Automated speed enforcement devices: multiple locations
In July 2024, the City of Ottawa will be commencing construction to support the installation of Automated Speed Enforcement (ASE) cameras as part of the City’s Road Safety Action Plan.
What: The contractor will be performing work within the right of way, which includes:
- Removal of asphalt, sidewalk, and excavation locally to install buried electrical conduit;
- Excavation and installation of electrical chambers;
- Installation of an electrical disconnect foundation (as required);
- Reinstatement of all roadways, sidewalks, and boulevards to existing condition. Boulevards impacted to have topsoil and seed applied.
A separate contractor will be responsible for installing the ASE equipment including the foundation, mounting hardware and camera unit. This work will occur after underground work is completed.
A Hydro One/Hydro Ottawa approved contractor will be completing work to connect to the transformer as required.
The City’s Traffic Operations staff will install electrical disconnect cabinets and cable.
Why: This work is being done to support the installation of Automated Speed Enforcement cameras within community safety zones, generally near schools or other locations with vulnerable road users to reduce speeding and improve safety.
Where: There are a total of 20 ASE cameras being installed as part of this project in 2024.
The duration for the following locations is expected to be less than one week:
- Castlefrank Road: on the west side of Castlefrank Road between Kakulu Road and Hungerford Gate. Work includes installing buried conduit from a hydro transformer along the Stonegate Park pathway and a new electrical disconnect foundation out to the boulevard of Castlefrank Road between the sidewalk and road.
- Colonial Road in front of Heritage Public School. Work will include excavation and reinstatement to install electrical infrastructure on the south side of Colonial Road on the school frontage. As the various activities are in progress, on-street parking may be restricted. Access to the school will be maintained.
- Crichton Street between Vaughan Street and Beechwood Avenue. Work will be limited to a small area on the east side of Crichton Street near the bus stop, connecting to a hydro pole and involve some minor sidewalk and road reinstatement.
- Kitchener Avenue between Cochrane Street and Jasper Avenue, on the south side of the road in front of the Clifford Bowey Public School parking lot. Work will also include installing buried traffic conduit from a hydro pole on the north side of Kitchener Avenue and crossing the road.
- Knoxdale Road: the north side of Knoxdale Road between Skipton Road and Cremona Crescent, in front of 159 Knoxdale Road. Work will include installation of buried conduit from a hydro pole on the south side of Knoxdale Road and under the road.
- Longfields Drive: on the east side of Longfields Drive between Clearbrook Drive and Strandherd Drive in front of École Secondaire Catholique Pierre-Savard.
- Ottawa Street: the south side of Ottawa Street across from South Carleton High School. Work will include installation of buried conduit on the south side of the road connecting to a hydro pole.
- Prince of Wales Drive: the east side of Prince of Wales Drive across the street from Carleton Heights Public School. Work will include installation of buried electrical conduit from a hydro pole on the west side of the road and crossing the road.
- Terry Fox Drive: on the north side of Terry Fox Drive, approximately 100 metres west of Old Second Line Road.
- Walkley Road: the north side of Walkley Road between Colliston Crescent and Albion Road / Colliston Crescent. Work will include installation of buried conduit in the boulevard and require minor sidewalk reinstatement.
The duration for the following locations is expected to be approximately one week:
- Cassidy Road in front of Bell High School. Work will be along the shoulders of Cassidy Road from Bruin Road for about 50 metres to the north and going across the roadway. As the various activities are in progress, on-street parking may be restricted in the area of Bell High School. The construction is within the City’s right of way and will be limited to work within the roadway and shoulders of Cassidy Road.
- Gardenway Drive: the north side of Gardenway Drive in front of St. Clare School. Work will include installation of buried conduit in the north boulevard in front of the school, across the roadway to a hydro transformer situated in front of 2128 and 2130 Gardenway Drive, and installation of an electrical post-mounted disconnect in front of the hydro transformer.
- Main Street: the west side of Main Street between Springhurst Avenue and Evelyn Avenue. Work will include installation of buried conduit for a distance of 20 metres on the west side of the road. The west sidewalk will be temporarily closed and the southbound cycle track will be temporarily routed onto the roadway and protected.
- Merivale Road: the west side of Merivale Road in front of St. Monica School. Work will include installation of buried electrical conduit under the east shoulder of Merivale Road from Brookdale Avenue to MacFarlane Road, and under the west boulevard of Merivale Road in front of the school.
- Ogilvie Road: the west side of Ogilvie Road in front of the Beacon Learning Centre (between Kender Avenue and La Vérendrye Drive). Work will include installation of buried electrical conduit in the west boulevard of Ogilvie Road in front of the Beacon Learning Centre and along the southern edge of the learning centre property to a hydro transformer.
- Old Richmond Road: the west side of Old Richmond Road between Our Lady of Peace School and St. Martin de Porres Church. Work will include upgrading the electrical disconnect cabinet at the pedestrian signal and installing conduit under the sidewalk from the signal to approximately 30 metres south of the signal. The sidewalk on the west side of the road may be temporarily closed during construction and reinstated.
