm, Monday to Friday.
Where:
- Athlone Avenue (Scott Street to Byron Avenue)
- Edgewood Avenue (Lincoln Avenue to Richmond Road)
- Lincoln Avenue (Churchill Avenue N to Edgewood Avenue)
- Eden Avenue (Lincoln Avenue to Richmond Road).
Who: Parsons Inc. and their sub-consultants, T2 Utility Engineers Inc. and Thurber Engineering Ltd., will coordinate the work for the City of Ottawa.
On-street parking
As the various road reconstruction activities are in progress on your street, on-street parking may be restricted. In the event that access to your driveway will be impacted, you will receive 24-hours’ notice and provided with a Temporary On-Street Parking Permit (orange form) to permit on-street parking within two blocks of your residence. Residents with electric vehicles will need to find alternative charging arrangements when access is restricted. The use of extension cords within the public right of way is not permitted. Should you have additional concerns about reduced access, such as business deliveries or accessibility requirements, please contact the project manager.