Project status
Planned

Project overview

Project description

The overall objective of this project is to replace approximately 90m of the old 305mm watermain on Industrial Avenue due to condition resulting in frequent breaks. Approximately 55m of the 406mm watermain on St-Laurent Boulevard at the intersection will also be replaced due to condition.

These replacements will connect to the new Industrial Avenue watermain west of this location which was replaced in 2016.

Project timing

Design: winter/spring 2024
Construction start: summer 2024
Construction completion: fall 2024

Project budget

Approved project funds to date are $1.894 million.

Accessibility

Accessibility is an important consideration for the City of Ottawa. The City makes every effort to provide access through and around construction sites. If you require a disability-related accommodation, please contact the project team listed below. Accessible formats and communication supports are available, upon request.

Safety

The City of Ottawa is committed to safety in and around project sites. The project team continues to work closely with the industry and to comply with recommendations provided by municipal, provincial and federal health officials, as well as the Ministry of Labour, Immigration, Training and Skills Development.

Contact information

Should you have any inquiries, please do not hesitate to contact:

Stacey Hogan (Rathwell), CET, CAPM
Project Manager
Infrastructure Services
Design & Construction – Municipal
Cell: 613-915-0424