- Stittsville Main Street: the west side of Stittsville Main Street in front of 1346/1354 Stittsville Main Street (Levante Stittsville Villa Retirement Residence). Work will include installation of buried electrical conduit under the boulevard on both sides of the road and crossing the road in front of the retirement residence and Holy Spirit Catholic School.
- Stoneway Drive: the south side of Stoneway Drive in front of Adrienne Clarkson Elementary School (in front of the bus loop near Forest Gate Way). Work will include installation of buried conduit along the south side of the road, crossing the bus loop driveway and crossing Stoneway Drive to a new electrical disconnect cabinet in front of 155 and 157 Stoneway Drive.
The duration for the following location is expected to be five days:
- Bridge Street in front of Manotick Public School. Work will take place on the north and south sides of Bridge Street between Arthur Crescent and West River Drive / Arthur Crescent and crossing underneath the roadway.
The duration for the following location is expected to be between one and two weeks:
- Queen Mary Street: the north side of Queen Mary Street between Edith Avenue and Quill Street. Work will include installation of buried conduit from a hydro pole at the south-east quadrant of Queen Mary Street and Edith Avenue, and under the roadway at the intersection. Local accessibility improvements will also be completed at the intersection.
When: Construction is planned to begin in July and be completed by mid-October 2024. The contractor will be using this duration to complete all 20 sites.
Who: The City of Ottawa has retained the contractor, TJL Construction Ltd., to complete the work.
Traffic management
To accommodate the proposed construction, there may be lane closures and localized disruption to traffic. Access to private properties, in addition to pedestrian and cycling access, will be maintained throughout the construction period.
On-street parking and local access
As the various activities are in progress, on-street parking may be restricted. Local access will be maintained to residents, business owners and emergency vehicles. Vehicular access to your property may be unavailable; the contractor is required to provide 24-hour notification of temporary loss of vehicular access/egress to your property. Access will be reinstated at the end of the work day, and if required to access or egress during the day, the contractor will provide steel plates to accommodate.
Should you have additional concerns about reduced access, such as business deliveries or accessibility requirements, please contact the project manager listed below.
Impact on the right of way and adjacent private properties
The construction is within the City’s right of way but may result in some disruption to part of the private property directly adjacent to the work. The City will reinstate sections of landscaping, driveways and walkways that are disturbed by construction.
Lawn irrigation systems
If you own a subsurface lawn irrigation system, please notify the City Project Manager identified below.
Construction disruptions
The contractor will take every precaution to minimize interruptions to the everyday life of your family and/or operation of your business, but, as you can appreciate, there may be some inconvenience during the course of the work, such as traffic delays, noise and dust. You may also feel vibrations due to heavy equipment operations. Vibrations from construction activities are quite common and rarely cause any problems. We would like to thank you for your patience and co-operation. For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255).
Contact information
For any emergency outside normal working hours, please call the City at 3-1-1.
For general project information, please contact the City’s Project Manager.
For construction related questions or concerns, please contact the Contractor Representatives.
City Project Manager
Jonathan Pach, P.Eng.
Senior Engineer, Infrastructure Projects
100 Constellation Drive, Ottawa, ON K2G 6J8
Tel.: 613-580-2424, ext. 23188
Contract Administrator
Matthew Julian
Contract Administrator, WSP
Tel: 613-790-5133
City On-Site Representatives
Pierrick Fokou Zotegouon
Site Inspector, WSP
Tel: 613-240-4659
Idrees Hassan
Site Inspector, WSP
Tel: 343-998-6154
Contractor Representatives
Toby Racine, P.Eng.
Project Manager, TJL Construction Ltd.
Tel: 819-334-4764
Patrick Lamarche, P.Eng.
Site Superintendent, TJL Construction Ltd.
Tel : 613-614-0340
Renewal of Snake Island Road Bridge Culvert
This notice is to advise that construction in your neighbourhood will be undertaken in late summer / early fall of 2024. This work is being conducted to complete the replacement of one bridge culvert to help improve your roadways and maintain surface drainage in your community.
What: Work will involve the removal and replacement of the existing culvert.
Why: The City of Ottawa will be undertaking these repairs as part of a programmed end-of-service-life replacement project.
When: The culvert will be replaced approximately between mid-September and mid-October 2024.
Where: The culvert is located on Snake Island Road at Doyle Creek Municipal Drain, 0.35 km east of Nixon Drive.
Who: The City of Ottawa has retained the contractor, W.H. MacSweyn Inc., to complete the work.
Traffic impacts
To safely complete this work a five-week road closure is required. A signed detour route will be provided.
The affected roads will have information and construction signs installed and maintained throughout the construction sites for the duration of the replacements to keep you informed of the changing conditions. Significant effort is being made to reduce the duration of the construction impacts in your community. Access to local businesses and private properties will be maintained throughout the construction period.
Construction disruptions
The contractor will take every precaution to minimize interruptions to the everyday life of your family and/or operation of your business, but as you can appreciate, there may be some inconvenience during the course of the construction work, such as delays and traffic detours, parking restrictions, noise and dust. You may also feel vibrations due to heavy equipment operations. Vibrations from construction activities are quite common and rarely cause any problems. We would like to thank you for your patience and co-operation. For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255).
Contact information
For any emergency outside normal working hours, please call the City at 3-1-1.
For general project information, please contact the City’s Project Manager.
For construction related questions or concerns, please contact the City On-Site Inspector.
City Project Manager
Carolyn Newcombe, P.Eng.
City of Ottawa
Design and Construction – Municipal
Tel: 613-580-2424, ext. 28230
City On-Site Inspector
Paul Nicol
City of Ottawa
100 Constellation Drive, Ottawa, ON K2G 6J8
Tel: 613-851-1258
Contractor Project Manager
Blair MacSweyn
W.H. MacSweyn Inc.
453 Gladstone Street, Winchester, ON K0C 2K0
Tel: 613-407-4694
Contract Administrator
Joshua Georg, P.Eng.
Egis Canada Ltd.
115 Walgreen Rd, RR3, Carp ON K0A 1L0
Tel: 613-903-4992
2023 Sidewalks and Pathways – Johnwoods Street
Beginning in late August / early September, the City of Ottawa will begin construction along Johnwoods Street to improve existing pedestrian and cycling connectivity conditions as well as overall street improvements in your neighbourhood.
What:
- A new 3.0m wide multi-use pathway will be implemented from Kinalea Crescent to Rosehill Avenue along the north and west side of Alon Street and Johnwoods Street, respectively.
- A new 2.0m wide paved shoulder on the east side of Johnwoods Street from Rosehill Avenue Alon Street.
- Improvements to crosswalk and sidewalk corners at the Johnwoods and Alon streets intersection.
- Various ditching realignments.
Why: To improve cycling connectivity and pedestrian traversing conditions within the neighbourhood.
When: Construction is expected to begin in mid to late August / early September and be completed by late September / early October 2024.
Where: Johnwoods Street from Rosehill Avenue to Alon Street.
Alon Street from Kinalea Crescent to Johnwoods Street.
Who: The City of Ottawa has retained the contractor, Goldie Mohr Ltd., to complete the work.
Traffic management
To accommodate the proposed construction minor lane reductions and delays are expected during off peak hours. Sidewalk detours are anticipated to accommodate the construction.
Construction disruptions
The contractor will take every precaution to minimize interruptions to the everyday life of your family and/or operation of your business, but, as you can appreciate, there may be some inconvenience during the course of the work, such as traffic delays, noise and dust.
You may also feel vibrations due to heavy equipment operations. Vibrations from construction activities are quite common and rarely cause any problems. We would like to thank you for your patience and co-operation.
For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255).
Contact information
For any emergency outside normal working hours, please call the City at 3-1-1.
For general project information, please contact the City’s Project Manager.
For construction related questions or concerns, please contact the Contractor Representative.
City Project Manager
Nick Giamberardino, P.Eng.
Project Manager, Infrastructure and Water Services
100 Constellation Drive
Ottawa, ON K2G 6J8
Tel.: 613-299-5852
Construction Inspector
Mitchell Clarke, RCSI
Parsons
1223 Michael Street, Suite 100
Gloucester ON K1J 7T2
Tel: 613-691-1597
Contract Administrator
Jeremy Smith, BASc, P.Eng., ing.
Parsons
1223 Michael Street, Suite 100
Gloucester ON K1J 7T2
Tel: 613-295-0191
Contractor Representative
Mike Buch
Senior Project Manager
Goldie Mohr LTD.
3862 Moodie Drive, Richmond, ON K0A 2Z0
Tel.: 613-223-1984
2023 Sidewalk and Pathway – Manotick Main Street
Beginning in late August / early September, the City of Ottawa will start construction for sidewalk renewal along Manotick Main Street in your neighbourhood.
What: Sidewalk replacement consisting of a 2.0m wide monolithic concrete curb and sidewalk including the removal of existing pavers.
Why: To improve existing sidewalk conditions and bring the section up to City AODA Standards.
When: Construction is expected to begin in late August / early September and be completed by mid to late September 2024.
Where: Manotick Main Street, between O’Grady Street and Currier Street.
Who: The City of Ottawa has retained the contractor, Goldie Mohr LTD., to complete the work.
Traffic management
To accommodate the proposed construction minor lane reductions and delays are expected during off peak hours. Sidewalk detours are anticipated to accommodate the construction.
Construction disruptions
The contractor will take every precaution to minimize interruptions to the everyday life of your family and/or operation of your business, but, as you can appreciate, there may be some inconvenience during the course of the work, such as traffic delays, noise and dust. You may also feel vibrations due to heavy equipment operations. Vibrations from construction activities are quite common and rarely cause any problems. We would like to thank you for your patience and co-operation.
For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255).
Contact information
For any emergency outside normal working hours, please call the City at 3-1-1.
For general project information, please contact the City’s Project Manager.
For construction related questions or concerns, please contact the Contractor Representative.
City Project Manager
Nick Giamberardino, P.Eng.
Project Manager, Infrastructure and Water Services
100 Constellation Drive
Ottawa, ON K2G 6J8
Tel.: 613-299-5852
Construction Inspector
Mitchell Clarke, RCSI
Parsons
1223 Michael Street, Suite 100
Gloucester ON K1J 7T2
Tel: 613-691-1597
Contract Administrator
Jeremy Smith, BASc, P.Eng., ing.
Parsons
1223 Michael Street, Suite 100
Gloucester ON K1J 7T2
Tel: 613-295-0191
Contractor Representative
Mike Buch
Senior Project Manager
Goldie Mohr LTD.
3862 Moodie Drive, Richmond, ON K0A 2Z0
Tel.: 613-223-1984
Resurfacing: Bilberry Drive
The City of Ottawa’s road resurfacing program rehabilitates and improves the driving surfaces of Ottawa’s roadways. Localized repairs to both curbs and sidewalks, along with accessibility improvements and updates, are also part of the program.
As part of the City of Ottawa’s annual infrastructure maintenance cycle, road resurfacing will occur along Bilberry Drive to improve this roadway and the overall citywide transportation network.
What: Work will involve milling, granular A placement, iron adjustments and paving of base and surface asphalt. Increased noise levels and vibrations to be expected to facilitate the work.
Why: The City of Ottawa will be resurfacing roads as preventative maintenance aimed at extending the City's roadway network lifecycle.
When: This work is scheduled to start early September and completion is anticipated by September 30, 2024. Work will take place between the hours 7 am and 10 pm. Some operations, such as milling, and paving may take place at night between the hours of 10 pm and 7 am. Bilberry Drive will remain open to traffic with lane closures expected.
Where: Work will occur along Bilberry Drive from du Bois Avenue (west) to Jeanne d’Arc Boulevard North.
Who: The City of Ottawa has retained the contractor, GIP Paving Inc., to resurface Bilberry Drive.
We encourage residents to contact the undersigned to identify and confirm that private irrigations systems have been disconnected or relocated. Damage may occur, should you choose not to relocate prior to our arrival.
The contractor has been made aware that adjacent streets are private property and the streets are not to be used for construction related activities and/or parking of equipment.
Impact on the right of way and adjacent private properties
The reconstruction is within the City’s right of way but may result in some disruption to part of the private property directly adjacent to the work. The City of Ottawa will reinstate all sections of landscaping, driveways and walkways that are disturbed by construction. However, if you have plants or any other assets located within the City’s right of way that you want to preserve, we suggest that you may want to move them in preparation for the construction work.
On-street parking
As the various road reconstruction activities are in progress on your street, on-street parking may be restricted. In the event that access to your driveway will be impacted, you will receive 24-hours’ notice and provided with a Temporary On-Street Parking Permit (orange form) to permit on-street parking within two blocks of your residence. Residents with electric vehicles will need to find alternative charging arrangements when access is restricted. The use of extension cords within the public right of way is not permitted.
Should you have additional concerns about reduced access, such as business deliveries or accessibility requirements, please contact the project manager listed below.
Traffic management
To accommodate the proposed construction, various lane reductions, alternating traffic and/or detours can be expected. Access to local businesses and private properties will be maintained throughout the construction period. Access for pedestrians and cyclists will be maintained.
Construction disruptions
The contractor will take every precaution to minimize interruptions to the normal life of your family and/or operation of your business, but as you can appreciate, there may be some inconvenience during construction. We would like to thank you in advance for your patience and co-operation. For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255).
Contact information
For any emergency outside normal working hours on weekdays and weekends, please call the City at 3-1-1. For further information about this project, please contact the City’s Project Manager.
City Project Manager
Guy Lavallee, C.E.T.
Project Manager, Road Rehabilitation
Infrastructure and Water Services
Tel: 613-291-9249
Contractor Representative
Warren Perry
Project Manager
GIP Paving Inc.
Tel: 343-988-8131
2024 Automated speed enforcement cameras: Bridge Street night work (September 9 to 13)
The City of Ottawa will be undertaking night work related to the 2024 Automated Speed Enforcement Cameras project.
What: Night work will involve excavation, electrical conduit installation and reinstatement including in the sidewalks and roadway, all within the City’s right of way.
Why: Night work is required to minimize traffic disruptions.
When: Night work is expected overnight from September 9 to September 13. Please note that this work is weather dependent and additional nights may be required to complete the work.
Where: The work will be located on Bridge Street in front of Manotick Public School (between West River Drive / Arthur Crescent and Arthur Crescent) on both sides of the road.
Who: The City of Ottawa has retained TJL Construction Limited to complete the work.
Lane reductions
Bridge Street will be reduced to a single lane for the duration of this work with alternating traffic.
Construction disruptions
The contractor will take every precaution to minimize interruptions to the normal life of your family and/or operation of your business, but as you can appreciate, there may be some inconvenience during construction. We would like to thank you in advance for your patience and co-operation. For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255). A noise by-law exemption will be in place for this work.
Contact information
For any emergency outside normal working hours on weekdays and weekends, please call the City at 3-1-1. For further information about this project, please contact the City’s Project Manager.
City Project Manager
Jonathan Pach, P.Eng.
Senior Engineer, Infrastructure Projects
100 Constellation Drive, Ottawa, ON K2G 6J8
Tel.: 613-580-2424, ext. 23188
Contract Administrator
Matthew Julian
Contract Administrator, WSP
Tel.: 613-790-5133
City On-Site Representatives
Pierrick Fokou Zotegouon
Site Inspector, WSP
Tel.: 613-240-4659
Idrees Hassan
Site Inspector, WSP
Tel.: 343-998-6154
Contractor Representatives
Toby Racine, P.Eng.
Project Manager, TJL Construction Ltd.
Tel.: 819-334-4764
Patrick Lamarche, P.Eng.
Site Superintendent, TJL Construction Ltd.
Tel.: 613-614-0340
Belfast Road and Trainyards Drive intersection and sidewalk improvements
Starting in June 2025, the City of Ottawa will begin construction of intersection improvements at Belfast Road and Trainyards Drive and sidewalk segments on Belfast Road. Construction is anticipated to be completed by September 2025.
The scope of work for this project is as follows:
- Intersection upgrades at Belfast Road and Trainyards Drive including a bidirectional crossride across the south leg of Trainyards Drive, extension of the eastbound right turn lane from Belfast Road to Trainyards Drive, and pavement marking modifications.
- Addition of approximately 40 metres of sidewalk along the north side of Belfast Road from 805 Belfast Road to 869 Belfast Road with new curb and boulevard separation.
- Addition of approximately 115 metres of sidewalk along the north side of Belfast Road from the property line between 899/925 Belfast Road to 1500 St. Laurent Boulevard with new curb and boulevard separation.
Construction disruptions
The contractor will take every precaution to minimize interruptions but as you can appreciate, there may be some inconvenience during construction. Please be advised that for the duration of construction, access to your business will be maintained. Significant effort is being made to reduce the duration of the construction impacts in your area. We would like to thank you for your patience and co-operation.
Contact information
Should you have any concerns or would like additional information, please reach out to the City Project Manager:
Andrew Krisciunas, P.Eng.
Senior Engineer, Infrastructure Projects
City of Ottawa, Infrastructure and Water Services
Design and Construction – Municipal
100 Constellation Drive, Ottawa, ON K2G 6J8
Tel: 613-580-2424, ext. 44232
Sewer lining program (Wards 2, 7, 8, 15 & 23)
Beginning in the fall of 2024, the City will begin preparation work for sewer rehabilitation in your area. The City will be using a trenchless technology called Non-Styrene Cured In Place Pipe to minimize the impact of construction.
What: The preparation work will involve cleaning and inspection of the sewer. The contractor will return at a later date to perform sewer rehabilitation using a Non-Styrene Cured in Place Pipe (CIPP) lining process. CIPP rehabilitation minimizes the impact of construction by repairing the existing sewer without having to dig. The CIPP method of construction is less disruptive and can be completed quicker than traditional construction techniques.
Why: Sewer rehabilitation is required due to the age and condition of the existing infrastructure.
When: Sewer cleaning and inspection work in preparation for rehabilitation is expected to begin in September. The preparation work is expected to take between one and three days to complete on each street. Please note this work is weather dependent. A subsequent notification letter will be distributed to your residence or business in advance of the start of sewer liner installation to provide further details.
Where:
Ward 2
- West side of Stoneboat Crescent between Lumberway Way and 100m north of Lumberman Way.
Ward 7
- Cedar Lane Terrace between Melwood Avenue and Maplecrest Avenue, as well as on Maplecrest Avenue at Cedar Lane Terrace.
Ward 8
- Elmira Drive between Cobden Road and Lambeth Walk.
- North side of Barnes Crescent from Harrison Street to 250 metres west of Harrison Street.
Ward 15
-
Parkdale Avenue from Burnside Avenue to Lyndale Avenue. To accommodate the proposed construction, lane reductions and/or alternating traffic can be expected after 6 pm.
Ward 23
- Coburn Avenue from Carbrooke Street to 100 metres west of Carbrooke Street.
Who: The City of Ottawa has retained the contractor, Clearwater Structures Inc., to complete the work.
What is Non-Styrene Cured in Place Pipe (CIPP)?
Non-Styrene Cured in place pipe (CIPP) is a sewer lining process where a styrene-free resin (glue like plastic) in a saturated tube is inserted into an existing pipe and inflated to take the shape of the existing pipe. Heat is then added to the inflated tube to cure (harden) the resin using hot water or steam. Once the resin has cured, a new seamless pipe has been installed in the sewer. The final step in the process is to cut holes in the newly installed CIPP liner to allow for flow from connected laterals to flow into the sewer. The use of styrene-free resin mitigates the odours emitted by standard styrenated resin during construction.
Traffic management
To accommodate the proposed construction, lane reductions and/or alternating traffic can be expected. Access to local businesses and private properties will be maintained throughout the construction period. Access for pedestrians and cyclists will be maintained.
On-street parking and local access
On-street parking restrictions will be needed to facilitate the work. Local access will be maintained to residents, business owners and emergency vehicles. In the event that access to your driveway will be impacted, you will receive 24-hours’ notice and be provided with a Temporary On-Street Parking Permit (orange form) to permit on-street parking within two blocks of your residence. Residents with electric vehicles will need to find alternative charging arrangements when access is restricted. The use of extension cords within the public right of way is not permitted.
Should you have additional concerns about reduced access, such as business deliveries or accessibility requirements, please contact the project manager listed below.
Construction disruptions
The contractor will take every precaution to minimize interruptions to the normal life of your family and/or operation of your business, but as you can appreciate, there may be some inconvenience during construction, such as traffic delays, parking restrictions, and noise. We would like to thank you in advance for your patience and co-operation. For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255).
Contact information
For any emergency outside normal working hours, please call the City at 3-1-1.
For further information about this project, please contact the City’s Project Manager.
City Project Manager
Christine Reist, P.Eng.
Senior Engineer, Infrastructure Projects
Tel: 613-580-2424, ext. 27820
Contract Administrator
Mathew Ojoleck, P.Eng.
Morrison Hershfield, now Stantec
Tel: 613-859-6547
Contractor Representative
Kyle Peori, C.E.T.
Project Manager
Clearwater Structures Inc
Tel.: 365-885-1526
Sewer lining program (Wards 16 and 17)
Beginning in the fall of 2024, the City will begin preparation work for sewer rehabilitation in your area. The City will be using a trenchless technology called PVC Fold and Form pipe lining to minimize the impact of construction.
What: The preparation work will involve cleaning and inspection of the sewer. The contractor will return at a later date to perform sewer rehabilitation using a PVC Fold and Form pipe lining process. Rehabilitation using PVC Fold and Form pipe liners minimizes the impact of construction by repairing the existing sewer without having to dig. The PVC Fold and Form pipe lining method of construction is less disruptive and can be completed quicker than traditional construction techniques.
Why: Sewer rehabilitation is required due to the age and condition of the existing infrastructure.
When: Sewer cleaning and inspection work in preparation for rehabilitation is expected to begin in September. The preparation work is expected to take between one and three days to complete on each street. Please note this work is weather dependent. A subsequent notification letter will be distributed to your residence or business in advance of the start of sewer liner installation to provide further details.
Where:
Ward 16
- Anna Avenue from Admiral Avenue to 120 metres west of Admiral Avenue. Pedestrian detours can be expected.
Ward 17
- Clover Street between Brookfield Road East and Gregg Street.
- Kaladar Avenue between Brookfield Road East and Dartmouth Avenue.
Who: The City of Ottawa has retained the contractor, Clearwater Structures Inc., to complete the work.
What is PVC Fold and Form Pipe Lining?
PVC Fold & Form pipe lining is a sewer lining process where a folded PVC liner is inserted into an existing pipe and then formed to the shape of the existing pipe using heat. Once the liner has cooled, a new seamless pipe has been installed in the sewer. The final step in the process is to cut holes in the newly installed liner to allow for flow from connected laterals to flow into the sewer.
Traffic management
To accommodate the proposed construction, lane reductions and/or alternating traffic can be expected. Access to local businesses and private properties will be maintained throughout the construction period. Access for pedestrians and cyclists will be maintained.
On-street parking and local access
On-street parking restrictions will be needed to facilitate the work. Local access will be maintained to residents, business owners and emergency vehicles. In the event that access to your driveway will be impacted, you will receive 24-hours’ notice and be provided with a Temporary On-Street Parking Permit (orange form) to permit on-street parking within two blocks of your residence. Residents with electric vehicles will need to find alternative charging arrangements when access is restricted. The use of extension cords within the public right of way is not permitted.
Should you have additional concerns about reduced access, such as business deliveries or accessibility requirements, please contact the project manager listed below.
Construction disruptions
The contractor will take every precaution to minimize interruptions to the normal life of your family and/or operation of your business, but as you can appreciate, there may be some inconvenience during construction, such as traffic delays, parking restrictions, and noise. We would like to thank you in advance for your patience and co-operation. For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255).
Contact information
For any emergency outside normal working hours, please call the City at 3-1-1.
For further information about this project, please contact the City’s Project Manager.
City Project Manager
Christine Reist, P.Eng.
Senior Engineer, Infrastructure Projects
Tel: 613-580-2424, ext. 27820
Contract Administrator
Mathew Ojoleck, P.Eng.
Morrison Hershfield, now Stantec
Tel: 613-859-6547
Contractor Representative
Kyle Peori, C.E.T.
Project Manager
Clearwater Structures Inc
Tel.: 365-885-1526
2023 Pipe repairs: road closure (Monteith Street and Goren Avenue)
This notice is to advise that construction in your neighborhood will be undertaken from September 23 to September 27, 2024. This work is being conducted to complete the replacement of approximately 10 meters of storm sewer infrastructure. As part of the work, a road closure is required.
What: Monteith Street and Goren Avenue will be closed with only local traffic being authorized to use the roadway. The intersection of Monteith Street and Goren Avenue will be inaccessible for the duration of the work.
Why: To facilitate the replacement of the storm sewer at the intersection of Monteith Street and Goren Avenue.
When: This work is planned to be completed from September 23 to September 27, 2024.
Where: Construction activity can be expected within the intersection of Monteith Street and Goren Avenue to facilitate the storm sewer repair. However, the whole length of Monteith Street and Goren Avenue will be close to all but local traffic.
Who: The City of Ottawa has retained the contractor, KCE Construction Ltd., to complete the work.
Traffic management
The intersection of Monteith Street and Goren Avenue will be fully closed to complete the construction. The full length of Monteith Street and Goren Avenue will also be closed to all but local traffic for the duration of the work.
Parking
On-street parking will be prohibited within the construction zone. Signs will be placed a minimum of 24 hours in advance indicating the parking prohibition. Vehicles parked at these locations may be towed at the owner’s expenses. Parking fines may also apply. In the event access to your driveway is temporarily restricted due to construction activities, the City’s inspector will provide you with a temporary On-Street Parking Permit (orange form) to authorize on-street parking within a few blocks of your residence.
Construction disruptions
KCE Construction Ltd. will take every precaution to minimize interruptions to the normal life of your family and/or operation of your business, but as you can appreciate, there may be some inconvenience during the operation of the work. We would like to thank you in advance for your patience and co-operation. For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255).
Contact information
For any emergency outside normal working hours on weekdays and weekends, please call the City at 3-1-1. Should you have any questions or concerns, please to contact the Project Team:
City Project Manager
Will Ball, P.Eng.
City of Ottawa - Design and Construction - Municipal
Tel: 343-996-3663
Contract Administrator
Anmar Al-Faraj, P.Eng.
Ainley Group
Tel: 902-210-3305
On-Site Representative
Connor Kennedy
Inspector
Ainley Group
Tel.: 613-847-7839
Contractor Representative
Rocky Galla
Project Manager
KCE Construction Ltd.
Tel.: 613-223-6232
2022 Pipe repairs: road closure (Archibald Street, south of Carling Avenue)
This notice is to advise that construction in your neighborhood will be undertaken on September 30, 2024. This work is being conducted to complete the replacement of approximately 6 metres of sanitary sewer infrastructure.
What: Archibald Street will be closed for a few days to all but local traffic and will be blocked entirely from the Carling Avenue end. The temporary barriers which are currently on Archibald Street will be temporarily moved during construction to allow access from Thames Street. The barriers will be reinstated after the construction works are complete.
Why: To facilitate the repair of the sanitary sewer at the north end of Archibald Street.
When: The work is planned to start on September 30 and will be completed on October 2, 2024.
Where: Construction activity can be expected on Archibald Street, south of Carling Avenue, to facilitate the sanitary sewer repair. The whole of Archibald Street will be closed to all but local traffic with access being fully blocked at Carling Avenue.
Who: The City of Ottawa has retained the contractor, Robert Excavating, to complete the work.
Traffic management
Residents can expect construction traffic and activity within the City’s right of way. Archibald Street will be closed at the intersection with Carling Avenue. During the closure, local access will be permitted from Thames Street. Pedestrian and cyclist access will not be impacted.
Parking
On-street parking will be prohibited within the construction zone. Signs will be placed a minimum of 24 hours in advance indicating the parking prohibition. Vehicles parked at these locations may be towed at the owner’s expenses. Parking fines may also apply. In the event access to your driveway is temporarily restricted due to construction activities, the City’s inspector will provide you with a temporary On-Street Parking Permit (orange form) to authorize on-street parking within a few blocks of your residence.
Construction disruptions
Robert Excavating will take every precaution to minimize interruptions to the normal life of your family and/or operation of your business, but as you can appreciate, there may be some inconvenience during the operation of the work. We would like to thank you in advance for your patience and co-operation. For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255).
Contact information
For any emergency outside normal working hours on weekdays and weekends, please call the City at 3-1-1. Should you have any questions or concerns, please to contact the Project Team:
City Project Manager
Will Ball, P.Eng.
City of Ottawa - Design and Construction - Municipal
Tel: 343-996-3663
Contract Administrator
Ahmad Almufleh, P.Eng.
Morrison Hershfield
Tel: 613-608-7530
On-Site Representative
Pierre Dion
Inspector
Morrison Hershfield
Tel.: 613-875-5235
Contractor Representatives
Gary Beisheim
Project Manager
Robert Excavating
Tel.: 613-229-4468
2022 Pipe repairs: road closure (Croft Street, south of Grandeur Avenue)
This notice is to advise that construction in your neighborhood will be undertaken from September 25 to October 2, 2024. This work is being conducted to complete the replacement of approximately 3 metres of sanitary sewer infrastructure. As part of the work, a road closure is required.
What: Croft Street will be closed with only local traffic being authorized to use the roadway.
Why: To facilitate the replacement of the sanitary sewer at the north end of Croft Street.
When: This work is planned to be completed from September 25 to October 2, 2024.
Where: Construction activity can be expected at the north end of Croft Street. However, the whole length of Croft Street will be closed to all but local traffic.
Who: The City of Ottawa has retained the contractor, Robert Excavation, to complete the work.
Traffic management
The north end of Croft Street will be fully closed to complete the construction. The full length of Croft Street will also be closed to all but local traffic for the duration of the work.
Parking
On-street parking will be prohibited within the construction zone. Signs will be placed a minimum of 24 hours in advance indicating the parking prohibition. Vehicles parked at these locations may be towed at the owner’s expenses. Parking fines may also apply. In the event access to your driveway is temporarily restricted due to construction activities, the City’s inspector will provide you with a temporary On-Street Parking Permit (orange form) to authorize on-street parking within a few blocks of your residence.
Construction disruptions
Robert Excavation will take every precaution to minimize interruptions to the normal life of your family and/or operation of your business, but as you can appreciate, there may be some inconvenience during the operation of the work. We would like to thank you in advance for your patience and co-operation. For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255).
Contact information
For any emergency outside normal working hours on weekdays and weekends, please call the City at 3-1-1. Should you have any questions or concerns, please to contact the Project Team:
City Project Manager
Will Ball, P.Eng.
City of Ottawa - Design and Construction - Municipal
Tel: 343-996-3663
Contract Administrator
Ahmad Almufleh, P.Eng.
Morrison Hershfield
Tel: 613-608-7530
On-Site Representative
Pierre Dion
Inspector
Morrison Hershfield
Tel.: 613-875-5235
Contractor Representative
Gary Beisheim
Project Manager
Robert Excavating
Tel.: 613-229-4468
2022 Pipe repairs: road closure (Iris Street, east of Cobden Road)
This notice is to advise that construction in your neighborhood will be undertaken on September 26 and 27, 2024. This work is being conducted to complete the replacement of approximately 7 metres of sanitary sewer infrastructure.
What: Iris Street will be closed to all but local traffic from Cobden Road to Highgate Road. Buses will still be accommodated through this section.
Why: To facilitate the repair of the sanitary sewer near Cobden Road.
When: This work is planned to be completed on September 26 and 27, 2024.
Where: Iris Street will be closed from Cobden Road to Highgate road to all but local traffic and buses.
Who: The City of Ottawa has retained the contractor, Robert Excavating, to complete the work.
Traffic management
Residents can expect construction traffic and activity within the City’s right of way. The roadway section where work is being done (east of Cobden Road) will be closed to general traffic except for buses and cyclists. Please watch for flaggers and signage. Pedestrian access will not be impacted.
Parking
On-street parking will be prohibited within the construction zone. Signs will be placed a minimum of 24 hours in advance indicating the parking prohibition. Vehicles parked at these locations may be towed at the owner’s expenses. Parking fines may also apply. In the event access to your driveway is temporarily restricted due to construction activities, the City’s inspector will provide you with a temporary On-Street Parking Permit (orange form) to authorize on-street parking within a few blocks of your residence.
Construction disruptions
Robert Excavation will take every precaution to minimize interruptions to the normal life of your family and/or operation of your business, but as you can appreciate, there may be some inconvenience during the operation of the work. We would like to thank you in advance for your patience and co-operation. For construction activity hours of work, the City of Ottawa follows provincial requirements and the City’s Noise By-law (2017-255).
Contact information
For any emergency outside normal working hours on weekdays and weekends, please call the City at 3-1-1. Should you have any questions or concerns, please to contact the Project Team:
City Project Manager
Will Ball, P.Eng.
City of Ottawa - Design and Construction - Municipal
Tel: 343-996-3663
Contract Administrator
Ahmad Almufleh, P.Eng.
Morrison Hershfield
Tel: 613-608-7530
On-Site Representative
Pierre Dion
Inspector
Morrison Hershfield
Tel.: 613-875-5235
Contractor Representative
Gary Beisheim
Project Manager
Robert Excavating
Tel.: 613-229-4468